United States v. Frank M. Chichester, Trustee in Bankruptcy of the Aircraftsmen Company, Bankrupt

312 F.2d 275, 1963 U.S. App. LEXIS 6541
CourtCourt of Appeals for the Ninth Circuit
DecidedJanuary 7, 1963
Docket17547_1
StatusPublished
Cited by22 cases

This text of 312 F.2d 275 (United States v. Frank M. Chichester, Trustee in Bankruptcy of the Aircraftsmen Company, Bankrupt) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Frank M. Chichester, Trustee in Bankruptcy of the Aircraftsmen Company, Bankrupt, 312 F.2d 275, 1963 U.S. App. LEXIS 6541 (9th Cir. 1963).

Opinion

JERTBERG, Circuit Judge.

Before us is an appeal by the United States from an order of the District Court affirming an order of the Referee in Bankruptcy disallowing the amended claim of the United States.

The jurisdiction of the United States District Court rests upon Title 28 U.S.C. § 1334, and § 2 of the Bankruptcy Act, Title 11 U.S.C. § 11. The jurisdiction of this Court has been properly invoked under Title 28 U.S.C. §§ 1291 and 1294, and § 24 of the Bankruptcy Act, Title 11 U.S.C. § 47.

The basic question presented by this appeal is whether the United States properly terminated for default a contract between the Department of the Army of the United States and The Aircraftsmen *277 Company for the manufacture and delivery of fire bombs.

The following facts are not in dispute and may be summarized as follows:

On June 28, 1954, The Aircraftsmen Company (hereinafter sometimes referred to as “the contractor” and “the bankrupt”) entered into a contract with the Department of the Army for the manufacture and delivery of 73,944 fire ■bombs at a fixed unit price and in accordance with a specific delivery schedule •commencing in December, 1954.

The contract per unit price was increased by modification on February 25, 1955, and Modern Metal Spinning and Manufacturing Company, the parent corporation of the contractor, was required to guarantee performance of the contract. On March 8,1955, the “payments” article of the contract was amended to permit the contracting officer to allow, from time to time, progress payments.

Production delays were encountered and prior to June, 1955, only 4,550 units :had been delivered. By a modification dated May 25,1955, a new delivery schedule for the remaining 69,394 bombs was set up which called for delivery of 5,000 units in June of 1955, 8,000 units per month during July of 1955 through February of 1956, with the balance of 394 units due in March of 1956. This was the delivery schedule under which the contractor was operating at the time of termination.

The contract performance went forward during June of 1955 but deliveries for that month totaled 4,630 units. In July of 1955. the contractor delivered 6,830 units.

On August 12, 1955, the contractor applied for relief under Title II of the First 'War Powers Act, as amended, 50 U.S.C. Appendix § 611. And on October 28, 1955, the contract was modified by increase in unit prices. This award amounted to almost $1,000,000 of which $95,000.00 was paid in cash to the contractor and the balance was offset . against unliquidated progress payments. The parties then executed a supplemental agreement, dated November 14, 1955, which implemented the award and made provision for certain safeguards which the contracting officer considered necessary to the Government’s interests. By a supplemental agreement dated December 16, 1955, it was agreed that the contractor would furnish to the Government certain technical data and that delivery of these items was to be made at the time of delivery of the final quantity of bombs.

Through the remainder of 1955, the contractor delivered 6,490 bombs in August; 7,140 in September; 6,134 in October; 7,675 in November; and 8,066 in December. In January 1956, the contractor delivered 7,120 bombs.

In the latter part of January 1956, the contractor advised the contracting officer that it was “in critical financial condition” and discussed the possibility of further financial relief. Under date of February 6, 1956, the contractor applied for further Title II relief which was submitted with the contracting officer’s approval. The application stated that the contractor “cannot possibly remain in business longer than another seven (7) days due to pressure from creditors and lack of money to meet operating expenses including payrolls,” and it was stated that the Government was over-extended on its progress payments. The last progress payment submitted was paid on February 8, 1956, and the contractor was advised on February 10, 1956 that further progress payments were being withheld. On the same date, the contractor laid off its employees who were working on this contract but not its supervisory personnel engaged in the fire bomb program. No bombs were manufactured after February 13, 1956, but between February 1st and 14th of 1956, 3,920 bombs were delivered, and in March of 1956, 531 bombs were delivered and accepted.

The following table shows monthly deliveries and acceptances of fire bombs *278 for the period June, 1955, through March, 1956; monthly units due for the same period under the delivery schedule; and cumulative monthly shortages.

Units Due by Units Unit Shortage

Month End Delivered For Month Cumulative

June 1955 5.000 4,630 370 370

July “ 8.000 6,830 1,170 1,540

Aug. “ 8,000 6,490 1,510 3,050

Sept. “ 8,000 7,140 860 3,910

Oct. 8,000 6,134 1,866 5,776

Nov. “ 8,000 7,675 325 6,101

Dec. 8,000 8,066 66 (overplus) 6,035

Jan. 1956 8,000 7,120 880 6,915

Feb. 8,000 3,920 4,080 10,995

Mar. 394 531 137 (overplus) 10,858

On February 28, 1956, the contractor supplemented its application for Title II relief and requested an immediate cash advance.

On March 1, 1956, a hearing was held before the Army Contract Adjustment Board; and on March 23, 1956, the Board declined to grant the application for relief.

On March 26,1956, the contracting officer notified the contractor by telegraph, following reference to the contract, that:

“in accordance with the General Provision entitled ‘Default’ your right to proceed further with delivery of the balance of 10,858 bombs of Item No. 1 under said contract is hereby terminated in whole for default, effective upon receipt of this notice. Letter follows.
“The Government hereby asserts title to the raw materials, work in process, finished items and special tooling manufactured or acquired in the performance of, and in accordance with the terms of the contract.”

By letter dated March 27, 1956, the contracting officer notified the contractor, after referring to the contract, as follows:

“2. In accordance with the telegraphic notice dated 26 March 1956, your right to proceed further with delivery on the balance of 10,858 Bombs of Item No. 1 under said contract was terminated in vjhole for default.
“3. The acts or omissions constituting a default under said contract are as follows:
“(a) Failure to deliver the quantity of Item No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Plaskett v. McCarthy
N.D. California, 2019
Victor v. State Farm Fire & Casualty Co.
795 F. Supp. 300 (D. Alaska, 1992)
State v. Romulus
555 A.2d 494 (Court of Appeals of Maryland, 1989)
United States v. Mottolo
695 F. Supp. 615 (D. New Hampshire, 1988)
City of Palmer v. Anderson
603 P.2d 495 (Alaska Supreme Court, 1979)
Curtis v. State
395 A.2d 464 (Court of Appeals of Maryland, 1979)
Kaiser v. Local No. 83
577 F.2d 642 (Ninth Circuit, 1978)
Milne v. Anderson
576 P.2d 109 (Alaska Supreme Court, 1978)
Cities Service Helex, Inc. v. United States
543 F.2d 1306 (Court of Claims, 1976)
Pritchard v. Insurance Co. of North America
61 F.R.D. 104 (N.D. Mississippi, 1973)
Gorge Lumber Co. v. Brazier Lumber Co.
493 P.2d 782 (Court of Appeals of Washington, 1972)
Knox v. Municipal Court of City of Des Moines
185 N.W.2d 705 (Supreme Court of Iowa, 1971)
Groves v. Prickett
420 F.2d 1119 (Ninth Circuit, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
312 F.2d 275, 1963 U.S. App. LEXIS 6541, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-frank-m-chichester-trustee-in-bankruptcy-of-the-ca9-1963.