This text of 212 F. App'x 972 (Schleicher Community Corrections Center v. Department of Justice) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schleicher Community Corrections Center v. Department of Justice, 212 F. App'x 972 (Fed. Cir. 2007).

Opinion

PROST, Circuit Judge.

Schleicher Community Corrections Center, Inc. (“Schleicher”) appeals a September 29, 2005 decision by the Department of Transportation Board of Contract Appeals (“Board”) denying Schleicher’s claim for interest on back wages, benefits, and taxes due under the Contract Dispute Act (“CDA”), and limiting profits awarded to Schleicher for increased wages, benefits, taxes, and other costs due to the belated incorporation of a wage determination. Because the Board correctly limited Schleicher’s profit award and held that Schleicher could not receive CDA interest for wages, benefits, and taxes it had not actually paid, we affirm.

I. BACKGROUND

On November 6, 1990, Schleicher was awarded a contract by the Federal Bureau of Prisons (“BOP”) to provide residential community corrections center services for Federal offenders in the greater Salt Lake City area. At the time the contract was awarded, a wage rate determination had been requested from the Department of Labor (“DOL”), but not yet received. On April 1, 1992, the wage determination was issued by DOL, and the contracting officer then issued a contract modification to incorporate the wage determination retroactive to the beginning of the contract. Subsequently, revised wage rates were also incorporated into the contract.

*974 During the course of performance, Schleicher submitted a number of requests for increased payments based largely on the contention that it was owed additional funds to pay for increased wages required by the Service Contract Act (“SCA”). Although BOP paid Schleicher $262,811 via price adjustments and manday increases during the performance period, Schleicher submitted a claim to the contracting officer seeking $826,797. The contracting officer denied the claim in its entirety.

Schleicher appealed the contracting officer’s decision to the Board. In a decision dated June 19, 2002, the Board recognized that Schleicher’s case raised some issues that were within the exclusive jurisdiction of DOL. The Board, however, went on to resolve the contractual matters that were within its jurisdiction. Because the issues relating to unresolved labor standards were reserved to DOL, the Board remanded the determination of the total amount of increased wages and fringe benefits for which Schleicher was liable to DOL. After this determination, the amount of the award due to Schleicher’s wage and fringe benefits liability would be transferred to DOL for distribution to Schleicher’s former employees. With regard to interest, the Board stated Schleicher was “automatically entitled to interest in the amount prescribed by [the CDA] upon the award we will make once the DOL determines the amount of back wage liability.” Schliecher Cmty. Corrections Ctr., Inc., 2002 WL 1860449, DOTBCA No. 3067, 02-2 BCA ¶ 31,902 (June 19, 2002). Schleicher appealed the adverse aspects of the Board’s decision, and we affirmed. Schleicher Cmty. Corr. Ctr., Inc. v. Ashcroft, 96 Fed.Appx. 718 (Fed.Cir.2004).

Subsequently, DOL completed its determination of the wages and fringe benefits due Schleicher’s employees, and the Board asked the parties to submit briefs addressing the outstanding quantum issues, including CDA interest in light of Richlin Security Services Co., 2004 WL 1638067, DOTBCA No. 3034, 04-2 BCA ¶ 32,670 (July 22, 2004), a subsequent opinion, since affirmed by this court, Richlin Security Service Co. v. Chertoff, 437 F.3d 1296 (Fed. Cir.2006), in which the Board held that a contractor was not entitled to receive CDA interest on unpaid back wages or associated taxes.

Determining that the ruling in Richlin was applicable to this case, the Board revisited its earlier decision awarding Schleicher CDA interest, and held that Schleicher could not recover CDA interest since it had not advanced its own funds to pay the underlying wages, benefits, and taxes. The Board also addressed an inconsistency in its earlier opinion, in which the summary stated that Schleicher was entitled to profit upon all of the increased wages, taxes, insurance, and other costs associated with the incorporation and subsequent revisions of the wage determination, but the body of the opinion held that only the increased wages resulting from the belated incorporation of the wage determination were subject to profit. Recognizing this inconsistency, the Board’s second opinion limited Schleicher’s profit on the increased wages to the first year of the contract alone, consistent with the holding in the body of its earlier opinion.

Pursuant to 41 U.S.C. § 607(g)(1)(A), Schleicher appeals the Board’s decision to this court. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(10).

II. DISCUSSION

A

The standard of review in cases under the Contract Disputes Act is governed by 41 U.S.C. § 609(b). As to questions of fact, if the Board’s factual findings are supported by substantial evidence, we will *975 not alter them unless the decision “is fraudulent, arbitrary, capricious, or so grossly erroneous as to necessarily imply bad faith.” Id.; see Fruin-Colnon Corp. v. United States, 912 F.2d 1426, 1428-29 (Fed.Cir.1990). As to questions of law, however, the Board’s decision is not final or conclusive. Am. Elec. Labs., Inc. v. United States, 774 F.2d 1110, 1112 (Fed. Cir.1985). Although “we give careful consideration and great respect to a board’s interpretation!;,]” Fruin-Colnon, 912 F.2d at 1429, the interpretation of the CDA is a matter of law reviewed de novo by this court. Abraham v. Rockwell Int'l Corp. 326 F.3d 1242, 1249 (Fed.Cir.2003); 41 U.S.C. § 609(b).

B

On appeal, Schleicher challenges the Board’s opinion on three grounds: (1) that the Board’s original opinion was final and could not be revisited by the Board; (2) that the Board erred on the merits in denying Schleicher interest under the CDA; and (3) that the Board erred on the merits in limiting Schleicher’s profit to the first year of the contract. We take each issue in turn.

1. Finality of the Board’s Original Opinion

Schleicher argues that the Board erred when it decided Schleicher could not receive CDA interest on unpaid wages, fringe benefits, and associated taxes because that issue had been finally decided in the Board’s June 19, 2002 opinion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
212 F. App'x 972, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schleicher-community-corrections-center-v-department-of-justice-cafc-2007.