United States v. City of Fulton

475 U.S. 657, 106 S. Ct. 1422, 89 L. Ed. 2d 661, 1986 U.S. LEXIS 93, 54 U.S.L.W. 4343
CourtSupreme Court of the United States
DecidedApril 7, 1986
Docket84-1725
StatusPublished
Cited by56 cases

This text of 475 U.S. 657 (United States v. City of Fulton) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. City of Fulton, 475 U.S. 657, 106 S. Ct. 1422, 89 L. Ed. 2d 661, 1986 U.S. LEXIS 93, 54 U.S.L.W. 4343 (1986).

Opinion

Justice Marshall

delivered the opinion of the Court.

This case presents the question whether the Secretary of Energy violated §5 of the Flood Control Act of 1944, 16 U. S. C. §825s, or his contractual obligations by putting rates for hydroelectric power generated at federally owned dams into effect on an interim basis pending further review by the Federal Energy Regulatory Commission. The Court of Claims held that the Secretary’s actions exceeded his contractual and statutory authority, and granted summary *659 judgment to respondents. 230 Ct. Cl. 635, 680 F. 2d 115 (1982). After further proceedings, the Court of Appeals for the Federal Circuit affirmed, finding that the Court of Claims’ decision was the law of the case and correct on the merits. 751 F. 2d 1255 (1985). We granted certiorari, 473 U. S. 903 (1985), and we now reverse.

I

A

In the Flood Control Act, Congress authorized the construction of a number of dam and reservoir projects, operated by the Army Corps of Engineers and producing large blocks of hydroelectric power. Congress had granted authority for several such projects before 1944, but had enacted no “general law governing the sale and distribution of power” so generated. S. Rep. No. 1030, 78th Cong., 2d Sess., 3 (1944). Intending “to place by law the responsibility for disposal of such power in an existing Federal agency,” ibid., Congress provided:

“Electric power and energy generated at reservoir projects under the control of the War Department and in the opinion of the Secretary of War not required in the operation of such projects shall be delivered to the Secretary of the Interior, who shall transmit and dispose of such power and energy in such manner as to encourage the most widespread use thereof at the lowest possible rates to consumers consistent with sound business principles, the rate schedules to become effective upon confirmation and approval by the Federal Power Commission. Rate schedules shall be drawn having regard to the recovery (upon the basis of the application of such rate schedules to the capacity of the electric facilities of the projects) of the cost of producing and transmitting such electric energy, including the amortization of the capital investment allocated to power over a reasonable period of years. ...” Ch. 665, § 5, 58 Stat. 887, 890 *660 (emphasis added) (codified as amended at 16 U. S. C. § 825s).

In order to sell the hydroelectric power turned over to him under that statute, the Secretary of the Interior created what eventually became five regional Power Marketing Administrations (PM As). The PM A Administrators were assigned the responsibility of preparing rate schedules and the supporting accounting and cost allocation studies. There were no formal procedures for public participation in PMA preparation of rate schedules, although some of the PMAs (not including the Southwestern Power Administration (SWPA), immediately concerned in this suit) began to adopt such procedures starting in late 1977. See 45 Fed. Reg. 86976 (1980).

When determining whether to approve a PMA’s proposed rates, the Federal Power Commission utilized its “special expertise” and its “independent judgment” in measuring the proposal against the statutory standards. Bonneville Power Administration, 34 F. P. C. 1462, 1465 (1965). 1 Because the Flood Control Act imposed no particular procedures for Commission review of rate proposals, the Commission was largely free to design its own. See Southeastern Power Administration, 54 F. P. C. 1631, 1632, n. (1975). It developed a practice of affording notice and comment to customers and other affected parties when the Secretary submitted a rate schedule, and granting requests for oral argument or public hearing on a case-by-case basis.

The parties differ as to the degree to which Commission practice included the use of interim rates. The Solicitor General cites several instances in which the Commission did *661 implement such rates; respondents answer that those instances were both isolated and unrepresentative. Our own examination of the historical record reveals that beginning in the 1970’s, the Commission announced its intention to examine PMA rate proposals “on the basis of evidentiary records which are developed during the course of [adjudicatory] public hearings,” Bonneville Power Administration, 54 F. P. C. 808, 810 (1975). It provided for full administrative hearings with cross-examination of witnesses. 2 At the same time, the Commission adopted, in some cases, the practice of examining rates submitted to it by the Secretary and, if the rates appeared to lie within the statutory boundaries, approving them on an interim basis pending the formal hearing. It required that the PMA refund any overcharges with interest if the Commission found after a hearing that an approved interim rate had been too high. See Southeastern Power Administration, 54 F. P. C. 3 (1975); Bonneville Power Administration, 52 F. P. C. 1912 (1974); see also Bonneville Power Administration, 58 F. P. C. 2498 (1977) (Federal Columbia River Transmission System Act). The Department of the Interior initially took the view that full evidentiary hearings were inappropriate under the Flood Control Act, and that if such hearings were to be held the Commission had no power to approve rates on an interim basis. The Commission, however, explicitly rejected that position. Southeastern Power Administration, supra, at 1632-1633; see also Bonneville Power Administration, 59 F. P. C. 1194, 1195 (1977) (Federal Columbia River Transmission System Act). The Interior Department then acquiesced in the Commission’s view. See ibid.

*662 B

This regulatory scheme was upset in 1977, with the passage of the Department of Energy Organization Act, 42 U. S. C. § 7101 et seq. (DOE Act). That statute, designed to “assur[e] coordinated and effective administration of Federal energy policy and programs,” §7112, eliminated the Secretary of the Interior’s role in hydroelectric power rate regulation, and abolished the Federal Power Commission entirely. The Interior Secretary’s rate-proposing function was transferred to the new Secretary of Energy, “acting by and through [the] Administrators” of the PMAs. § 7152(a)(2). The Federal Power Commission’s rate approval function was transferred to the Secretary of Energy as well. 3

The Secretary of Energy institutionalized an interim rate-approval process for hydroelectric rates.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chandler v. United States
District of Columbia Court of Appeals, 2026
East Bay Sanctuary Covenant v. Donald Trump
993 F.3d 640 (Ninth Circuit, 2020)
Statesman II Apartments, Inc. v. United States
66 Fed. Cl. 608 (Federal Claims, 2005)
North Star Steel Co. v. United States
58 Fed. Cl. 720 (Federal Claims, 2003)
Ramirez v. State
96 S.W.3d 386 (Court of Appeals of Texas, 2003)
United States v. Mead Corp.
533 U.S. 218 (Supreme Court, 2001)
Bragg v. West Virginia Coal Ass'n
248 F.3d 275 (Fourth Circuit, 2001)
Sierra Club v. Larson
First Circuit, 1993
Haynes Ambulance Service, Inc. v. Alabama
820 F. Supp. 590 (M.D. Alabama, 1993)
HAYNES AMBULANCE SERVICE v. State of Ala.
820 F. Supp. 590 (M.D. Alabama, 1993)
New York City Health & Hospitals Corp. v. Perales
954 F.2d 854 (Second Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
475 U.S. 657, 106 S. Ct. 1422, 89 L. Ed. 2d 661, 1986 U.S. LEXIS 93, 54 U.S.L.W. 4343, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-city-of-fulton-scotus-1986.