C.R. Pittman Construction Co., Inc.

CourtArmed Services Board of Contract Appeals
DecidedFebruary 4, 2015
DocketASBCA No. 57387, 57388, 57688
StatusPublished

This text of C.R. Pittman Construction Co., Inc. (C.R. Pittman Construction Co., Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C.R. Pittman Construction Co., Inc., (asbca 2015).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) C.R. Pittman Construction Co., Inc. ) ASBCA Nos. 57387, 57388, 57688 ) Under Contract No. DACW29-00-C-0075 )

APPEARANCES FOR THE APPELLANT: Gerald A. Melchiode, Esq. Jeffery B. Struckhoff, Esq. Galloway, Johnson, Tompkins, Burr & Smith New Orleans, LA

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney William G. Meiners, Esq. Engineer Trial Attorney U.S. Army Engineer District, New Orleans

OPINION BY ADMINISTRATIVE JUDGE WILSON

These appeals originate from claims filed under a construction contract for improvements to the Soniat Canal in Jefferson Parish, Louisiana. 1 The contract required, inter alia, C.R. Pittman Construction Co., Inc. (appellant or Pittman) to increase the drainage capacity of the existing drainage canal by lining it with concrete and increasing the cross-sectional area by excavation. Appellant filed three claims alleging the following: (1) a Type II differing site condition regarding removal of sheet piling (ASBCA No. 57387); (2) delays due to flood events (ASBCA No. 57388); and (3) breach of contract by the Corps due to the deletion of gravity sewer line work from the contract (ASBCA No. 57688). The Board has jurisdiction of the appeals under the Contract Disputes Act of 1978, 41 U.S.C. §§ 7101-7109. The Board held a hearing in New Orleans, Louisiana, on the above-captioned appeals. The parties have submitted post-hearing and reply briefs. Only entitlement is before the Board for decision.

1 The Board previously issued a decision under the same contract denying entitlement to additional delay costs associated with timber mats. See C.R. Pittman Constr. Co., ASBCA No. 54901, 08-1BCA~33,777. Familiarity with that decision is presumed. FINDINGS OF FACT

A. The Contract

1. On 25 July 2000, the United States Army Corps of Engineers (government or Corps) awarded Contract No. DACW29-00-C-0075 to appellant in the amount of $14,426,258 for the "Southeast Louisiana Urban Flood Control Project, Improvements to Soniat Canal" in Jefferson Parish, Louisiana (R4, vol. II, tab D). The fixed-price contract required appellant to increase the drainage capacity of the existing drainage canal by lining the canal with concrete and increasing the canal cross-sectional area by shallow excavation. Upon completion of the project, the canal would convey storm runoff from Metairie, Louisiana, towards a pumping station in Jefferson Parrish and ultimately into Lake Pontchartrain. (ASBCA No. 57387 (57387), compl. and answer ii 8; tr. 1/28) The contract further required completion of the work within 900 calendar days of the receipt of "Notice to Proceed," which was issued and received on 28 July 2000 (57387, compl. ii 9; supp. R4, tab 3; R4, vol. II, tab D). Thus the contract completion date was 14 January 2003.

2. The contract contained the following standard clauses: Federal Acquisition Regulation (FAR) 52.233-1, DISPUTES (DEC 1998); FAR 52.243-4, CHANGES (AUG 1987); Defense Federal Acquisition Regulation Supplement (DF ARS) 252.243-7001, PRICING OF CONTRACT MODIFICATIONS (DEC 1991 ); and DF ARS 252.243-7002, REQUESTS FOR EQUITABLE ADJUSTMENT (MAR 1998) (R4, vol. II, tab D).

3. The contract contained the standard FAR 52.232-5, PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MA y 1997) clause, which stated in relevant part:

(1) The Contractor's request for progress payments shall include the following substantiation:

(i) An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment requested.

(2) In the preparation of estimates, the Contracting Officer may authorize material delivered on the site and preparatory work done to be taken into consideration ....

2 (f) Title, liability and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government. ...

(R4, vol. II, tab D at 58-60) The contract also contained FAR 52.236-2, DIFFERING SITE CONDITIONS (APR 1984) which reads:

(a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of ( 1) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract, or (2) unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract.

(b) The Contracting Officer shall investigate the site conditions promptly after receiving the notice. If the conditions do materially so differ and cause an increase or decrease in the Contractor's cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, an equitable adjustment shall be made under this clause and the contract modified in writing accordingly.

(Id. at 73)

4. Additionally, the contract contained the following special provision in pertinent part:

52.231-5000, EQUIPMENT OWNERSHIP AND OPERA TING EXPENSE SCHEDULE (MAR 1995)-- EFARS

(b) Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the contractor's accounting records.

3 When both ownership and operating costs cannot be determined ... costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region III.

(R4, vol. II, tab D at 58)

B. Additional Findings of Fact Pertaining to ASBCA No. 57387 Type II Differing Site Condition (Sheet Piling) Claim

5. The contract also contained the following provision:

SECTION 02252 -TEMPORARY RETAINING STRUCTURES

PART 1 GENERAL

1.1 SCOPE

This work shall consist of designing, furnishing, installing, maintaining and subsequently removing all temporary retaining structures required to complete this project. The Contractor shall be solely responsible for the design, layout, construction, maintenance and subsequent removal and disposal of all elements of the temporary retaining structures.

1.2 MEASUREMENT AND PAYMENT

No measurement will be made for work specified in this section. Payment will be made at the contract lump sum price for "Temporary Retaining Structures". Price and payment shall constitute full compensation for furnishing all plant, labor, materials, and equipment; designing, furnishing, installing, maintaining, and removing the temporary retaining structures, backfilling voids, and all other work incidental thereto.

4 1.4.2 Elevations

The retaining structures shall have sufficient height to retain the soil between them. The minimum tip elevation shall be (-) 52 feet C.D.

PART3 EXECUTION

3 .2 REMOVAL OF MATERIAL

3.2.1 Removal Criteria

... All Contractor-furnished temporary retaining structures shall be removed from the site of work upon completion of work.

3.2.2 Safety

The removal of the temporary retaining structures shall be accomplished in a manner not injurious to the properties adjacent to and in the proximity of the project excavations.

(R4, vol. II, tab D at 232-33, 235) Additionally, Section 02252 was amended (via Amendment No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
C.R. Pittman Construction Co., Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/cr-pittman-construction-co-inc-asbca-2015.