Total Engineering, Inc. v. United States

120 Fed. Cl. 10, 2015 U.S. Claims LEXIS 30, 2015 WL 328216
CourtUnited States Court of Federal Claims
DecidedJanuary 26, 2015
Docket13-881C
StatusPublished
Cited by7 cases

This text of 120 Fed. Cl. 10 (Total Engineering, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Total Engineering, Inc. v. United States, 120 Fed. Cl. 10, 2015 U.S. Claims LEXIS 30, 2015 WL 328216 (uscfc 2015).

Opinion

Subject Matter Jurisdiction; Contract Disputes Act; Government Claim; Deductive Credit; 48 C.F.R. § 2.101; Contracting Officer’s Final Decision; Failure to State a Claim Upon Which Relief Can Be Granted; Rule 8.

OPINION AND ORDER

WILLIAMS, Judge.

This action under the Contract Disputes Act (“CDA”) comes before the Court on Defendant’s motion to dismiss Plaintiff Total Engineering Inc.’s (“Total”) Amended Complaint. Plaintiff appeals the Contracting Officer’s Final Decision demanding payment of $2,301,209 as a deductive credit due to Total’s defective work. Plaintiff alleges that its work was not defective, that the Government’s design specifications were flawed, and seeks payment of the contract balance of $737,838.75, which the Government deducted from the amount it claims from Plaintiff.

The Government seeks dismissal, arguing that Total’s Amended Complaint raises contractor claims which were not submitted to the Contracting Officer as required by the CDA. Specifically, Defendant contends that both Total’s defense of defective specifications and its challenge to the Government’s retention of the contract balance should be treated as independent contractor claims. Because Defendant misconstrues Plaintiffs defective specification defense and the Government’s set-off of the contract balance as independent contractor claims, the Court denies the Government’s motion.

Background

In early 2009, the United States Army Corps of Engineers (“Agency”), solicited proposals for the construction of the United States Army Medical Research Institute of Chemical Defense Replacement Facility, located at the Aberdeen Proving Grounds in Edgewood, Maryland. Am. Compl. ¶ 4. The Replacement Facility will be the “Department of Defense’s lead laboratory for medical chemical defense research, and the location for the development, testing, and evaluation of medical treatments and materials to prevent and treat casualties of chemical warfare.” COFD 1 ¶ 1. The work on this project was split into two separate contracts — the Early Site Package and the Primary Building Package. Am. Compl. ¶¶ 5-6. On April 10, 2009, the Agency awarded Total contract No. W912DR-09-C-0030 for the Early Site Package. Id. at ¶ 8. The Primary Building Package was awarded to Clark Construction Group (“Clark”). Id. at ¶ 7.

The contract required Total to perform a variety of work, including demolishing existing structures, removing hazardous materials, excavating soils, installing erosion and sediment controls, and constructing a new steam line system, comprised of a 10-inch steam line and 6-inch condensate line anchored to concrete piers installed parallel to each other inside a concrete trench. Id. at ¶¶ 9, 12-13.

Total Engineering was also required to: Submit detail drawings for valve manholes and the piping and equipment in the valve manholes, such as steam traps, valves, sump pumps, pressure gauges, thermometers and insulation, including a complete list of equipment and materials, manufacturer’s descriptive and technical literature, performance charts and curves, catalog cuts, installation instructions, and complete wiring and schematic diagrams. Show on the drawings pipe anchors and guides, and layout and anchorage of equipment and appurtenances in valve manholes, and equipment relationship to other parts of the work including clearances for maintenance and operation.

COFD ¶ 7.

According to the Contracting Officer, several deficiencies in Total’s steam line work were brought to Total’s attention in late May and early June 2010. Id. at ¶ 10. During a required hydrostatic pressure test, conducted by Total’s subcontractor, L.J. Brossoit & Sons, Inc., on June 17, 2010, Agency personnel “saw cracking in the piers, movement of *13 the pipe, and noticed damage on the anchor support in manhole 2.” Id. at ¶ 11. It was “evident that the [s]team [l]ine had dislodged from its anchors and concrete piers at several points along the underground portion” of the steam line. Id. Failure of the anchor points resulted in the steam line moving inside its trench. Id. Total alleges that “[t]he Government’s faulty pier design — and specifically the Government-furnished drawings and designs for the below-ground pipe and concrete anchor support piers, including Pier 85, and anchor support piers located in Manholes 2 and 4” was the most probable cause of the failure. Am. Compl. ¶ 16.

The Contracting Officer’s Final Decision details events that occurred after the hydrostatic pressure test. On June 18, 2010, the Agency, L.J. Brossoit & Sons, Inc., and Total personnel met to discuss alleged deviations from the construction design. COFD ¶ IS. On July 9, 2010, the Government’s designer prepared a report, which found that the cause of the construction failures was Total’s deficient work. 2 Id. at ¶ 15.

On July 26, 2010, the Contracting Officer issued a cure letter allowing Total 14 days to fix the defective steam line, stating that if Total did not cure the identified work, the Government might elect to terminate the contract for default or modify the contract “to remove unfinished work and assign it to another contractor_” Id. at ¶28. According to the Government, Total’s work remained “unsatisfactory” during that 14-day period. Id. at ¶ 29.

On August 19, 2010, the Agency issued a change order requiring Total to cease construction of the steam line, stating: “ ‘[g]iven these circumstances, it is the decision of the Contracting Officer to modify the contract to remove the new steam system and all features of the work required to render it operational. This modification will be in accordance with Contract Clause 52.243-4 Changes.’ ” Am. Compl, ¶ 17. The steam line portion of the contract was then assigned to Clark. COFD, ¶ 31. On October 8, 2010, the Agency sent Total a “Request for Proposal (RFP)-BF” for the amount of a deductive credit. Id. at ¶ 35, 43. Total eventually responded to RFP BF on May 29, 2011, proposing a deductive credit of $80,047.21 and revised its proposal on July 8, 2011, proposing a deductive credit of $521,726.45 for the steam line work removed from its contract. Id. at ¶¶ 45,48.

After Total submitted a payment request, the Agency sent Total a letter on August 24, 2010, stating that the pending modification for steam system work was anticipated at $425,000. Id. at ¶ 32. On March 28, 2011, the Agency informed Total that “due to the increasing discovery of deficiencies in Total’s previous [s]team [l]ine work, the cost to obtain an operable steam line could reach as high as two million dollars ($2,000,000).” Id. at ¶ 42. The Agency terminated Total’s contract for default on August 10, 2011. Id. at ¶ 51. 3 On December 28, 2011, the Agency issued a second RFP to Total, which included additional work not previously identified in RFP BF. Id. at ¶ 58. 4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
120 Fed. Cl. 10, 2015 U.S. Claims LEXIS 30, 2015 WL 328216, Counsel Stack Legal Research, https://law.counselstack.com/opinion/total-engineering-inc-v-united-states-uscfc-2015.