Hicks Corp. v. United States

487 F.2d 520, 203 Ct. Cl. 65, 1973 U.S. Ct. Cl. LEXIS 153
CourtUnited States Court of Claims
DecidedNovember 14, 1973
DocketNo. 22-71
StatusPublished
Cited by4 cases

This text of 487 F.2d 520 (Hicks Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hicks Corp. v. United States, 487 F.2d 520, 203 Ct. Cl. 65, 1973 U.S. Ct. Cl. LEXIS 153 (cc 1973).

Opinion

Pee Ctjeiam :

This case comes before the court on plaintiff’s request, filed April 16, 1973, for review by the court of a recommended decision filed by Trial Judge George Willi pursuant to Buie 166(c) on March 20, 1978. The court has considered the case on the record and the briefs of the parties. Since the court agrees with the decision of the trial judge, as hereinafter set forth, it hereby affirms and adopts the same as the basis for its judgment in this case. Therefore, it is concluded that plaintiff is not entitled to recover and its petition should be dismissed; that judgment in the amount of $55,067.57 should be entered for defendant on its first counterclaim; and, that defendant’s second, third, fourth and fifth counterclaims are remanded to the trial judge for further proceedings of an appropriate nature. Plaintiff’s petition is to be dismissed and judgment is to be entered for defendant on its first counterclaim at the conclusion of the proceedings remanded to the trial judge.

OPINION OE TRIAL JUDGE

Willi, Tried Judge:

By cross-motions for summary judgment the parties present a single issue common to four of the six counts of the petition herein. It is the correctness, subject to the finality standards of the Wunderlich Act, 68- Stat. 81, [68]*6841 U.S.C. §§ 321-22 (1964), of three decisions of the Armed Services Board of Contract Appeals (Board) upholding the default termination of four contracts for the supply of various missile components to the Army and Navy. The Micks Corporation, 67-1 BCA ¶¶6803, 6304 and 6305.

Except to the limited extent hereafter discussed, plaintiff’s attack on the subject decisions totally lacks the substantive particularity essential to an efficacious challenge. For the most part, both its pleadings and moving papers simply adumbrate those statutory factors and ultimate circumstances for which the Wunderlich Act, supra, would deny finality to a board decision. That approach is insufficient, as a matter of law, to bring the merits of such a decision into issue. Sundstrand Turbo v. United States, 182 Ct. Cl. 31, 59-60, 389 F. 2d 406, 422-23 (1968).

Each of the four contracts mentioned above may be correlated with the particular count of the petition to which it relates and to the Board decision rendered in respect to it as follows:

Count II: Army Contract No. DA-01-021-AMC-10604(Z) : 67-1 BCA ¶ 6305
Count III: Army Contract No. AMC (Z) 01-021-64-11572 (Z) : 67-1 BCA ¶ 6305
Count IY: Navy Contract No. NOw 63-0530-f: 67-1 BCA ¶ 6303
Count Y: Navy Contract No. NOw(Z) 63-0376-f: 67-1 BCA ¶ 6304

In each of these counts plaintiff relies on the same two factors to excuse its acknowledged failure to make progress because of lack of capital. First, it urges that working capital was impaired by the additional costs and inefficiencies engendered by the Government’s change, while performance was under way, from 100 percent inspection to lot sampling and its withdrawal of Government in-plant inspectors during the second and Saturday work shifts. Neither of these actions exculpates the defaults that followed. Plaintiff neither contends, nor do the contractual inspection provisions suggest, that the Government was required to provide the services of resident inspectors for the second, Saturday or any other of plaintiff’s work shifts. As to the change in inspection method, [69]*69the Board correctly pointed out that each of the contract’s standard inspection clauses expressly authorized the lot sampling of which plaintiff complains. 67-1 BCA ¶ 6304 at 29,179. Government conduct authorized by the terms of a contract cannot serve either to excuse the contractor’s failure to perform or to create for him an actionable claim for money damages or other relief.

The second allegedly unwarranted source of capital impairment invoked by plaintiff to justify its inadequate performance progress is set forth in Count I of the petition. There plaintiff recites the difficulties experienced in attempting to perform an earlier (1962) Army contract, No. DA-01-021OBD-J13055, for the supply of Nike rocket motor cases. In a decision rendered November 12, 1964, at which time the four contracts detailed in Counts II through Y were outstanding, the Board found certain specifications of that contract to be defective and remanded the matter to the contracting officer for determination of an appropriate adjustment in contract price. 65-1 BCA ¶ 4516.

On December 18,1964, while the parties were negotiating the amount of the equitable adjustment, plaintiff closed its plant for lack of operating funds. On January 5,1965, plaintiff was paid $48,720 by the contracting officer. Although it appealed the adequacy of that payment, it used the money to reopen its plant on January 11,1965.1 On March 22,1965, while the appeal was pending, the contracting officer increased the equitable adjustment by $64,040.62. Plaintiff again appealed and in a supplementary decision of March 18, 1966, the Board held that the adjustment should be still further increased by $53,249, which amount was paid that date. 66-1 BCA ¶ 5469.2

Meanwhile, on May 6, 1965, plaintiff had again closed its plant for lack of working capital and this time the closing was permanent. It was this closing that precipitated the default termination of each of the four contracts represented in Counts II through V. A survey of plaintiff’s financial con[70]*70dition following the plant closing disclosed that while it was due $19,571 on unpaid vouchers for finished goods that had been delivered and had $33,109 outstanding on unpaid progress payment billings, it had a current balance of unliqui-dated progress payment receipts totaling more than $660,000 and had been paid some $54,000 [under Army Contract 10604 (Count II) ] for 270 rocket motor adapters that it had not delivered. All of these matters are chronicled in the Board’s opinion affirming the default termination of the two Army contracts detailed in Counts II and III of the petition herein and are not presently disputed by the plaintiff. 67-1 BCA ¶6305. In that opinion, speaking of those two Army contracts in addition to the two basically contemporaneous Navy contracts (Counts IV and V) that were similarly defaulted, the Board concluded: (1) that insufficient operating capital was the effective cause of plaintiff’s May plant closing and its consequent inability to make progress on all of the defaulted contracts; (2) that performance could only have been resumed by the infusion of additional Government credit; (3) that such assistance was discretionary with the contracting officer; and (4) that his refusal to extend more credit in an attempt to recoup prior unliquidated advances could not be deemed an abuse of discretion under the circumstances. 67-1 BCA at 29,181.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

D. Moody & Co. v. United States
32 Cont. Cas. Fed. 72,390 (Court of Claims, 1984)
Discount Co. v. United States
554 F.2d 435 (Court of Claims, 1977)
Wickham Contracting Co. v. United States
546 F.2d 395 (Court of Claims, 1976)
Hicks Corp.
503 F.2d 1406 (Court of Claims, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
487 F.2d 520, 203 Ct. Cl. 65, 1973 U.S. Ct. Cl. LEXIS 153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hicks-corp-v-united-states-cc-1973.