SCAFAR CONTRACTING, INC. v. CITY OF NEWARK v. MALCOM PIRNIE, INC. (L-6951-14, ESSEX COUNTY AND STATEWIDE)

CourtNew Jersey Superior Court Appellate Division
DecidedMarch 29, 2022
DocketA-1726-19
StatusUnpublished

This text of SCAFAR CONTRACTING, INC. v. CITY OF NEWARK v. MALCOM PIRNIE, INC. (L-6951-14, ESSEX COUNTY AND STATEWIDE) (SCAFAR CONTRACTING, INC. v. CITY OF NEWARK v. MALCOM PIRNIE, INC. (L-6951-14, ESSEX COUNTY AND STATEWIDE)) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SCAFAR CONTRACTING, INC. v. CITY OF NEWARK v. MALCOM PIRNIE, INC. (L-6951-14, ESSEX COUNTY AND STATEWIDE), (N.J. Ct. App. 2022).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-1726-19

SCAFAR CONTRACTING, INC.,

Plaintiff-Appellant,

v.

CITY OF NEWARK,

Defendant/Third-Party Plaintiff-Respondent,

MALCOM PIRNIE, INC., a/k/a ARCADIS U.S., INC.,

Third-Party Defendant. ______________________________

Argued October 4, 2021 – Decided March 29, 2022

Before Judges Messano, Rose, and Enright.

On appeal from the Superior Court of New Jersey, Law Division, Essex County, Docket No. L-6951-14.

Shawn R. Farrell argued the cause for appellant (Cohen Seglias Pallas Greenhall & Furman, PC, attorneys; Shawn R. Farrell, Jennifer R. Budd, and Gary J. Repke, Jr., on the briefs).

Morrison Kent Fairbairn argued the cause for respondent (Michael A. Armstrong & Associates, LLC, attorneys; Michael A. Armstrong and Morrison Kent Fairbairn, on the brief).

PER CURIAM

Plaintiff Scafar Contracting, Inc., submitted the lowest bid in response to

the City of Newark's request for bids (RFB) to construct a "Combined Sewer

Overflow" facility on .46 acres of open space at Clay Street, adjacent to the

Passaic River. The RFB's scope of work included the removal of an estimated

7,000 tons of non-hazardous soil and 10,000 tons of hazardous soil, and bidders

were required to submit per unit prices for each category of soil to be removed.

Plaintiff's bid was $9,987,834, based on quoted prices of $22/ton of non-

hazardous soil, and $123/ton for hazardous soil. The City accepted the bid, and

the parties executed a contract for that amount, which incorporated, with

exceptions we note below, the terms, conditions, specifications and other

information provided in the RFB.

Plaintiff completed the work, but disputes arose during its performance of

the contract, with plaintiff claiming that the City had superior knowledge of the

actual conditions of the soils which plaintiff was required to excavate and

A-1726-19 2 dispose of and failed to disclose these conditions. Plaintiff asserted the technical

reports made available at the time of the bid failed to disclose the actual

conditions at the site. As a result, plaintiff claimed its costs for installing a

cofferdam at the site and testing and disposing of the excavated material greatly

increased and generated delays that increased plaintiff's expenses in performing

the contract. Plaintiff filed a complaint against the City alleging breach of

contract, unjust enrichment, or alternatively, quantum meruit, and violation of

the Prompt Payment Act (PPA), N.J.S.A. 2A:30A-1 to -2. The City filed its

answer.1

Discovery ensued, and the City subsequently moved for summary

judgment. It contended under the terms of the incorporated RFB documents

plaintiff was not entitled to additional payments, and, furthermore, plaintiff's

failure to comply with the claim-notice provisions of the contract barred its

request for additional payment. Plaintiff cross-moved for partial summary

judgment, arguing the contract documents included a "Differing Subsurface or

1 The City later impleaded third-party defendants Malcom Pirnie, Inc., and Arcadis U.S., Inc., which later consolidated into a single company, Arcadis, served as the City's engineering consultant for the project. Shortly thereafter, the City dismissed its third-party complaint without prejudice. The case proceeded without Arcadis as a party, and the company has not participated in this appeal. A-1726-19 3 Physical Conditions" clause (the DSC clause), which entitled it to additional

payment for its expenses incurred because of unforeseen subsurface conditions.

Plaintiff also contended it substantially complied with the contract's claim-

notice provisions. The judge denied both motions, determining material

disputed facts existed requiring a trial.

Shortly before trial, which took place before a different judge, plaintiff

moved in limine to bar the City from introducing evidence of exculpatory

provisions in the contract, some of which we discuss below. The judge denied

the motion, concluding plaintiff essentially was seeking to relitigate the

arguments it made when it sought partial summary judgment. The case

proceeded to trial before a jury.

At the close of plaintiff's case, the City moved for a directed verdict.

Plaintiff voluntarily dismissed its claims for unjust enrichment and quantum

meruit, but otherwise opposed the motion. Although originally denying the

motion, after additional briefing, the judge dismissed plaintiff's PPA claim,

finding the statute did not apply to situations where the parties essentially

disagreed about the claimant's entitlement to payment. After testimony on the

defense case, the jury returned a no cause verdict in the City's favor on plaintiff's

breach of contract claim.

A-1726-19 4 Plaintiff moved for judgment notwithstanding the verdict (JNOV), or,

alternatively, for a new trial. In a brief oral opinion, the judge denied the motion

finding no miscarriage of justice.

Before us, plaintiff argues it was entitled to partial summary judgment as

a matter of law, because: 1) the DSC clause reflects the parties' anticipation that

the successful bidder could incur additional costs for undisclosed soil

conditions; 2) pursuant to federal case law and P.T. & L. Construction Co. v.

State of New Jersey Department of Transportation, 108 N.J. 539 (1987),

contractual exculpatory clauses cannot trump a DSC clause; and, 3) plaintiff

substantially complied with the contract's claim-notice provisions. Plaintiff also

argues the judge erred in denying the in limine motion to exclude evidence at

trial of the exculpatory clauses in the contract.

Plaintiff additionally contends the trial evidence did not support the

verdict, or, alternatively, it is entitled to a new trial because evidence presented

at trial regarding the exculpatory clauses "tainted the verdict by confusing the

jury as to the law." Lastly, plaintiff argues the judge erred in dismissing its PPA

claim.

We have considered the arguments in light of the record and applicable

legal standards. We affirm.

A-1726-19 5 I.

"Whether a summary judgment motion is granted, denied, or granted in

part and denied in part, an appellate court is limited to an examination of 'the

original summary judgment record.'" Noren v. Heartland Payment Sys., Inc.,

449 N.J. Super. 193, 196 (App. Div. 2017) (quoting Lombardi v. Masso, 207

N.J. 517, 542 (2011)). Our review of the motion judge's decision is de novo,

applying the same standard as he did, which

mandates that summary judgment be granted "if the pleadings, depositions, answers to interrogatories and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact challenged and that the moving party is entitled to a judgment or order as a matter of law."

[Templo Fuente De Vida Corp. v. Nat'l Union Fire Ins. Co. of Pittsburgh, 224 N.J. 189, 199 (2016) (quoting R. 4:46-2(c)).]

A dispute of material fact is "genuine only if, considering the burden of

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
Zabilowicz v. Kelsey
984 A.2d 872 (Supreme Court of New Jersey, 2009)
Ell-Dorer Contracting Co. v. State
484 A.2d 356 (New Jersey Superior Court App Division, 1984)
Frugis v. Bracigliano
827 A.2d 1040 (Supreme Court of New Jersey, 2003)
Green v. New Jersey Manufacturers Insurance
734 A.2d 1147 (Supreme Court of New Jersey, 1999)
SMC Corp. v. NJ WATER SUPPLY AUTH.
759 A.2d 1223 (New Jersey Superior Court App Division, 2000)
Velazquez v. Jiminez
763 A.2d 753 (New Jersey Superior Court App Division, 2000)
Do-Wop Corp. v. City of Rahway
773 A.2d 706 (Supreme Court of New Jersey, 2001)
Golomore Associates v. NJ State Highway Auth.
413 A.2d 361 (New Jersey Superior Court App Division, 1980)
Surkis v. Strelecki
277 A.2d 888 (New Jersey Superior Court App Division, 1971)
Konop v. Rosen
41 A.3d 773 (New Jersey Superior Court App Division, 2012)
Lombardi v. Masso
25 A.3d 1080 (Supreme Court of New Jersey, 2011)
Brill v. Guardian Life Insurance Co. of America
666 A.2d 146 (Supreme Court of New Jersey, 1995)
Risko v. Thompson Muller Automotive Group, Inc.
20 A.3d 1123 (Supreme Court of New Jersey, 2011)
L.J. Zucca, Inc. v. Allen Bros. Wholesale Distributors inc.
82 A.3d 274 (New Jersey Superior Court App Division, 2014)
Amratlal C. Bhagat v. Bharat A. Bhagat (068312)
84 A.3d 583 (Supreme Court of New Jersey, 2014)
Ads Associates Group, Inc. v. Oritani Savings Bank (069987)
99 A.3d 345 (Supreme Court of New Jersey, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
SCAFAR CONTRACTING, INC. v. CITY OF NEWARK v. MALCOM PIRNIE, INC. (L-6951-14, ESSEX COUNTY AND STATEWIDE), Counsel Stack Legal Research, https://law.counselstack.com/opinion/scafar-contracting-inc-v-city-of-newark-v-malcom-pirnie-inc-njsuperctappdiv-2022.