Algate v. City of Lansing

147 N.W. 561, 180 Mich. 484, 1914 Mich. LEXIS 919
CourtMichigan Supreme Court
DecidedJune 1, 1914
DocketDocket No. 28
StatusPublished
Cited by2 cases

This text of 147 N.W. 561 (Algate v. City of Lansing) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Algate v. City of Lansing, 147 N.W. 561, 180 Mich. 484, 1914 Mich. LEXIS 919 (Mich. 1914).

Opinion

Steere, J.

Plaintiff, by a writ of error, seeks review and asks reversal of a judgment on a directed verdict rendered against him in the circuit court of Ingham county in an action brought upon a written contract entered into between him and defendant whereby he engaged to construct a sewer system for a portion of the city of Lansing according to certain plans and specifications made a part of said contract.

The' system, involving an expenditure of near $40,000, contemplated an egg-shaped, trunk sewer built of brick and concrete, 72 inches from top to bot[486]*486tom at the lower end, and gradually growing smaller as it receded from its outlet, with several laterals of tile extending from the main sewer in different directions.

The contract, following a form approved and adopted by the common council of the city of Lansing on October 11, 1909, is an elaborate document covering 20 pages of the printed record, very full and complete as to all matters involved in the undertaking, with specifications divided and subdivided under headings as to method of construction, workmanship, material, and other details relating to different branches of the work and the rights, duties, and responsibilities of the parties. It was executed May 9, 1910, requiring the work to be commenced June 1, 1910, and completed not later than November 30, 1911. Further reference will be made to such portions of this contract as become material to questions which it is necessary to pass upon or consider.

Performance of the contract was entered upon, and the work progressed, under plaintiff’s general control, but in direct charge of his son and other foremen; he being absent portions of the time looking after other contracts he had taken until July 10, 1911, when plaintiff took personal charge. About August 5th the city engineer, who was inspector by the terms of the contract, made objection to the manner in which certain work was done, and especially forbade the use of some red sand brick, in the trunk sewer, which was from the same brickyard but varied in color from that previously used. Just at that time the brickmakers were unable to furnish the light colored sand brick which had been previously used, and plaintiff, claiming that the red was just as good or better, more expensive, and fully complied with the specifications of the contract, continued its use for a time, until the other brick could be again furnished, building about 32 feet of the sewer with it.

[487]*487On August 10, 1911, the engineer sent plaintiff a written communication stating that on August 5th notice had been given him not to lay the red brick, and later to discontinue laying certain inverted stone in an unworkmanlike manner, with notice that no estimate would be given him for work done until the same was replaced according to specifications. This notice was received while plaintiff was unable to get the light brick, and he continued to use the red for a time thereafter, until authorized by the engineer to use a certain mud brick which the brickyard was able to furnish, when he continued with the latter, joining them to the red brick which he did not replace. During the time he was laying the mud brick the city engineer and chairman of the sewer committee were many times at the sewer and observed what was being done. The culminating and chief cause of friction between the parties appears to be plaintiff’s refusal to replace the red brick with others. On August 18th plaintiff made written application to the engineer for an estimate claimed due him under the contract, with which to obtain a partial payment “on work done on said sewer, and not previously estimated by you,” which was refused. Plaintiff continued the work for a time, until after the next meeting of the city council, and, being unable to secure an estimate or payment, withdrew his tools and men and discontinued work on September 1st, claiming defendant had violated the contract in not paying him the percentage due on work done according to the contract, and that he was unable to continue through lack of funds resulting from the city refusing to pay him money then due. On September 11th he received a communication of defendant, from the common council, inclosing a copy of a resolution directing him to proceed with his contract at once, or his bond for its faithful performance would be forfeited and he held responsible for all resulting damages. He sought legal advice, and on [488]*488September 14th. his attorney wrote the city engineer, stating the facts as plaintiff claimed them, and concluding :

“Kindly advise me, as Mr. Algate’s attorney, if you will now make these estimates and when. Also whether you do withdraw your objections as stated in said letter, or still insist on same. Also if you insist on work being replaced as stated in said letter.
“Mr. Algate is entitled to the information that he may know how to proceed and is entitled to his money, in order to continue to finance the work.”

On September 17th he sent to the city council copies of the correspondence and resolution accompanied by the following letter:

“Lansing, Mich., Sept. 17, 1911. “Hon. Common Council,
“City of Lansing.
“Gentlemen:
“Annexed you will please find copy of a letter to City Engineer Sparks; also copy of letter from said City Engineer Sparks to John Algate; also resolutions of common council to John Algate.
“Kindly advise us as to attitude of city in reference to matters mentioned in said letters. Your early advice will be kindly appreciated.”

This communication was received and placed on file, but not answered. On August 23, 1912, this action was begun.

By the opposing claims of these litigants, as set forth in their elaborate pleadings, each charges the other with numerous violations of their contract in many detailed particulars.

The theory of plaintiff’s declaration is a hostile attitude towards him manifested in the inspection of the work, which was unjust, captious, oppressive, and in effect fraudulent, in that proper material was repeatedly rejected, and the work objected to when being properly carried on in strict compliance with the contract; that the inspector hampered and interfered [489]*489with the progress of the work by abusive and profane language and brutal conduct towards plaintiff’s employees to an extent which rendered it difficult to keep men on the job, and captiously ordered work which complied with the contract to be changed and done again, refusing estimates and payments for work done, and not objected to, until such orders were obeyed, and by such refusal deprived plaintiff of the necessary means to continue.

The theory and claim of defendant, as indicated by its special notice under a plea of the general issue and lengthy cross-examination of plaintiff’s witnesses, is that plaintiff persisted in slighting the requirements of his contract by faulty construction and inferior material, in defiance or evasion of the inspector, repeatedly violating the terms of his contract, and finally, when compliance was insisted upon, abandoned it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lanzo Construction Co. v. City of Port Huron
276 N.W.2d 613 (Michigan Court of Appeals, 1979)
Porath v. Village of Highland Park
179 N.W. 229 (Michigan Supreme Court, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
147 N.W. 561, 180 Mich. 484, 1914 Mich. LEXIS 919, Counsel Stack Legal Research, https://law.counselstack.com/opinion/algate-v-city-of-lansing-mich-1914.