Claremont Construction Group, Inc. v. Arc Nj, LLC

CourtNew Jersey Superior Court Appellate Division
DecidedAugust 15, 2025
DocketA-3246-23/A-0457-24
StatusUnpublished

This text of Claremont Construction Group, Inc. v. Arc Nj, LLC (Claremont Construction Group, Inc. v. Arc Nj, LLC) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Claremont Construction Group, Inc. v. Arc Nj, LLC, (N.J. Ct. App. 2025).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-3246-23 A-0457-24

CLAREMONT CONSTRUCTION GROUP, INC.,

Plaintiff-Respondent,

v.

ARC NJ, LLC,

Defendant-Appellant. ____________________________

Plaintiff-Appellant,

Defendant-Respondent. ____________________________

Argued (A-3246-23) March 18, 2025 and (A-0457-24) June 3, 2025 – Decided August 15, 2025

Before Judges Susswein and Bergman. On appeal from the Superior Court of New Jersey, Chancery Division, Morris County, Docket Nos. C-000011-24 and C-000055-24.

Erin C. Borek (Phillips Lytle, LLP) argued the cause for ARC NJ, LLC.

Frederick W. Alworth and Kevin W. Weber argued the cause for Claremont Construction Group, Inc. (Gibbons, PC, attorneys; Frederick W. Alworth, Kevin W. Weber and Michael A. Conforti, on the briefs).

PER CURIAM

We consolidated these appeals that were argued on two separate dates for

purposes of issuing a single opinion. The matters arise from trial court orders

entered in two separate Chancery actions both involving an agreement for the

sale of plaintiff Claremont Construction Group, Inc.'s construction business to

defendant Arc, NJ, LLC.

In A-3246-23, defendant appeals from three orders dated June 12, 2024

which granted plaintiff's motion to confirm an arbitration award (Award) and

denied defendant's motion to (1) vacate the Award; (2) modify the Award to

correct mathematical and form errors; and (3) grant defendant leave to assert a

counterclaim against plaintiff for setoffs.

In A-0457-24, plaintiff appeals from two orders dated August 30, 2024.

The first order denied its request for injunctive relief to bar a second arbitration

initiated by defendant and the second order granted defendant's motion to

A-3246-23 2 dismiss plaintiff's complaint and order to show cause (OTSC) with prejudice

and to compel arbitration. Plaintiff also appeals the court's order denying

reconsideration. Plaintiff's subsequent motion requesting a stay of the second

arbitration pending this appeal was granted by the trial court.

Based on our review of the record and application of the relevant legal

principles, we affirm the trial court orders with one exception. We modify the

orders of August 30, 2024 to permit the arbitrator in the second arbitration to

determine what portion, if any, of the $899,051.20 credit provided to defendant

in the first arbitration regarding the Hackensack Project was based on monies

due from plaintiff to defendant under the subcontractor agreement for that

project.

I.

We first address A-3246-23. We presume the parties are familiar with the

pertinent facts and procedural history leading to this appeal, which we briefly

summarize. The parties' disputes centered around the sale of plaintiff's

construction business to defendant pursuant to a "Project Transfer Agreement"

(PTA). A principal component of the PTA concerned an "earn-out" process in

which plaintiff would transfer its ongoing contracts (Backlog Projects) to

defendant without defendant paying "any upfront payment . . . for [plaintiff's]

long-standing and successful construction business." The PTA contemplated

A-3246-23 3 earnings for both parties would be based on "Estimated Gross Profit" (EGP).

Rather than defendant paying an upfront amount to plaintiff, the parties would

agree on the EGP at the outset of the project and defendant would pay plaintiff

sixty-five percent of the EGP during the course of the project in quarterly

installments. These payments were to be made regardless of what occurred on

the actual project or with respect to actual profits. Thereafter, defendant would

retain any additional profits or shoulder any losses.

The PTA contemplated the only projects that were subject to the EGP

payment obligation were those that achieved the status of a "Backlog Project"

under a procedure set forth in the PTA. The PTA also listed other types of

projects including "Pipeline Rights," which if satisfied, transformed the project

into a Backlog Project subject to EGP sharing.

When disputes arose between the parties concerning the sharing of the

EGP, they submitted to arbitration before a single arbitrator from the American

Arbitration Association (AAA) as required by the PTA. Plaintiff alleged it was

owed $5,209,900.68 for its share of EGP for the ten projects in dispute based on

the terms of the payout provisions in the PTA. In its damage calculations,

plaintiff included $1,735,500 from the Bayonne 3 project alleging it received no

EGP payments from defendant for this project. Plaintiff also included two other

projects in the calculation: Pennrose and 81 Orange, which were not yet

A-3246-23 4 awarded to defendant and categorized these projects as "Additional Pipeline

Projects." Plaintiff alleged it was entitled to sixty-five percent of EGP if

defendant was eventually awarded these projects.

Defendant filed a counterclaim seeking reimbursement of $5,065,184.14

which represented all the EGP paid to plaintiff on the ten disputed projects.

Defendant argued because formal amendments to the PTA were never executed

to include these projects as Backlog Projects, it had no obligation to pay any

EGP to plaintiff. Defendant asserted plaintiff failed to satisfy a six-step process1

set forth in the PTA as a condition precedent, to transform the disputed projects

into Backlog Projects in order to be paid its share of the EGP.

Defendant also sought $9,189,250 in anticipated lost profits on nine of the

projects which had not moved forward. Defendant claimed these projects should

be included under the PTA. Defendant further sought recoupment of business

1 The six conditions defendant asserts must be satisfied under the PTA for a Pipeline Right to become an Additional Backlog Project subject to sharing of EGP are: (1) plaintiff must own and control a right that is subject to transfer to defendant; (2) the parties must come to an agreement as to the price of defendant's work; (3) the Pipeline Right must be embodied in a Construction Contract with defendant for its work; (4) plaintiff and defendant must agree to EGP for the Pipeline Right; (5) the PTA "shall be amended" to remove the Pipeline Right and add such Right as an Additional Backlog Project; and (6) the PTA shall be amended to include such Additional Backlog Projects and the agreed upon EGP.

A-3246-23 5 losses allegedly sustained from 2020 to 2022 in the amount of $5,481,397.

Finally, defendant sought $859,099.90 in "preconstruction costs" it allegedly

incurred on projects that it was not awarded. Plaintiff conceded that

$162,760.87 was due to defendant for the preconstruction costs claim.

The arbitration hearing took place over eight days. The arbitration process

included discovery demands including substantial document productions,

depositions, preparation and production of expert reports, motion practice, pre-

trial submissions, an arbitration hearing with witness testimony from fourteen

individuals, post-hearing written submissions, and post-hearing arguments.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hillsborough Township Bd. of Ed. v. Faridy Thorne Frayta, PC
728 A.2d 857 (New Jersey Superior Court App Division, 1999)
DiTrolio v. Antiles
662 A.2d 494 (Supreme Court of New Jersey, 1995)
Atlantic Northern Airlines, Inc. v. Schwimmer
96 A.2d 652 (Supreme Court of New Jersey, 1953)
Karpovich v. Barbarula
696 A.2d 659 (Supreme Court of New Jersey, 1997)
Highland Lakes Country Club & Community Ass'n v. Nicastro
988 A.2d 90 (Supreme Court of New Jersey, 2009)
Creter v. Davies
103 A.2d 392 (New Jersey Superior Court App Division, 1954)
M.J. Paquet, Inc. v. New Jersey Department of Transportation
794 A.2d 141 (Supreme Court of New Jersey, 2002)
Fawzy v. Fawzy
973 A.2d 347 (Supreme Court of New Jersey, 2009)
Great Atl. & Pac. Tea Co. v. Checchio
762 A.2d 1057 (New Jersey Superior Court App Division, 2000)
Creter v. Davies
107 A.2d 17 (New Jersey Superior Court App Division, 1954)
Oliver v. Ambrose
705 A.2d 742 (Supreme Court of New Jersey, 1998)
County College of Morris Staff Ass'n v. County College of Morris
495 A.2d 865 (Supreme Court of New Jersey, 1985)
Kwabena Wadeer v. New Jersey Manufacturers Insurance Company (072010)
110 A.3d 19 (Supreme Court of New Jersey, 2015)
Minkowitz v. Israeli
77 A.3d 1189 (New Jersey Superior Court App Division, 2013)
Borough of East Rutherford v. East Rutherford PBA Local 275
61 A.3d 941 (Supreme Court of New Jersey, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Claremont Construction Group, Inc. v. Arc Nj, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/claremont-construction-group-inc-v-arc-nj-llc-njsuperctappdiv-2025.