North American Landscaping Construction & Dredge Company, Inc. v. United States

CourtUnited States Court of Federal Claims
DecidedMarch 15, 2019
Docket17-903
StatusPublished

This text of North American Landscaping Construction & Dredge Company, Inc. v. United States (North American Landscaping Construction & Dredge Company, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North American Landscaping Construction & Dredge Company, Inc. v. United States, (uscfc 2019).

Opinion

In the United States Court of Federal Claims No. 17-903C

(E-Filed: March 15, 2019)

) NORTH AMERICAN ) Contract; Contract Disputes Act of LANDSCAPING, ) 1978, 41 U.S.C. §§ 7101-7109 CONSTRUCTION AND DREDGE ) (2012); Dredging Contract; COMPANY, INC., ) Differing Site Condition Claim; ) Superior Knowledge Claim; Barge Plaintiff, ) Traffic Delay Claim; Severe ) Weather Delay Claim; Completion v. ) Survey Delay Claim; Return of ) Liquidated Damages Claim; THE UNITED STATES, ) Equitable Adjustment Claim; ) Re-dredged Quantity Costs Claim; Defendant. ) Summary Judgment; RCFC 56. )

Joseph L. Katz, Columbia, MD, for plaintiff.

Daniel B. Volk, Trial Attorney, with whom were Joseph H. Hunt, Assistant Attorney General, Robert E. Kirschman, Jr., Director, and Elizabeth M. Hosford, Assistant Director, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, for defendant. Mark R. Higgins, United States Army Corps of Engineers, Norfolk, VA, of counsel.

OPINION

CAMPBELL-SMITH, Judge.

This matter is before the court on defendant’s motion for summary judgment, ECF No. 11, and plaintiff’s cross-motion for summary judgment, ECF No. 18, filed pursuant to Rule 56 of the Rules of the United States Court of Federal Claims (RCFC). Defendant filed a response/reply brief, ECF No. 21, and plaintiff filed a reply brief, ECF No. 22. Both parties filed exhibits in support of their motions: (1) defendant’s appendix is found at ECF Nos. 11-2, 12-1, and 12- 2; (2) plaintiff’s exhibits are found at ECF Nos. 18-1 through 18-4; and, (3) a declaration filed in support of defendant’s response/reply brief is found at ECF No. 21-1. The parties’ motions address liability, not damages, deferring any discovery regarding damages until the question of the liability of the government has been addressed by the court. See ECF No. 9 at 2 (joint motion describing the government’s motion as a motion for summary judgment, and plaintiff’s motion as a “cross-motion for partial summary judgment as to liability”). This matter is fully briefed and ripe for decision. For the reasons set forth below, defendant’s motion for summary judgment is GRANTED in part and DENIED in part, and plaintiff’s cross-motion is DENIED.

I. Background 1

The contract at issue here was awarded after sealed bids were received in response to Solicitation No. W91236-15-B-0009, for maintenance dredging of Hoskins Creek, Tappahannock, VA. ECF No. 12-1 at 68. This procurement was a firm, fixed price contract opportunity set aside for small businesses. Id. at 66, 68, 77. The solicitation was issued by the United States Army Corps of Engineers, Norfolk District (Corps). Id. at 66. The contract, W91236-15-C-0038, was awarded to plaintiff North American Landscaping, Construction and Dredge Company, Inc. (NALCO). ECF No. 1 at 2 (complaint). Several provisions of the solicitation and resulting contract are of relevance to plaintiff’s claims.

Most importantly, the contract provisions which discussed boat traffic on the navigable waterway also required the contractor to obstruct the passage of boats and barges as little as possible, and to stop dredging when necessary to allow the passage of such vessels. See ECF No. 12-1 at 330 (“The Contractor shall expect that the [shallow draft fishing vessels, pleasure craft, tugs, grain barges, and various other small crafts] traffic will cause periodic delays and interruptions of his operations.”); id. (“The Contractor will be required to conduct the work in such manner as to obstruct navigation as little as possible, and in case the Contractors’ plant so obstructs the channel as to make difficult or endanger the passage of vessels, said plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage.”).

Further, the solicitation predicted that the project would take less than 30 days to complete. Id. at 74. The contract duration, however, was set at 120 calendar days. Id. at 66, 68. The contract documents signed by NALCO required the work to be completed within 120 days of the issuance of the Notice to Proceed, which in this case was effective on June 4, 2015. Id. at 362, 394. Thus, NALCO was on notice that the deadline for contract completion was set for October 2,

1 The facts recounted here are taken from the parties’ exhibits. The facts supporting the parties’ arguments are mostly undisputed, because the parties’ briefing focuses primarily on legal disputes, not factual disputes.

2 2015. Id. at 394. The solicitation, and the contract, contained a liquidated damages clause which specified that the contractor would pay the government $300 per day for each day beyond the completion deadline that the contract work was not “completed or accepted.” Id. at 97, 378.

Bidders were encouraged “to visit the site of the work in order to acquaint themselves as to site conditions and other problems incident to the prosecution of the work.” Id. at 71. At least one bidder visited the site of Hoskins Creek and submitted a question to the Corps about the project based on that site visit. Id. at 346-47. NALCO’s president avers that he visited the site “several times” before submitting NALCO’s bid. ECF No. 18-1 at 2. Among the standard contract clauses included in the solicitation was the Site Investigation and Conditions Affecting the Work clause, 48 C.F.R. § 52.236-3 (2017). ECF No. 12-1 at 88.

When NALCO submitted its bid, there was some hesitation among Corps personnel who were not certain that NALCO was capable of completing the contract work. See, e.g., id. at 356 (“I do not feel they have answered the [Pre- Award Survey] questions and provided sufficient detail to make a decision as to whether or not they are a responsi[ble] bidder.”). One specific concern was the technology proposed by NALCO:

In reviewing the capability of [NALCO’s proposed] Ellicott dredge 670, it does not appear to have the performance characteristics to complete this work. Went to the Ellicott Dredges website and found the performance curve for this dredge. For fine sand, silts, and clays (not clay balls) at 12,000 feet pumping distance, the theoretical production rate from the manufacturer’s literature is 100 cubic yards per hour; most efficient pumping rate (no or short distance) is about 600 cubic yards per hour. At 12,000 feet of pumping distance, they would be operating at a very poor efficiency.

Our project conditions are 13,000 feet AND a static head of 45 feet, outside the parameters of the manufacturer’s literature. I think it is reasonable to ask how the Contractor intends to be successful with these less than marginal conditions.

Id. at 358.

Other concerns were NALCO’s ability to perform the contract work within the scheduled timeframe, and whether the final phase of the project would prove to be too challenging for NALCO:

3 Still will be monitoring schedule and production very closely, as this seems to be the challenge for them on several others Federal dredging projects.

In particular, I believe the challenge will be those longer dredging pipeline distances when they are working on the outer reach of the project. With that stated, they will likely start at the beginning of the navigation project, pipeline distance will be shortest.

Id. at 360. After meeting with NALCO to gather further information as to NALCO’s plan for the contract work, the Corps concluded that NALCO could complete the project:

I think the meeting went well. NALCO understands the [projects’] requirement . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Perry and Wallis, Inc. v. The United States
427 F.2d 722 (Court of Claims, 1970)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Sweats Fashions, Inc. v. Pannill Knitting Company, Inc.
833 F.2d 1560 (Federal Circuit, 1987)
Dairyland Power Cooperative v. United States
16 F.3d 1197 (Federal Circuit, 1994)
Comtrol, Inc. v. United States
294 F.3d 1357 (Federal Circuit, 2002)
Duhame v. United States
119 F. Supp. 192 (Court of Claims, 1954)
R.P. Wallace, Inc. v. United States
63 Fed. Cl. 402 (Federal Claims, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
North American Landscaping Construction & Dredge Company, Inc. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-american-landscaping-construction-dredge-company-inc-v-united-uscfc-2019.