Systems Technology Associates, Inc. v. The United States

699 F.2d 1383, 30 Cont. Cas. Fed. 70,829, 1983 U.S. App. LEXIS 13562
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 18, 1983
DocketAppeal 46-81
StatusPublished
Cited by32 cases

This text of 699 F.2d 1383 (Systems Technology Associates, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Systems Technology Associates, Inc. v. The United States, 699 F.2d 1383, 30 Cont. Cas. Fed. 70,829, 1983 U.S. App. LEXIS 13562 (Fed. Cir. 1983).

Opinion

EDWARD S. SMITH, Circuit Judge.

This case presents a question of Federal Government contract law: whether a settlement agreement between a contractor and the Government should be set aside for duress or coercion in light of the contractor’s precarious financial condition at the time the settlement agreement was reached. The contractor, Systems Technology Associates, Inc., appeals the February 19, 1981, decision of the Department of the Interior Board of Contract Appeals (board), 1 dismissing the contractor’s claim that the settlement agreement should be set aside. While we do not fully endorse the board’s analysis, we do find that the settlement was not induced by coercion or duress. We, therefore, affirm the decision of the board.

I.

Systems Technology Associates (STA) entered into a contract with the Environmental Protection Agency (EPA) on August 15, 1974. STA agreed to supply computer equipment to EPA’s Ann Arbor, Michigan, laboratory for the fixed price of $1,302,993. At the Government’s behest, the contract was modified several times between May and December 1975. With no agreement on schedule and price adjustments, STA stopped work and, on March 8, 1976, EPA terminated the contract for default.

The contractor’s appeal of the default termination was sustained by the board. In its January 19, 1978, decision, 2 the board converted the default termination to a termination for convenience and required the Government to equitably adjust the contract. STA’s constructive change order claims were denied -without prejudice and remanded to the contracting officer.

On February 14, 1978, the parties met and STA suggested that the settlement be *1385 on a “total cost” basis. STA submitted a termination settlement proposal. 3 In evaluating that proposal, a Government auditor requested and was denied access to STA’s books on June 5,1978. The parties met and discussed their disagreements over the use of the total cost basis methodology, favored by the Government, and over Government access to STA’s books. 4

Subsequently, STA resubmitted its claim, protesting the Government’s insistence on a total cost basis settlement and agreeing under protest to make cost records available to Government auditors.

The auditors, however, insisted on using STA’s job cost ledgers. STA again protested. The auditors finally concluded that, because of STA’s failure to make the job cost ledgers available, the field audit office could not render an opinion on STA’s settlement proposal.

This dispute over methodology and access to the job cost ledgers continued until October 4, 1978, when STA submitted under protest a settlement proposal prepared on a total cost basis and allowed the auditors access to its job cost ledgers. STA’s total cost basis settlement proposal requested an additional payment of $2,718,448.®

During the period of this dispute, STA was under financial pressure from its bank and a principal contractor, Xerox. The record is clear that the Government was at least aware of STA’s precarious financial position.

The audit report was delivered to the Government in mid-January 1979. Following discussion of the Government’s refusal to supply a copy of the audit report to STA, the parties met on February 8, 1979, at which time the Government offered a total settlement payment of $798,952. The contractor rejected the offer claiming that the Government’s strategy was to place STA under duress to force a reduced settlement. 5 6 Another negotiation meeting was held February 22, 1979, but no progress was made.

The Government eventually relented on the issue of making the audit report available; on March 7,1979, STA received a copy of the audit report. The audit report questioned $2,235,056 of STA’s $4,696,968 total cost basis settlement claim. Only $2,461,-912 of contractor’s claim was established by the auditors as verified costs.

It was against this background of financial pressure and disputes over settlement methodology and access to records that the parties met on March 16, 1979. Xerox had offered to waive interest on its claim against STA if full payment was made by that date. The Government was fully apprised of this offer.

Although STA requested a speedy settlement, almost 14 months had elapsed since the board ordered equitable adjustment of the contract. Much of this time was consumed by the disputes discussed above. STA was finally forced to accept the Government’s position on both points in order to advance the negotiations.

Unable to move the Government in the March 16 meeting, STA’s president accepted a total settlement in the amount of $1,200,639, citing his inability to pursue the matter further due to the company’s precarious financial condition.

On June 11, 1979, STA appealed to the board, asking that the March 16 settlement *1386 be set aside on the grounds that it was procured by duress, coercion, and such arbitrary action as to be tantamount to fraud. The board determined that duress was not established. STA’s request for reconsideration of the board’s February 19, 1981, decision was denied.

STA then appealed to this court, requesting reversal of the board’s February 19, 1981, decision.

II.

The sole issue raised by this appeal is whether the board erred in determining that the settlement agreement should not be set aside for coercion or duress. In arguing that this court should set aside the settlement agreement, STA contends that the board erred in articulating the applicable legal standard and in applying that standard to the facts before it. The Government defends the board’s decision as reasonable, thorough, and legally correct.

In reviewing the determination of the board we must decide whether, with respect to the facts, the board’s decision is fraudulent, or arbitrary, or capricious, or so grossly erroneous as necessarily to imply bad faith, or is not supported by substantial evidence. The legal conclusions of the board are freely reviewable by this court. 7

A.

We look first to the board’s articulation of the standard of what conduct constitutes economic duress: 8

The essential elements of economic duress are summarized by Nash and Cibinic in Federal Procurement Law (1969 ed., p. 208) as: (1) A person compels another to assent to a transaction against his will; (2) such assent is induced by wrongfully threatening action the person has no legal right to take; and (3) the threatened action, if taken, will cause irreparable damage to the other person. * * *

Focusing on the second of Nash and Cibinic’s elements, the board went on to state that duress requires a wrongful act or an act the Government is not legally empowered to take.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A4 Construction Company, Inc
Armed Services Board of Contract Appeals, 2025
First Division Design, LLC
Armed Services Board of Contract Appeals, 2018
Salter v. United States
119 Fed. Cl. 359 (Federal Claims, 2014)
New Iraq Ahd Company
Armed Services Board of Contract Appeals, 2014
Starr International Co. v. United States
106 Fed. Cl. 50 (Federal Claims, 2012)
Robinson v. United States
95 Fed. Cl. 480 (Federal Claims, 2011)
IMS Engineers-Architects, P.C. v. United States
92 Fed. Cl. 52 (Federal Claims, 2010)
Skoczen v. Shinseki
564 F.3d 1319 (Federal Circuit, 2009)
North Star Steel Co. v. United States
68 Fed. Cl. 672 (Federal Claims, 2005)
Abatement Contracting Corp. v. United States
58 Fed. Cl. 594 (Federal Claims, 2003)
Preferred National Insurance v. United States
54 Fed. Cl. 600 (Federal Claims, 2002)
Green Management Corp. v. United States
42 Cont. Cas. Fed. 77,412 (Federal Claims, 1998)
Niko Contracting Co. v. United States
42 Cont. Cas. Fed. 77,244 (Federal Claims, 1997)
McLain Plumbing & Electrical Service, Inc. v. United States
39 Cont. Cas. Fed. 76,593 (Federal Claims, 1993)
In Re Rochkind
128 B.R. 520 (E.D. Michigan, 1991)
Granite Construction Co. v. United States
37 Cont. Cas. Fed. 76,080 (Court of Claims, 1991)
Kelsey-Hayes Co. v. Galtaco Redlaw Castings Corp.
749 F. Supp. 794 (E.D. Michigan, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
699 F.2d 1383, 30 Cont. Cas. Fed. 70,829, 1983 U.S. App. LEXIS 13562, Counsel Stack Legal Research, https://law.counselstack.com/opinion/systems-technology-associates-inc-v-the-united-states-cafc-1983.