State Ex Rel. Cipriano v. Triad Mechanical, Inc.

925 P.2d 918, 144 Or. App. 106, 1996 Ore. App. LEXIS 1467
CourtCourt of Appeals of Oregon
DecidedOctober 16, 1996
Docket9306-04234; CA A84922
StatusPublished
Cited by11 cases

This text of 925 P.2d 918 (State Ex Rel. Cipriano v. Triad Mechanical, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Cipriano v. Triad Mechanical, Inc., 925 P.2d 918, 144 Or. App. 106, 1996 Ore. App. LEXIS 1467 (Or. Ct. App. 1996).

Opinions

[109]*109WARREN, P. J.

Triad Mechanical, Inc., appeals from a judgment dismissing its breach of contract and quantum meruit claims against the Oregon Department of Fish and Wildlife (ODFW). Before trial, the court granted ODFW’s motion under the parol evidence rule to exclude evidence of anything intended to contradict the terms of a written contract and change orders signed by ODFW and Triad. The trial court also ruled that two change orders constituted an accord and satisfaction between ODFW and Triad. Those rulings effectively precluded Triad from presenting evidence to support its claims. The court then granted ODFW’s motion to dismiss Triad’s claims and entered a judgment under ORCP 67 B. We affirm.

Triad contends that the trial court erred in the following three particulars: (1) in holding that the parol evidence rule barred evidence of discussions that the parties allegedly had before signing the two written change orders; (2) in holding that the change orders constituted an accord and satisfaction; and, (3) in granting ODFW’s motion to dismiss.1 We affirm.

Triad and ODFW entered into a written contract to construct improvements to the Oak Springs Fish Hatchery. The contract required Triad to complete the improvements in 335 days. Rich & Associates Construction Company, a subcontractor to Triad, agreed to perform a portion of the project involving rock excavation.

The contract between Triad and ODFW specified that 100 cubic yards of rock were to be excavated and provided that any rock excavation in excess of 100 cubic yards would be a change to the contract. The contract gave Triad a claims procedure to pursue equitable adjustments to the contract for changed conditions. As relevant, Article 27 of the contract provides that ODFW’s engineer would

“promptly investigate the conditions, and if he finds that such conditions do so materially differ [from those specified [110]*110in the contract] and cause an increase or decrease in the cost of, or the time required for, performance of this Contract, an equitable adjustment shall be made and the Contract modified in writing accordingly. * * * Adjustment for such conditions shall be made in accordance with Article 28 of [the Contract].”

Article 28 provides, in turn, that equitable

“[a]djustments for changes or changed conditions covered in Article 26 and 27 will be made on the basis of agreement of the parties: Provided, that if the parties fail to agree on the amount of an increase in the cost of performance of the Contract, the adjustment shall be on the basis of force account * * (Emphasis in original.)

In mid-March 1992, Rich encountered rock in excess of 100 cubic yards. On March 25, 1992, representatives of Triad, Rich and ODFW met to discuss changes to the contract required by the excess rock.

The parties disagree as to the result of the meeting. According to Triad, the parties agreed that ODFW would pay Triad a fixed unit price, ranging from $7 to $226.26 per cubic yard, for the direct cost of removing the additional rock, depending on the type and depth of the rock to be excavated. Triad asserts that the parties decided to postpone consideration of additional compensation for time and expense resulting from the extra excavation work because the total amount of those costs could not be determined at the time of the meeting.2 Triad asserts that the parties understood that those costs would be pursued as a separate claim on completion of the project. ODFW contends that all the terms of the parties’ agreement with respect to the extra rock excavation are contained in two written change orders, which ODFW prepared, signed and sent to Triad for its signature in June and August 1992. Thus, ODFW maintains that the evidence supporting Triad’s assertions constitutes evidence of an oral agreement, proof of which is barred by the parol evidence rule because the change orders constitute either a completely or partially integrated agreement.

[111]*111The written change orders, numbered 4 and 6, specified the costs per cubic yard for the additional rock excavation.3 In addition, each stated that “the completion time [for the project] will not increase and [will] remain at 335 days as a result of this change order.” There is no mention in the change orders of an agreement that another claim would be submitted for the delay and impact costs associated with the extra excavation or, put another way, that the change orders reflect only the parties’ agreement regarding the direct costs of the extra rock removal. Upon receipt, Triad promptly signed and returned the change orders to ODFW.

Triad completed the project on January 5, 1993, 52 days after the completion date specified in the contract of November 15,1992. On January 7,1993, it presented a claim to ODFW for the delay and impact costs associated with excavating the extra rock. ODFW refused to pay the claim, asserting, inter alia, that Triad had waived further claims for costs incurred as a result of the extra rock excavation when it signed change orders 4 and 6. Rich thereafter filed an action against Triad and ODFW on the subcontract between Rich and Triad. Triad, in turn, filed cross-claims against ODFW for breach of contract, seeking to recover the delay and impact costs allegedly incurred by Triad as a result of the additional excavation.

Before trial, ODFW filed a motion, based on the parol evidence rule, “for a ruling precluding [Triad and Rich] from entering any evidence or making reference in the presence of the jury to anything intended to contradict the terms of the written contract and change orders.” That motion sought to exclude evidence of the discussion that Triad alleges the parties had at their March 25 meeting.

[112]*112After reviewing the change orders, the trial court granted ODFW’s motion to limit evidence. The trial court also ruled that change orders 4 and 6 constituted an accord and satisfaction between the parties. Triad told the court that those rulings effectively precluded it from presenting evidence necessary to prove its claims. Triad then sought to introduce evidence of the facts surrounding the March 25 meeting to show that the change orders did not encompass all of the terms that the parties had agreed upon.

After the offer of proof, ODFW moved to dismiss Triad’s claims and, in the alternative, for summary judgment.4 The trial court granted ODFW’s motion and entered judgment under ORCP 67 B dismissing Triad’s cross-claims against ODFW for breach of contract on the ground that there was no genuine issue as to any material fact and that ODFW was entitled to judgment in its favor as a matter of law.5

Triad first assigns error to the trial court’s grant of ODFW’s motion to limit evidence under the parol evidence rule.6 The parol evidence rule is found in ORS 41.740, which provides, as relevant:

“When the terms of an agreement have been reduced to writing by the parties, it is to be considered as containing all those terms, and therefore there can be, between the parties and their representatives or successors in interest, [113]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morton & Associates, LLC v. McCain Foods USA, Inc.
204 P.3d 167 (Court of Appeals of Oregon, 2009)
McDonald v. Sun Oil Company
423 F. Supp. 2d 1114 (D. Oregon, 2006)
BC Metal Fabrication Inc. v. Haco NV
79 F. App'x 259 (Ninth Circuit, 2003)
M.J. Paquet, Inc. v. New Jersey Department of Transportation
794 A.2d 141 (Supreme Court of New Jersey, 2002)
Hall Street Associates, L.L.C. v. Mattel, Inc.
145 F. Supp. 2d 1211 (D. Oregon, 2001)
Oregon Trail Electric Consumers Cooperative, Inc. v. Co-Gen Co.
7 P.3d 594 (Court of Appeals of Oregon, 2000)
Varner v. Eves
990 P.2d 357 (Court of Appeals of Oregon, 1999)
Loverin v. Paulus
982 P.2d 20 (Court of Appeals of Oregon, 1999)
State Ex Rel. Cipriano v. Triad Mechanical, Inc.
925 P.2d 918 (Court of Appeals of Oregon, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
925 P.2d 918, 144 Or. App. 106, 1996 Ore. App. LEXIS 1467, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-cipriano-v-triad-mechanical-inc-orctapp-1996.