North Star Steel Co. v. United States

68 Fed. Cl. 672, 2005 U.S. Claims LEXIS 356, 2005 WL 3216914
United States Court of Federal Claims·Decided November 30, 2005·No. No. 00-238C·Published·Cited by 2 cases

Opinion

MEMORANDUM OPINION AND FINAL ORDER REGARDING CONTRACTUAL LIABILITY AND DAMAGES

BRADEN, Judge.

This sui generis case concerns an August 16, 1994 contract for services to regulate electric power transmitted between the Western Area Power Administration (“WAPA”) and the Arizona Electric Power Cooperative, Inc. (“AEPCO”) for the benefit of North Star Steel Co. (“North Star”). See North Star Steel Co. v. United States, 58 Fed.Cl. 720, 734-35 (Fed.Cl.2003). The contract at issue required WAPA to “jointly establish an appropriate cost-based methodology,” before the conclusion of the first year of normal operations of the North Star plant. In this action, North Star sought damages of $6,465,889.65 for breach of that contractual requirement and WAPA’s failure to negotiate in good faith. WAPA countered that there was no breach and WAPA negotiated with AEPCO/North Star in good faith for rates that were reasonable. For the reasons discussed herein, to ascertain whether a breach occurred and the appropriate amount of damages, the appointment of a court-appointed expert in utility ratemaking was required.

To facilitate a review of this Memorandum Opinion, the court has provided the following outline:

BACKGROUND

A. Federal Regulation Of The Electric Utility Industry.

1. The Effect Of Federal Legislation Enacted 1920-1977.

2. Effect Of The Department Of Energy Organization Act Of 1977 And Creation Of The Western Area Power Administration.

B. Relevant Facts.

1. Early 1990-August 17, 1994 — Negotiations Between North Star Steel Co. And The Western Area Power Administration For Regulating Services.

2. August 17, 1994 — The Western Area Power Administration And North Star Steel Co. Execute Interconnection And Consolidated Contracts.

3. October 23,1997-July 28,1999 — The Western Area Power Administration Failed To Establish “An Appropriate Cosh-Based Methodology” For The “In-Kind Energy” Payment.

a. October 23,1997-June 19,1998 — Post Consolidated Contract Negotiations.

b. December 7,1998 — The Western Area Power Administration Files An Open Access Transmission Tariff With The Federal Energy Regulatory Commission.

c. December 8, 1998-September 15, 1999 — The Western Area Power Administration And North Star Steel Co. Continue To Negotiate Until The Unilateral Imposition Of Amendment No. 3 On September 15,1999.

d. During 2000, The Western Area Power Administration And North Star Steel Co. Resumed Negotiations Until North Star Steel Co. Rejected Revision 1 On October 17, 2001.

C. Procedural Background.

DISCUSSION

A. Jurisdiction.

B. North Star Steel Co. Has Standing As A Third-Party Beneficiary To The August 17, 1994 Consolidated Contract For Regulating Services.

C. The Court’s Resolution Of The Remaining Substantive Issues.

[675]*6751. The Western Area Power Administration Had No Contractual Obligation To North Star Steel Co. To “True Up” Over Or Under Payments Of “In-Kind Energy” On An Annual Basis And No Duty To Refund Retroactively Any Overpayment For Regulating Services.

2. The Terms Of The Consolidated Contract Evidence Sufficient Certainty To Determine: The Intent Of The Parties To Enter a Contract; Whether And When A Breach Occurred; And An Appropriate Remedy For Breach.

3. The Western Area Power Administration Breached The Consolidated Contract By Failing To Establish A “Cost-Based Methodology” For Regulating Services On July 1,1998 Or Thereafter.

a. In Discovery And At Trial, The Western Area Power Administration Claimed That No Data Existed To Evidence Annual Operations And Maintenance Costs For The Regulating Services Provided To North Star Steel Co.

b. Substantial Expert Testimony Confirmed That The Western Area Power Administration Did Not Establish A “Cost-Based” Methodology With North Star Steel Co.

(1) June 22, 2004 Direct Testimony Of North Star Steel Co.’s Expert — Dr. Carl Pechman.

(a) Qualifications.

(b) Expertise.

(e) Opinion.

(2) July 27, 2004 Direct Testimony Of North Star Steel Co.’s Expert — R. Mark Clements.

(a) Qualifications.

(b) Expertise.

(c) Opinion.

(i) Generation Capacity Costs.

(ii) Automatic Generation And Communications Costs.

(in) Variable Operating And Maintenance Costs.

(iv) Opportunity Costs.

(v) Conclusion.

(d) Cross Examination.

(3) July 2, 2004 Direct Testimony Of The Western Area Power Administration’s Expert — Dr. Douglas A. Gegax.

(a) Qualifications.

(b) Expertise.

(c) Opinion.

(4) July 27, 2004 Rebuttal Of North Star Steel Co.’s Expert — R. Mark Clements To The Western Area Power Administration’s Expert — Dr. Gegax.

(a) Summary Critique Of Dr. Gegax’s Report.

(b) Calculation Of Actual Costs For Regulating Services Provided To North Star Steel Co. For The Period July 1997 — March 2003.

(5) October 25,2004 Direct Testimony Of The Court’s Expert — Dr. Barbara R. Barkovich.

(a) Qualifications.

(b) Expertise.

(c) Opinion.

(i) Comparison Of Alternative Cost Models.

(ii) The Western Area Power Administration’s Regulating Services Were Not Provided To North Star Steel Co. On A “Cost-Of-Service” Basis.

(iii) Dr. Barkovich’s Initial “Cost-Of-Service” Calculations.

(6) November 16, 2004 Supplemental Report Of The Court’s Expert — Dr. Barbara R. Barkovich.

(7) February 1,2005 Post-Trial Additional Report Of The Court’s Expert — Dr. Barbara R. Barkovich.

(8) February 15, 2005 Post-Trial Sur-Rebuttal Report Of North Star Steel Co.’s Expert — R. Mark Clements.

(9) November 7, 2005 Post-Trial Response Of The Court’s Expert — Dr. Barkovich To February 15,2005 Post-Trial Sur-Rebuttal Report Of North Star Steel Co.’s Expert — R. Mark Clements.

[676]*6764. The Western Area Power Administration’s Unilateral Imposition Of Amendment No. 3 On September 15,1999 Was An Act Of “Economic Duress” And A Breach Of The Obligation To Negotiate In Good Faith.

a. North Star Steel Co. “Involuntarily Accepted” Amendment No. 3.

b. The “Circumstances Permitted” North Star Steel Co. “No Other Alternative,” Than To Accept Amendment No. 3.

e. Amendment No. 3 Was Not “Cost-Based.”

D. North Star Steel Co. Is Entitled To Damages In The Amount Of $1,521,626. CONCLUSION

BACKGROUND

A. Federal Regulation Of The Electric Utility Industry.1

To understand the context of this contractual dispute, a summary review of the labyrinth of laws enacted by Congress that regulate virtually all aspects of the electric utility industry is required.

1.

Free access — add to your briefcase to read the full text and ask questions with AI

North Star Steel Co. v. United States, 68 Fed. Cl. 672, 2005 U.S. Claims LEXIS 356, 2005 WL 3216914 (uscfc 2005).

68 Fed. Cl. 672 (North Star Steel Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Oasis International Waters, Inc. v. United States
134 Fed. Cl. 155 (Federal Claims, 2017)
North Star Steel Co. v. United States
477 F.3d 1324 (Federal Circuit, 2007)