Donley v. Lockheed Martin Corp.

608 F.3d 1348, 2010 U.S. App. LEXIS 11822, 2010 WL 2302741
CourtCourt of Appeals for the Federal Circuit
DecidedJune 10, 2010
Docket2009-1261
StatusPublished
Cited by3 cases

This text of 608 F.3d 1348 (Donley v. Lockheed Martin Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Donley v. Lockheed Martin Corp., 608 F.3d 1348, 2010 U.S. App. LEXIS 11822, 2010 WL 2302741 (Fed. Cir. 2010).

Opinion

BRYSON, Circuit Judge.

In 1991, the Air Force and Lockheed Corporation (now Lockheed Martin Corporation) entered into a contract for the development of the F-22 “new generation” fighter aircraft. The F-22 contract was a cost-plus-award fee contract with a total value of $9.55 billion. Under a cost-plus-award fee contract, a contractor is reimbursed for its costs and receives a profit, or fee. Northrop Grumman Corp. v. Goldin, 136 F.3d 1479, 1481 (Fed.Cir.1998). Performance was scheduled to take place over an eight-to-nine-year period. This case grows out of a “rephasing” of the F-22 contract that was negotiated by the parties early in the contract performance period. The dispute concerns whether, under the applicable statutory, regulatory, and contractual provisions, the government is entitled to recover a portion of the negotiated price increase on the ground that it resulted from a change in Lockheed’s accounting practices and could not lawfully be charged against the contract price.

I

The F-22 contract incorporated a number of provisions of the Federal Acquisition Regulation (“FAR”), including provisions of the Cost Accounting Standards (“CAS”). Among the pertinent FAR pro *1350 visions incorporated into the contract was 48 C.F.R. § 52.230-2 (“FAR 52.230-2”), which governs the manner in which a contractor may alter its accounting practices and what duties the contractor must undertake when it makes such an accounting change. That regulation was issued pursuant to 41 U.S.C. § 422(h), which requires the Cost Accounting Standards Board to promulgate regulations requiring contractors to agree to a contract price adjustment “for any increased costs ... by reason of a change in the contractor’s ... cost accounting practices.” Id. § 422(h)(1)(B).

By regulation, a contractor that wishes to modify its accounting practices must first negotiate the terms and conditions under which the change will be made with the appropriate Divisional Administrative Contracting Officer (“DACO”). FAR 52.230 — 2(a) (4) (ii). If the accounting change results in increased costs because expenses previously accounted as indirect are now directly charged to the government contract, the contractor is required to agree to a contract price adjustment and repay the government any increased costs caused by the accounting change. FAR 52.230-2(a)(2), (a)(5). The regulations also state that the amount of the price adjustment is generally limited to the additional amount paid by the government “in the aggregate” over “all of the contractor’s affected CAS-covered contracts and subcontracts.” FAR 30.602-3 (1993); see 41 U.S.C. § 422(h)(3); FAR 52.230-2(a)(5).

The FAR defines the term “affected CAS-covered contract,” in pertinent part, to mean a contract in which the contractor “[ujsed one accounting practice to estimate costs and a changed cost accounting practice to accumulate and report costs under the contract.” FAR 52.230-6(a)(l) (2005); FAR 30.001 (2005). The dispute in this case focuses on whether the F-22 contract was an “affected contract” and thus whether Lockheed’s mid-1993 change in its accounting practices was subject to the FAR’s limitations on the allowance of increased costs resulting from that change.

A

In 1992, the Air Force informed Lockheed that it anticipated a funding shortfall for the F-22 program. At the same time, Lockheed told the Air Force that it expected the costs of the F-22 project to increase. As a response to those funding issues, the Air Force issued a Request for Proposal (“RFP”) on November 18, 1992, to “rephase” the F-22 contract. The RFP asked Lockheed to prepare a cost proposal that would bring the F-22 contract within the program’s “revised funding profile” for fiscal years 1993 through 2001. The RFP identified several technical and schedule changes to the F-22 contract, such as deleting two aircraft and modifying the date for several performance milestones. The RFP also required Lockheed’s proposal to include both an estimated cost and a not-to-exceed base price for the rephased contract.

The RFP required Lockheed to divide estimated expenses into five categories, referred to as “buckets.” Those buckets were (1) deletion of two aircraft, (2) “Revised Program Baseline,” (3) “Other Cost Changes,” (4) “Weight Reduction Requirement Challenges,” and (5) “Program Re-phase Impacts.” In the RFP, the Air Force specifically stated that the cost estimate should include “the proposed re-phased hours with narrative substantiation including a discussion comparing the proposed changes with the current program.” In addition, the Air Force required Lock *1351 heed to disclose a detailed breakout of labor costs.

On December 22, 1992, the Air Force issued Contract Modification P00059 as an “undefinitized contract action,” which required Lockheed to rephase the F-22 contract. The Air Force later issued additional instructions for the rephase proposal, each time repeating the requirement for a summary of the build-up of man hours by calendar year. Lockheed timely submitted its cost proposal on April 23, 1993.

Meanwhile, the Secretary of the Air Force recommended that several government contractors, including Lockheed, change their cost accounting practices to more accurately reflect the costs incurred on each of them contracts. As part of that effort, the Air Force initiated a “Comprehensive Overhead Cost Analysis and Control Review” process, which recommended specific changes to various contractors’ accounting practices. In the course of that review process, the government urged Lockheed to change its accounting practices and directly charge certain personnel costs to the F-22 contract. Even though Lockheed voiced concern about the cost impact of those changes, it notified its DACO on June 4, 1993, that it would comply with the Air Force recommendation and change its accounting methods for all of its contracts. Lockheed indicated that to make those changes it would treat personnel costs associated with program management, master scheduling, industrial engineering, and engineering administration as direct costs. Lockheed sought to amend its disclosure statement to reflect the changed practices. In addition, it requested a waiver of the 60-day waiting requirement, and it asked permission to make the accounting changes effective as of June 28, 1993. The DACO waived the waiting period and permitted the changes to be made effective as requested.

On June 22, 1993, Lockheed sent a “General Order of Magnitude Cost and Rate Impact Study Reflecting Mid Year 1993 Accounting Changes” to the DACO. That study estimated that the accounting changes would increase the cost of the F-22 contract by more than $10 million for the period between mid-1993 and 1997. On July 19, 1993, Lockheed submitted its proposed forward pricing rates to the DACO. Those pricing rates included both direct and indirect labor rates estimated under Lockheed’s new accounting practices.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Raytheon Company v. United States
747 F.3d 1341 (Federal Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
608 F.3d 1348, 2010 U.S. App. LEXIS 11822, 2010 WL 2302741, Counsel Stack Legal Research, https://law.counselstack.com/opinion/donley-v-lockheed-martin-corp-cafc-2010.