City of Palmer v. Anderson

603 P.2d 495, 1979 Alas. LEXIS 691
CourtAlaska Supreme Court
DecidedNovember 30, 1979
Docket4118
StatusPublished
Cited by22 cases

This text of 603 P.2d 495 (City of Palmer v. Anderson) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Palmer v. Anderson, 603 P.2d 495, 1979 Alas. LEXIS 691 (Ala. 1979).

Opinion

OPINION

MATTHEWS, Justice.

The City of Palmer appeals from a jury finding that it breached its contract with the appellee, Dale Anderson, doing business as Anderson Garbage Service. Damages were awarded in the amount of $24,424.00.

Anderson purchased his garbage business from his father in 1973. At that time the business included a sanitary landfill operation, garbage collecting equipment, a certificate from the Alaska Public Utilities Commission authorizing garbage and refuse collection from the area immediately outside the city limits of Palmer, and an oral agreement with the City of Palmer under which Anderson’s father had collected refuse in the city for many years.

Shortly after buying the business, Anderson determined that he needed to upgrade his equipment and began negotiating the purchase of a larger, more efficient garbage-packer truck. When he contacted his bank for financing, he was told that due to insufficient collateral, a loan could not be arranged unless his agreement with the City was formalized and extended over several years.

Anderson discussed his requirements with Palmer’s city manager, William E. Curtis. After preliminary negotiations, a proposed contract was drawn up by the City. The typed provisions in the contract stated that the agreement was to last for one year, with automatic renewal unless one of the parties objected. This provision was unacceptable to Anderson’s bank, which wanted a five-year contract guarantee before it would advance the money Anderson needed. Anderson returned to Curtis with proposed changes making the contract a five-year agreement, which could be reviewed annually if necessary to reflect changing costs and expenses. Curtis took the agreement before the Palmer City Council, which approved the contract and authorized Curtis to sign.

Several days later, Curtis and Anderson met to finalize and sign the contract. Their testimony as to what happened at the meeting is in conflict. Anderson testified that a five year contract was signed. According to Curtis, Anderson agreed to a one-year contract after further negotiations. Anderson’s copy of the contract supported his claim. The City’s copy indicated that the contract was to last only one year.

*497 In his complaint Anderson pleaded that he had fully performed his duties under the contract. The City’s answer alleged as an affirmative defense that Anderson had materially breached the contract. The City at trial put on evidence tending to show that it had received many complaints about the garbage collection service and that these had resulted in a warning to Anderson that his contract was in danger. In particular, the City attempted to show that garbage service during July, 1976, was especially bad, that many customers had not been serviced on schedule, and that the resulting sanitation and health problems caused the City to go out on several occasions and pick up garbage on its own. The City also put on evidence indicating that Anderson’s sanitary landfill operation had not been run in compliance with the permit issued by the State Department of Environmental Conservation as required by the contract.

Curtis testified that on July 30, 1976, Anderson told him that he was quitting altogether and that as a result the City had been forced to make emergency arrangements to collect garbage and refuse.

The evidence presented by Anderson was in many instances directly contradictory to the City’s. Witnesses for Anderson testified that their garbage service had been satisfactory. Anderson testified that he maintained frequent contact with city hall to see if any complaints had been received and to notify the City when, for some reason, he was unable to service a customer as scheduled. On cross-examination, Curtis admitted that the City’s subsequent operation of the garbage collection service had not been complaint-free, and that “anytime you’re in the garbage business you get complaints. . . .” Anderson also showed that his landfill permit was still effective and that it had never been suspended or revoked.

Anderson testified that problems with the collection service in July of 1976 resulted from the breakdown of his new garbage compactor truck. While waiting for a new transmission, Anderson used his older equipment to make his rounds. He admitted that he may have been from a day to a day and a half behind schedule during the last three weeks in July, but denied that service' had been suspended, or that he had failed to continue working to meet his schedule. According to Anderson he maintained his contact with city hall, keeping them informed when he was unable to meet his schedule.

On July 31, 1976, Curtis gave a letter addressed to Anderson to Anderson’s brother-in-law, who was assisting Anderson with collections that weekend. The letter indicated that “[t]he contract that once existed between yourself and the City has expired the 31st day of July, 1974. The informal relationship that has been in existence since that time has been terminated by your declaration of intention to end your business.” Since that date, the City of Palmer has collected garbage and refuse within the city limits. Anderson continues to operate outside the city limits. There was testimony at trial showing that Anderson cannot operate profitably without the City of Palmer’s business.

Anderson filed suit on March 10, 1977. The jury found in his favor and awarded damages in the amount of $24,424. On appeal the City of Palmer argues that the trial court should not have instructed the jury that it could find that the City had waived its breach of contract defense against Anderson, that the evidence presented to prove the amount of damages was too speculative to support the jury’s award, and that the trial court improperly denied the City’s motions for a directed verdict and a new trial. We affirm.

Although neither party requested such an instruction, the trial court told the jury that it could find that the City had waived its defense of noncompliance with the contract by Anderson. The waiver instruction was given over timely and proper objection by the City. The City argues that the instfuction should not have been given because Anderson failed to plead waiver in his complaint or to raise the issue during trial.

It is clear that Anderson had no duty to include the waiver theory in any of *498 his pleadings. Rule 8(a), Alaska Rules of Civil Procedure, requires only that a claim for relief contain a short, plain statement of the claim showing the plaintiff is entitled to relief. Anderson’s complaint did so, alleging the existence of a contract, full performance, and breach by the City. It was not necessary for him to plead his responses to the defenses which might be raised by the City and, technically speaking, it would have been improper for him to do so. 1

When the City answered the complaint with the affirmative defense of failure to perform under the contract, Anderson had no responsibility to reply. • Rule 7(a), Alaska Rules of Civil Procedure, states in pertinent part:

Pleadings. There shall be a complaint and an answer; a reply to a counterclaim denominated as such . . . . No other pleading shall be allowed, except that the court may order a reply to an answer or a third-party answer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peggy Downing v. Shoreside Petroleum, Inc. and Russell Mills
528 P.3d 874 (Alaska Supreme Court, 2023)
Douglas Galipeau v. Briana Bixby and Mei-Lani Bixby
476 P.3d 1129 (Alaska Supreme Court, 2020)
Cameron v. CHANG-CRAFT
251 P.3d 1008 (Alaska Supreme Court, 2011)
Veys v. Applequist
2007 WY 60 (Wyoming Supreme Court, 2007)
Central Bering Sea Fishermen's Ass'n v. Anderson
54 P.3d 271 (Alaska Supreme Court, 2002)
DeNardo v. GCI Communication Corp.
983 P.2d 1288 (Alaska Supreme Court, 1999)
Alaska Tae Woong Venture, Inc. v. Westward Seafoods, Inc.
963 P.2d 1055 (Alaska Supreme Court, 1998)
Power Constructors, Inc. v. Taylor & Hintze
960 P.2d 20 (Alaska Supreme Court, 1998)
Ben Lomond, Inc. v. Schwartz
915 P.2d 632 (Alaska Supreme Court, 1996)
Geolar, Inc. v. Gilbert/Commonwealth Inc.
874 P.2d 937 (Alaska Supreme Court, 1994)
Richey v. Oen
824 P.2d 1371 (Alaska Supreme Court, 1992)
Municipality of Anchorage v. Locker
723 P.2d 1261 (Alaska Supreme Court, 1986)
Sawyers v. FMA Leasing Co.
722 P.2d 773 (Utah Supreme Court, 1986)
Hayes v. Xerox Corp.
718 P.2d 929 (Alaska Supreme Court, 1986)
Alaska Children's Services, Inc. v. Smart
677 P.2d 899 (Alaska Supreme Court, 1984)
Bullard v. B. P. Alaska, Inc.
650 P.2d 402 (Alaska Supreme Court, 1982)
Sebring v. Colver
649 P.2d 932 (Alaska Supreme Court, 1982)
Baker v. Werner
654 P.2d 263 (Alaska Supreme Court, 1982)
Metcalf v. Wilbur, Inc.
645 P.2d 163 (Alaska Supreme Court, 1982)
Bailey v. Lenord
625 P.2d 849 (Alaska Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
603 P.2d 495, 1979 Alas. LEXIS 691, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-palmer-v-anderson-alaska-1979.