First Street Contractors, LLC

CourtArmed Services Board of Contract Appeals
DecidedFebruary 20, 2026
Docket64028
StatusPublished

This text of First Street Contractors, LLC (First Street Contractors, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First Street Contractors, LLC, (asbca 2026).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - ) ) First Street Contractors, LLC ) ASBCA No. 64028 ) Under Contract No. W912P6-20-C-0021 )

APPEARANCES FOR THE APPELLANT: Jonathan R. Neri, Esq. Lauren R. Brier, Esq. Josephine R. Farinelli, Esq. PILIEROMAZZO PLLC Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Ian T. McDaniel, Esq. Engineer Trial Attorney U.S. Army Engineer District, Chicago

OPINION BY ADMINISTRATIVE JUDGE SWEET ON THE PARTIES’ CROSS-MOTIONS FOR SUMMARY JUDGMENT

This appeal involves a contract between appellant, First Street Contractors, LLC (First Street) and the United States Army Corps of Engineers (Corps) for First Street to replace existing grit dewatering equipment at the Gary Sanitary District’s wastewater treatment plant in Gary, Indiana. First Street claims that the Corps: (1) provided defective specifications because the contract drawings allegedly showed openings in the existing concrete floor that were larger than grit pumps that First Street had to place below the concrete floor, when the existing concrete floor openings actually were smaller than the grit pumps (Concrete Floor Openings Claim) 1 (compl. ¶¶ 65-78); (2) constructively changed the contract by requiring that valves larger than three inches be glass lined (Glass Lined Valve Claim) (id. ¶¶ 100-144); and

1 First Street also alleges a Type I differing site condition claim regarding the concrete floor openings (compl. ¶¶ 79-99). When an appellant alleges both a defective specifications claim and a differing site condition claim, and the claimed defect in the specifications is a failure to disclose the alleged differing site condition, the two claims collapse into a single differing site condition claim. Meridian Eng’g Co. v. United States, 885 F.3d 1351, 1361 (Fed. Cir. 2018). Thus, as the parties agree we should do, we treat First Street’s defective specifications and differing site condition claims regarding the concrete floor openings as a differing site condition claim (gov’t mot. at 22; app. mot. at 16). (3) constructively changed the contract by requiring First Street to provide continual watch services for a temporary grit pump (Temporary Grit Pump Watch Services Claim) (id. ¶¶ 145-167). The parties have cross-moved for summary judgment on the Concrete Floor Openings, Glass Lined Valve, and Temporary Grit Pump Watch Services Claims.

For the reasons discussed below, we deny the parties’ cross-motions for summary judgment on the Concrete Floor Openings Claim because there are genuine issues of material fact as to whether First Street reasonably interpreted and relied upon the contract documents to conclude that the existing concrete floor openings were larger than the grit pumps, and whether the existing concrete floor openings being smaller than the grit pumps was reasonably foreseeable based upon all the information available at the time of bidding. We also deny the parties’ cross-motions for summary judgment on the Glass Lined Valve Claim because the contract is ambiguous as to whether valves larger than three inches had to be glass lined, and there is a genuine issue of material fact as to whether, based upon extrinsic evidence, a reasonable contractor in First Street’s position would have interpreted the ambiguous contract to require that valves larger than three inches be glass lined. Finally, we deny the parties’ cross-motions regarding the Temporary Grit Pump Watch Services Claim because there is a genuine issue of material fact as to whether the Corps’ direction that First Street provide continuous temporary grit pump watch services required work beyond the contract’s requirement.

For the reader’s convenience, we will address the facts and analysis of each claim together.

CONCRETE FLOOR OPENINGS CLAIM

I. Concrete Floor Openings Claim Statement of Facts (SOF) for Purposes of Deciding the Motions

1. On August 20, 2020, the Corps issued Solicitation No. W912P620B0020 (Solicitation) for a contractor to replace the existing grit dewatering equipment 2 at the Gary Sanitary District wastewater treatment plant in Gary, Indiana with higher capacity and more robust equipment (SMF ¶¶ 1, 4 (citing R4, tab 1 at 1)). 3 The grit dewatering equipment was located inside the Detritor Building (SMF ¶ 5).

2 Grit dewatering equipment transports and treats grit, or sewage. It consists of detritor tanks to hold the grit, pumps to move the grit, and pipes to transfer the grit to a classifier where it is treated (SMF ¶ 6). 3 “SMF” refers to the joint stipulation of material fact. 2 2. The Solicitation included a clause pursuant to Federal Acquisition Regulation (FAR) 52.236-27, which provided bidders the opportunity to arrange site-visits (SMF ¶ 18 (citing R4, tab 1 at 14)). However, given the ongoing COVID-19 pandemic, First Street attended a virtual pre-bid meeting on September 2, 2020, in place of an in-person inspection (SMF ¶ 19).

3. The specifications in the Solicitation required First Street to provide and install two new Smith & Loveless, Inc. (Smith & Loveless) 6D3J Pista turbo grit pumps (Grit Pumps) below an existing concrete floor, which contained two openings through which First Street had to lower the Grit Pumps (SMF ¶¶ 11, 13-15; R4, tab 2 at 975, tab 3). In particular, Drawing Sheet M-5 (DETRITOR BUILDING GRIT NEW WORK – PLANS) depicted the floor plan for the wastewater treatment plant pump room as follows:

(R4, tab 3 at 1; see also SMF ¶ 13) Drawing Sheet M-6 (DETRITOR BUILDING GRIT NEW WORK – SECTIONS) included the following depiction of the Grit Pumps and concrete floor openings in the wastewater treatment plant pump room:

3 (R4, tab 3 at 2; see also SMF ¶ 14). Drawing Sheet M-6 labeled certain features, such as: “Grit Pump,” “Grit Pump Local Control Station,” and “6”-Grit-DI-Discharge”; and appears to show those features with darker lines than other, unlabeled features, such as what appears to be stairs, railings, walls, floors, floor openings (R4, tab 3 at 2). Drawing Sheet M-2 (MECHANICAL NOTES AND PIPE AND VALVE SCHEDULES) stated, under “Demolition Notes,” that “[d]imensions and locations of existing equipment, appurtenances and structures have been obtained from existing record drawings and field survey. All should be field verified.” (R4, tab 10 at 34 (emphasis omitted)) Drawing Sheet M-2 also stated under “Demolition Notes,” that “[i]t is not warranted that the locations and dimensions of existing equipment, appurtenances and structures are exact. It is the responsibility of the contractor to field verify all dimensions and locations of existing piping, equipment, electrical conduits, HVAC, Ducts, etc. as required to be removed for the new construction.” (Id. (emphasis omitted)) The Contract also includes demolition plans, including for the Detritor Building; although those plans do not appear in the record (R4, tab 4 at 25-26).

4 4. The specifications and drawings did not provide numerical dimensions for the Grit Pumps (SMF ¶ 12), and were silent as to whether First Street had to obtain information about the Grit Pumps’ dimensions from Smith & Loveless (id. at ¶ 20 (citing R4, tabs 1-1.5)). Moreover, Smith & Loveless did not provide First Street with a drawing indicating the Grit Pumps’ dimensions (SMF ¶ 22). Nor did the contract documents provide numerical dimensions for the existing concrete floor openings (SMF ¶ 15), or specifically identify the need to perform demolition on the existing concrete floor (id. at ¶16).

5. On September 30, 2020, the Corps awarded Contract No. W912P620C0021 (Contract) to First Street (SMF ¶ 9 (citing R4, tab 4)), based upon the Solicitation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Hol-Gar Manufacturing Corp. v. The United States
351 F.2d 972 (Court of Claims, 1965)
Pacific Alaska Contractors, Inc. v. The United States
436 F.2d 461 (Court of Claims, 1971)
Pure Gold, Inc. v. Syntex (u.s.a.), Inc.
739 F.2d 624 (Federal Circuit, 1984)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Beta Systems, Inc. v. The United States
838 F.2d 1179 (Federal Circuit, 1988)
C. Sanchez and Son, Incorporated v. United States
6 F.3d 1539 (Federal Circuit, 1993)
H.B. Mac, Inc. v. United States
153 F.3d 1338 (Federal Circuit, 1998)
Varilease Technology Group, Inc. v. United States
289 F.3d 795 (Federal Circuit, 2002)
Comtrol, Inc. v. United States
294 F.3d 1357 (Federal Circuit, 2002)
Coast Federal Bank, Fsb v. United States
323 F.3d 1035 (Federal Circuit, 2003)
Turner Construction Co., Inc. v. United States
367 F.3d 1319 (Federal Circuit, 2004)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)
bell/heery v. United States
739 F.3d 1324 (Federal Circuit, 2014)
Meridian Engineering Company v. United States
885 F.3d 1351 (Federal Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
First Street Contractors, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-street-contractors-llc-asbca-2026.