U.S. Aeroteam, Inc.

CourtArmed Services Board of Contract Appeals
DecidedMay 14, 2025
Docket61933, 61934
StatusPublished

This text of U.S. Aeroteam, Inc. (U.S. Aeroteam, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
U.S. Aeroteam, Inc., (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of - ) ) U.S. Aeroteam, Inc. ) ASBCA Nos. 61933, 61934 ) Under Contract No. FA8526-12-C-0039 )

APPEARANCE FOR THE APPELLANT: Milton Johns, Esq. Executive Law Partners, PLLC Fairfax, VA

APPEARANCES FOR THE GOVERNMENT: Caryl A. Potter, III, Esq. Air Force Deputy Chief Trial Attorney Isabelle P. Cutting, Esq. Michael Farr, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE O’CONNELL PURSUANT TO BOARD RULE 11

The Air Force terminated for default a contract with U.S. Aeroteam, Inc. (USAT), for failure to make progress furnishing trailers used to transport aircraft engines and demanded the return of progress payments. The parties have elected to submit the appeals on the record pursuant to Board Rule 11. USAT previously filed an appeal with the United States Court of Federal Claims (COFC) regarding the denial of its claims for additional costs under two contracts (including the above-captioned contract) related to running gear for the trailers. After the COFC ruled in favor of the government, USAT filed an appeal at the United Stated Court of Appeals for the Federal Circuit, which affirmed the lower court’s decision. U.S. Aeroteam, Inc. v. United States, 2022 WL 2431626 (Fed. Cir. 2022). For the reasons discussed below, we conclude that the government has adequately supported the default termination as well as the return of a portion of the progress payments. The Board denies the appeals.

FINDINGS OF FACT

1. USAT is a contractor that specializes in building components for the aerospace industry. U.S. Aeroteam, Inc. v. United States, 2022 WL 2431626 at *1 (USAT) (Fed. Cir. 2022).

2. On September 6, 2012, the Air Force awarded USAT Contract No. FA8526- 12-C-0039 (the 0039 contract), a firm fixed price contract for 86 trailers to be used for transporting C-17 aircraft engines (R4, tab 1 at 1-4). At that time, USAT was performing a similar contract that the Air Force had awarded in 2009, No. FA8526-09- C-0007 (the 007 contract) (compl. ¶¶ 1-2). The 007 contract is not at issue in these appeals, but it has some bearing on the facts because USAT experienced the same problem on both contracts.

3. The original price for the (0039) contract was $15,477,850, or $179,975 per trailer (R4, tab 1 at 1-3). The government exercised an option to add an additional 12 trailers at $184,975 each for a total of 98 trailers (R4, tabs 3, 5-6).

4. The contract contained various clauses including Federal Acquisition Regulation (FAR) 52.232-16, PROGRESS PAYMENTS (APR 2012); FAR 52.233-1, DISPUTES (JUL 2002); and FAR 52.249-8, DEFAULT (FIXED-PRICE SUPPLY AND SERVICE) (APR 1984) (R4, tab 1 at 15, 17-18).

5. Originally, the trailers were to be delivered within 280 days of order but two bilateral schedule modifications along with the modifications ordering additional trailers pushed the last delivery to July 2016 (R4, tab 1 at 3, tabs 2-6).

6. The government made progress payments to USAT almost every month from April 5, 2013 to May 4, 2015 (see R4, tabs 27-54 (each tab is a progress payment sheet); R4, tab 18 at 2).

USAT Submits REAs

7. Although not before the Board in the present appeals, on or about January 31, 2015, USAT submitted requests for equitable adjustment (REAs) on both the 007 and 0039 contracts (app. supp. R4, tab 2 at ¶¶ 9-10; No. 61973, R4, tab 20 at 167 (hereinafter “REA at 167”); ASBCA Nos. 61972, 61973, joint stipulation of facts (JSF) ¶¶ 42-43). The REA for the 0039 contract sought $4,531,523 for 11 items that USAT referred to as “factors” (JSF ¶ 43).

8. By far the largest single element in each REA was factor 1, which related to the running gear for the trailers (app. br. at 2; JSF ¶ 43). For the 0039 contract, USAT sought an additional $3,559,810 for this factor (JSF ¶ 43). 1 The running gear is essentially a drive train for the trailer, which allows it to roll, brake, and steer. The running gear was the largest and most expensive sub-assembly for the trailer. USAT obtained the running gear from a subcontractor, PDI Ground Support Systems (PDI). USAT, 2022 WL 2431626 at *1; (JSF ¶ 43; app. supp. R4, tab 54; app. br. at 2)

1 For the 007 contract, USAT sought $1,092,415 for the running gear (JSF ¶ 42). 2 9. In 2011 (nine months or more before the parties executed the 0039 contract), PDI experienced financial difficulties and attempted to raise its price per unit from an agreed upon $20,300 to at least $38,000. USAT, 2022 WL 2431626 at *1; (REA at 6, 168).

10. USAT formally asked the Air Force if it could assume responsibility for manufacturing the running gear. The contracting officer (CO) granted the request, but USAT incurred higher costs than it expected. USAT, 2022 WL 2431626 at *1. The REA stated that the PDI cost per trailer had been $20,300 but USAT’s cost to manufacture was $56,625 (REA at 168).

11. The parties executed Modification No. 10 (Mod 10) on March 2, 2016, to give USAT some relief while the government considered the REA by suspending the schedule but requiring USAT to make a good faith effort to continue production (R4, tab 11). The modification stated:

The purpose of this modification is to extend the delivery schedule of CLINs 0001AA, 0001AB, 1001AA, 1001AB, 1001AC, 1001AD, 1001AE, and 1001AF indefinitely. A firm delivery schedule will be established upon resolution of the REAs submitted for FA8526-09-C-0007 and FA8526-12-C-0039.

...

USAeroteam shall make a good faith effort to continue to produce and ship units prior to REA resolution and establishment of a firm delivery schedule.

All other terms and conditions remain unchanged and in full force and effect.

(Id. at 3)

USAT Fails to Manufacture any Trailers after Mod. 10

12. USAT did not manufacture any trailers after the execution of Mod. 10. At the time the modification was executed, USAT had four completed trailers on hand that it had not delivered to the Air Force (R4, tabs 119 at 2, 120 at 1). USAT delivered two of those trailers on March 9, 2016; it delivered the third trailer on March 23, 2016, and the fourth on June 23, 2016. USAT did not deliver any trailers after June 23, 2016. USAT delivered 58 of the 98 trailers ordered. (R4, tab 23 at 1; app. supp. R4 tab 33 at 1)

3 13. On June 28, 2016, the parties addressed the pending REA in bilateral Modification No. 11 (Mod. 11). Mod. 11 provided payment of $136,542.21 to USAT for REA Factors 5 and 6 and stated that the interest that USAT had requested in Factor 4 was unallowable. The modification left the remaining issues open to allow USAT to submit further documentation:

REA factor Numbers 1, 2, 3, 4 (except interest as addressed above), 7, 8, 9, 10, and 11 are considered “open” pending the Contractor’s submission of adequate supporting documentation in accordance with FAR 31.201- 2(d).

(R4, tab 12 at 1-2)

14. On November 10, 2016, the contracting officer (CO) wrote by email to USAT to inquire about re-establishing a delivery schedule. The CO stated that the government had understood that USAT would resume production once its facility relocated and that USAT had informed the government over the summer that it had enough material on hand to manufacture 5-6 trailers. He stated that “[d]elivering new trailers represents the surest way for USAT to liquidate the $3.54M in overpaid progress payments currently owed to the AF. . . .” Among other things, he asked USAT to propose a schedule by December 1, 2016. (App. supp. R4, tab 22)

15. USAT responded by email on November 14, 2016, stating that it was working on a request for a CO’s final decision. USAT did not propose a delivery schedule but instead stated “[w]e need to make a good progress on your side to resolve the REA/COFD, before we know our action plans. . . .” (Id.)

16.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)
Dcx, Inc. v. William J. Perry, Secretary of Defense
79 F.3d 132 (Federal Circuit, 1996)
Universal Fiberglass Corp. v. United States
537 F.2d 393 (Court of Claims, 1976)
Discount Co. v. United States
554 F.2d 435 (Court of Claims, 1977)
B-E-C-K Constructors v. United States
571 F.2d 25 (Court of Claims, 1978)
Transportation v. Eagle Peak Rock & Paving, Inc.
69 F.4th 1367 (Federal Circuit, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
U.S. Aeroteam, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-aeroteam-inc-asbca-2025.