Central Trust Co. v. Louisville, St. L. & T. Ry. Co.

70 F. 282, 1895 U.S. App. LEXIS 3188
CourtU.S. Circuit Court for the District of Kentucky
DecidedOctober 1, 1895
DocketNos. 6,345, 6,346
StatusPublished
Cited by10 cases

This text of 70 F. 282 (Central Trust Co. v. Louisville, St. L. & T. Ry. Co.) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the District of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Central Trust Co. v. Louisville, St. L. & T. Ry. Co., 70 F. 282, 1895 U.S. App. LEXIS 3188 (circtdky 1895).

Opinion

BARR, District Judge.

This intervening petition claims that the railway company on the 23d of July, 1892, made a contract with H. M. McCracken, who agreed to procure the necessary right of way for an extension of its line from its terminus at West Point, at a place called Howard, across to a junction with the Louisville & Hashville Railroad,' and also agreed to erect a bridge across Salt river. McCracken was to construct and complete said extension to the Hashville Railroad, and get therefor, from the railroad com-' pany, $25;000 of its first mortgage 6 per cent, bonds, and $25,000 of its capital stock, for each mile of road thus constructed. On the 6th of October, 1892, McCracken entered into an agreement with the interveners Mchols, Watkins & Co., to construct, in a substantial and workmanlike manner, to the satisfaction and ac[283]*283ceptance of the engineer in charge of the same, all the grading, clearing, grubbing, masonry in culverts and bridges, trestle-work, pile-driving, riprap, on the extension from Howard of the said defendant’s railway. In said contract the specifications and price of the work are given, and among other provisions are these:

“(20) * ⅞ * During the progress of the work, and until it is completed, there shall he monthly estimates, made hy the engineer In charge, of the quantity, character, and value of the work'done during the preceding month, or since the last monthly estimate, 90% of which value shall he paid the parties of the first part on or about the 20th day of each month, in this manner, — that is, paid under such regulations as may he agreed upon between the parties, and at such place as the party of the second part may appoint; and when the said work is completed, and so accepted by the engineer in charge, there shall he a final estimate made hy the engineer of the quantity, character, and value of said work, agreeably to the tonus of tins agreement, when the balance appearing to he due to the said parties of the first part shall be paid to them, upon their giving a release, under seal, to the jiarty of the second part, from all claims or demands whatsoever growing in any manner out of tins agreement. (21) The monthly estimates of the engineer shall be subject to correction by him in any subsequent monthly or final estimate. The monthly estimate being merely made out as a basis of payment on account, it will necessarily he only approximately correct as to quantity and value; pains being taken, however, to make them as accurate as possible. (22) The contractor shall render an account monthly, through the proper superintending- engineer, of any extra work which lie may have been authorized to do; and, to prevent disputes hereafter, it is hereby understood that no hills for extra work will he allowed unless authorized and ordered in writing by the engineer in charge, and the bill for said work presented at the end of the month in which the work was done, and approved hy said engineer.” “(28) The word ‘engineer,’ wherever used in this agreement, shall he understood to mean the chief engineer. Now, therefore, 'in consideration of these premises, tills agreement further witnosseth that the said H. M. McCracken hereby agrees with Nichols, Watkins, & Co., of the first part, that lie, the said II. M. McCracken, shall and will, for doing and performing the work aforesaid well and truly, pay, or cause to be paid, to the said Nichols, Watkins & Co., of the first part, their surviving partners, executors, or administrators, the following prices, viz. [Then follows a list of the prices for the different work, and following this, as follows:] The above payments shall be made in the following maimer; that is to say: [Then follows the language already first quoted herein.]”

The interveners allege that under this contract, and according to the schedule of prices therein, they have done work to the amount of $88,597.61, and also extra work amounting to $9,561.19, making a total of $98,148.80, and that there has been paid on account of extra work, $843.88, and on account of work specifically described in the contract, $47,355.80, leaving a balance due of $19,919.16. They do not allege that this amount is due according to the final estimate made by the chief engineer, but allege:

“That the chief engineer mentioned in said contract has made a final estimate of the work specifically included in the contract, and also given the vouchers for the extra work, and that through the failure of said engineer to properly measure said work included in tiie contract, and properly classify the same according to the terms and true intent thereof, the said final estimate and vouchers for said extra work are not as large as the true amount clue to your interveners according to the terms of said contract; but, through a mistake of said engineer, lie has, both in measurement and classification, made such amount to he much less than that which it correctly is, on proper measurement and classification.”

[284]*284The interveners claim a lien ior this balance on the property of the railway under the act of Kentucky approved March 27,1888. They allege that said railway company on the 1st of February, 1887, executed a deed of trust to the Central Trust Company, on its road which should be located and constructed from Louisville to Henderson, but provided that no extension of said road beyond the termini mentioned, to wit, Louisville and Henderson, or any branches which might be thereafter constructed, or any property or franchises pertaining exclusively to said extension of branches, should be deemed to be included in said conveyance, but same was expressly excepted therefrom, and that on the 24th of May, 1889, said railway company made, executed, and delivered a writing whereby they conveyed a branch line at Creen River to trustees for same purpose, which branch was about a mile in length, and on the 23d of August, 1892, executed to said trust company another deed of trust, in which it conveyed and mortgaged, all and singular, the main line of railway and branches of said railway, as then constructed or to be constructed, from Louisville to Henderson, or its eastern terminus; also, said railway company’s line of road purchased from the Louisville, Hardinsburg & Western Railway Company, from Irvington, in Breck-inridge county, Ky., and Fordsville, in Ohio county, Ky., and its branches, as now constructed, to Hardinsburg and Falls of Rough. It is alleged that under an arrangement between the railway company and the Central Trust Company, trustee in the deed of February 1, 1887, there were reserved 370 of the bonds secured by said deed of trust; that none of said bonds were issued until long after the year 1891, and all were unissued at the time said contract was entered into between said defendant railway company and said McCracken; that “whatever may be the right of any holder of bonds issued prior to the passage of the mechanic’s lien law, under which the interven-ers are claiming, the interveners say that in no event could the holders of these 370 bonds, or any of them, claim priority to these in-terveners, but are subject thereto.” '

This intervening petition is demurred to by the trust company, and several grounds presented, but the only ones which have been argued by counsel are those which raise the question of the finality of the chief engineer’s estimates, and the priority of the lien of in-terveners to the holders of the 370 bonds. It is insisted for the trust company that, by the terms of the contract between McCracken and the interveners, the final estimate is conclusive between the parties, and that no other or different amount can be recovered.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Massman Construction Co. v. Lake Lotawana Ass'n
210 S.W.2d 398 (Missouri Court of Appeals, 1948)
Penker Construction Co. v. United States
96 Ct. Cl. 1 (Court of Claims, 1942)
Landers-Morrison-Christenson Co. v. Ambassador H. Co.
214 N.W. 502 (Supreme Court of Minnesota, 1927)
Landers-Morrison-Christenson Co. v. Ambassador Holding Co.
214 N.W. 503 (Supreme Court of Minnesota, 1927)
Lovell v. Potts
207 P. 1006 (Oregon Supreme Court, 1924)
United States v. A. Bentley & Sons Co.
293 F. 229 (S.D. Ohio, 1923)
Algate v. City of Lansing
147 N.W. 561 (Michigan Supreme Court, 1914)
Central Trust Co. of New York v. Bodwell Water Power Co.
181 F. 735 (U.S. Circuit Court for the District of Maine, 1910)
Williams v. Mount Hood Ry. & Power Co.
110 P. 490 (Oregon Supreme Court, 1910)
General Fireproofing Co. v. L. Wallace & Son
175 F. 650 (Eighth Circuit, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
70 F. 282, 1895 U.S. App. LEXIS 3188, Counsel Stack Legal Research, https://law.counselstack.com/opinion/central-trust-co-v-louisville-st-l-t-ry-co-circtdky-1895.