Nelson, Inc.

CourtArmed Services Board of Contract Appeals
DecidedDecember 15, 2015
DocketASBCA No. 57201, 58166
StatusPublished

This text of Nelson, Inc. (Nelson, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nelson, Inc., (asbca 2015).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) Nelson, Inc. ) ASBCA Nos. 57201, 58166 ) Under Contract No. W912EQ-09-C-0025 )

APPEARANCES FOR THE APPELLANT: Joree G. Brownlow, Esq. Cordova, TN

Dedrick Brittenum, Jr., Esq. Brittenum Bruce PLLC Memphis TN

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney Ann M. Bruck, Esq. Suzanne Mitchem, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Memphis

OPINION BY ADMINISTRATIVE JUDGE PEACOCK

These appeals involve the termination for default of the referenced contract for construction of stone dike extensions and other work at four sites on the Mississippi River. ASBCA No. 57201 is an appeal from the final decision terminating the contract. The Board conducted a nine-day hearing 1 in ASBCA No. 57201 regarding the propriety of the termination. We sustain the appeal. ASBCA No. 58166 involves a termination for convenience settlement proposal claim and appeal which we dismiss as premature.

FINDINGS OF FACT

1. On 31 July 2009, the U.S. Army Corps of Engineers (Corps or government) awarded the captioned contract to Nelson, Inc. (Nelson or appellant), for $9,241,900, for "Stone Dike Construction at Various Locations in the Mississippi River" (R4, tab 3 at 48, tab 14 at 369). In general, the contract provided for construction of stone dikes and other features at four Mississippi River sites, known as "Loosahatchie," "Robinson Crusoe," "Friars Point," and '"Cow Island" (R4, tab 3 at 41 ). The Loosahatchie work was located at Mississippi River Mile 738.7R AHP in Shelby County, Tennessee; the adjacent Robinson Crusoe work was located at Mississippi River Miles 738.7R AHP to 737.8R

1 The hearing was conducted by Administrative Judge Terrence S. Hartman. AHP in Shelby County, Tennessee; the Friars Point work was located at Mississippi River Miles 653.0L AHP to 652.7L AHP in Coahoma County, Mississippi; and the Cow Island work was located at Mississippi River Miles 715.2R AHP to 714.6R AHP, in Crittenden County, Arkansas (id.).

2. Following bid opening on 16 June 2009, the Corps conducted a pre-award survey to evaluate Nelson's capability to perform. Based on the results of that survey, the Corps concluded that appellant was non-responsible. (R4, tab 9 at 358) On 2 July 2009, the matter of appellant's responsibility was submitted to the U.S. Small Business Administration (SBA) where Nelson filed for a Certificate of Competency (COC) (R4, tabs 9, 10). On 22 July 2009, the SBA issued a COC (R4, tabs, 12, 13).

3. The Friars Point work and the Cow Island work were depicted on a separate set of contract drawings; the Loosahatchie and Robinson Crusoe work was depicted on one set of contract drawings (R4, tab 5 at 314-18 (Friars Point), at 320-25 (Loosahatchie & Robinson Crusoe), at 326-30 (Cow Island)). The adjacent Loosahatchie and Robinson Crusoe work were located approximately 1.5 miles upstream of Memphis, Tennessee. The contract included separate pricing for each activity related to each of the four sites (consisting of, but not at each site, mobilization/demobilization, graded stone, excavation, riprap paving, and standby time), which together totaled to the $9 ,241,900 lump sum amount for the entire contract. (R4, tab 3 at 48, 50-54) The Loosahatchie activities totaled $590,500; the Robinson Crusoe activities, $542,700; the Friars Point activities, $4,520,600; and the Cow Island activities, $3,578,100 (id.). To complete the work at all four locations required the placement of a total estimated quantity of 494,300 tons of stone (R4, tab 3 at 43-45).

4. Part 1.1.1 of the Summary of Work provided the following "Project Description" of the work (R4, tab 3 at 202):

FRIARS POINT CHEVRON CONTRACT: The work consists of furnishing all plant, labor and materials for constructing Friars Point Chevron Nos. 1 - 3 by placing Graded Stone A and Graded Stone Caswell as incidental related work.

LOOSAHATCHIE DIKE CONTRACT: The work consists of furnishing all plant, labor and materials for extending Loosahatchie Bar Dike No. 4 by placing Graded Stone C, and constructing Loosahatchie Bar Chevron No. 1 and Roundpoint Nos. 1 and 2 by placing Graded Stone C as well as incidental related work. No Riprap Paving will be placed.

2 ROBINSON CRUSOE DIKE CONTRACT: The work consists of furnishing all plant, labor and materials for extending Robinson Crusoe Dike Nos. 3, 4, and 5, and notching Robinson Crusoe Dike No. 5 as well as incidental related work. No riprap Paving will be placed.

COW ISLAND BENDWAY WEIR CONTRACT: The work consists of furnishing all plans, labor, and materials by constructing Cow Island Bendway Weir Nos. 1-6 by placing Graded Stone A as well as incidental related work. Riprap Paving will be placed on the bank at each weir location. [Emphasis added]

5. The contract included Federal Acquisition Regulation (FAR) clause 52.211-10, COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984), which provides (with revisions to accommodate the contract):

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 75 calendar days for Friars Point project, 20 calendar days for Loosahatchie project, 20 calendar days for Robinson Crusoe project, and 50 calendar days for Cow Island project after the date of receipt by him of notice to proceed. A separate Notice to Proceed will be issued for each location as specified in the Bid Schedule. [Underlining added]

(R4, tab 3 at 68)

6. The following pertinent "'CONSTRUCTION PROCEDURES" were set forth in section 35 31 25.00 11 of the specifications (R4, tab 3 at 267-69, 271-72):

PART 1 GENERAL

1.2 SCOPE

... The work shall be completed as expeditiously as possible even though river conditions may become increasingly severe as the construction progresses. The work requires steady and uninterrupted progress to

3 minimize loss of stone during construction. The Contractor shall diligently prosecute the work and provide the necessary equipment, a skilled and experienced crew, and a regular and well-balanced supply of stone to ensure uniform and continuous progress once construction of a chevron/dike/bendway weir has been started ....

1.3 RIVER STAGE LIMITATIONS

1.3 .1 River Stage Limitations for Dikes and Chevrons

Unless otherwise authorized by the Contracting Officer, subaqueous placement of stone will not be permitted when the river stage is more than 10 feet above the top elevation of that portion of the dike/chevron. Also, unless otherwise authorized or directed by the Contracting Officer, the top of the final lift of stone shall be placed in the dry whenever the dike/chevron is higher than +I 0 L WRP [2]and/or the crown width is 6 feet or more. Work will not be required on any dike/chevron when river stages are below 0 L WRP. Work will also not be required on a particular dike/chevron if a 6 foot continuous channel does not exist from the navigation channel to some work point on the dike/chevron where work is required.

1.3.2 River Stage Limitations for Bendway Weirs

Unless otherwise authorized by the Contracting Officer, subaqueous placement of stone will not be permitted on any weir when the river stages are above + 20 L WRP. Work will also not be required on any weir if a 6-foot continuous channel does not exist from the navigation channel to some work point on the weir where work is required.

2 L WRP stands for low water reference plane which is a tool used on the Mississippi River to establish navigation depths tied to certain gages on the river.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)
Spartan Aircraft Co. v. United States
100 F. Supp. 171 (Court of Claims, 1951)
Murphy v. United States
164 Ct. Cl. 332 (Court of Claims, 1964)
Dynalectron Corp. v. United States
518 F.2d 594 (Court of Claims, 1975)
Discount Co. v. United States
554 F.2d 435 (Court of Claims, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
Nelson, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/nelson-inc-asbca-2015.