Hercules Inc. v. United States

626 F.2d 832, 27 Cont. Cas. Fed. 80,514, 224 Ct. Cl. 465, 1980 U.S. Ct. Cl. LEXIS 231
CourtUnited States Court of Claims
DecidedJuly 2, 1980
DocketNo. 442-77
StatusPublished
Cited by8 cases

This text of 626 F.2d 832 (Hercules Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hercules Inc. v. United States, 626 F.2d 832, 27 Cont. Cas. Fed. 80,514, 224 Ct. Cl. 465, 1980 U.S. Ct. Cl. LEXIS 231 (cc 1980).

Opinion

PER CURIAM:

This case comes before the court on plaintiffs request for review by the court of the recommended decision of Trial Judge C. Murray Bernhardt, filed July 23, 1979, pursuant to Rule 166(c), on plaintiffs motion and defendant’s cross-motion for summary judgment. The court has heard oral argument and has considered the briefs of the parties. Agreeing with the trial judge’s recommended decision, as hereinafter set forth, the court hereby affirms and adopts that decision, together with the following paragraphs of this per curiam opinion, as the basis for its judgment in this case.

A major part of plaintiffs case is comprised of the twin propositions that (i) the contracting officer for the fixed-price contracts necessarily decided, in accepting plaintiffs prices for those contracts, that the method used to determine the depreciation allowance for the Hercopel Plant which was included in those fixed prices was proper and fully in accord with the pertinent provisions of Section XV of the Armed Services Procurement Regulations (ASPR), and (ii) such an approving decision by that contracting officer, taken together with the need for consistency of treatment, controls the determination of the reimbursable General and Administrative (G&A) expense for plaintiffs cost-reimbursable contracts now before us.1 The factual predicate for consideration of those propositions — as found by the Armed Services Board of Contract Appeals and [469]*469confirmed by the trial judge — is (to use the trial judge’s words) that plaintiff decided "to adjust its costing practices for its fixed price contracts by understating its depreciation [on the Hercopel Plant] in order to make its prices lower and thus more competitive.”2

We are satisfied that, on these facts, nothing in Section XV of ASPR, including the specific provisions plaintiff cites (i.e., ASPR §§ 15-201.3, 15-203, 15-205.9), precluded the contracting officer on the fixed price contracts from accepting a fixed price which included an understated or too-low depreciation cost on the Hercopel Plant if the bidder or potential contractor wanted to proffer such a deliberately lower cost for its own competitive purposes. Conversely, the regulations did not forbid plaintiff from offering a fixed price lower than that computed according to ASPR.3 The texts of the regulations do not forbid a contracting officer from accepting such a too-low price on a fixed-price contract, nor do they require him to reject it if offered, nor do they preclude a bidder or contractor from putting forward such a too-low price. What the regulations do is to declare the criteria for deciding what types of depreciation allowances should not be accepted because they are too high for the particular contract. Unless perhaps the proffered fixed price is so low that it might well endanger performance, there is no legal or practical requirement that the contracting officer go through each item making up the proffered price to determine whether that specific item is too low, considered by itself. In our system for bid and negotiated fixed price contracts, that process and that determination are left to the judgment of the bidder or potential contractor. It is his choice if he wishes to cut his [470]*470price for competitive ends, and there is nothing illegal or improper in his doing so.

None of the decisions on which plaintiff relies states or implies a contrary holding. In particular, they do not say or suggest that acceptance by a contracting officer of a fixed price necessarily implies that he also accepted each of the underlying components of that fixed price as proper under the ASPR standards. Rather, the deciding tribunal (this court or a board of contract appeals) has ruled for itself, in cost-reimbursement cases, that a contractor’s cost accounting practices accorded, or did not accord, with the pertinent ASPR and controlling standards, where the Government contended that the claimed reimbursement was excessive and a review of the contractor’s practices was necessary in order to resolve that question. We do the same here, holding that in the circumstances usage depreciation did not comply with ASPR and resulted in excessive reimbursement on plaintiffs cost-reimbursable contracts.

Accordingly, on the basis of the foregoing paragraphs and the trial judge’s opinion, we hold that plaintiffs motion for summary judgment is denied, defendant’s motion for summary judgment is allowed, and the petition is dismissed.

OPINION OF TRIAL JUDGE

BERNHARDT, Trial Judge: This review under the Wun-derlich Act (41 U.S.C. §§ 321-22 (1976)) of a decision of the Armed Services Board of Contract Appeals (77-1 BCA ¶ 12,394) on claims under two Navy cost reimbursement research and development (R&D) contracts turns entirely on elusive accounting principles. In the abstract, what is accepted practice in the accounting profession is a factual inquiry. But the application of accounting rules to a finite problem raises an issue of contract interpretation, which is an issue of law. "Thus, the ultimate question is one of law, though facts are essential to its solution.” Lockheed Aircraft Corp. v. United States, 179 Ct. Cl. 545, 553, 375 F. 2d 786, 790 (1967). See also Tri-Cor, Inc. v. United States, 198 Ct. Cl. 187, 204, 458 F. 2d 112, 122 (1972). 3 A. Corbin, Corbin on Contracts § 554 (2d ed. 1960).

[471]*471Synoptically, plaintiff wishes to employ the same usage basis of depreciation in its cost reimbursable contracts under review that it was permitted to employ in its fixed price contracts being performed contemporaneoulsy in another of its plants. A usage basis of depreciation, if allowed, would increase the reimbursable General and Administrative (G&A) expense that plaintiff could recapture in the subject cost reimbursable contracts, while at the same time decrease the prices it could offer in bidding on fixed price contracts in order to make plaintiffs bids on government work more competitive. The contracting officer, affirmed by the Board, disallowed employment of the usage formula for the cost reimbursable contracts under review, and required that depreciation for such contracts be computed on a straight-line basis for inclusion in the determination of G&A rates. From this refusal the plaintiff appeals, without avail.

The two contracts in dispute were awarded on August 25, 1967 and October 23, 1969, and required the rendition of R&D services from, respectively, July 1, 1967 through June 30, 1968, and November 1, 1969 through October 31, 1970. Each contract contains the standard Disputes Clause (ASPR 7-103.12(a), January 1958) and the clause entitled "Allowable Cost, Fixed Fee, and Payment” (ASPR 7-203.4(a)). The contracts were performed at plaintiffs Alle-gany Ballistics Laboratory (Plant # 1) at Cumberland, Maryland, which was primarily an R&D laboratory facility that was owned by the Navy and operated by plaintiff.

On land adjacent to Plant #1 plaintiff constructed the Hercopel Plant (Plant #2) which became operational by February 1968. Plant #2 was an automated special purpose facility designed to manufacture tactical rocket motors fueled by proprietary composite propellants known as "Hercopel.” The manufacture of Hercopel propellants is hazardous; hence the emphasis on automation in Plant # 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
626 F.2d 832, 27 Cont. Cas. Fed. 80,514, 224 Ct. Cl. 465, 1980 U.S. Ct. Cl. LEXIS 231, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hercules-inc-v-united-states-cc-1980.