A4 Construction Company, Inc

CourtArmed Services Board of Contract Appeals
DecidedMay 16, 2025
Docket63252, 63456, 63626, 63961
StatusPublished

This text of A4 Construction Company, Inc (A4 Construction Company, Inc) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A4 Construction Company, Inc, (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of - ) ) A4 Construction Company, Inc. ) ASBCA Nos. 63252, 63456 ) 63626, 63961 ) Under Contract Nos. W9128F-19-C-0016 ) W9128F-19-C-0018 )

APPEARANCE FOR THE APPELLANT: Denver C. Snuffer, Jr., Esq. Nelson, Snuffer, Dahle & Poulsen, P.C. Sandy, UT

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Jacob W. Harberg, Esq. Thomas J. Tracy, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Omaha

OPINION BY ADMINISTRATIVE JUDGE TAYLOR ON THE GOVERNMENT’S PARTIAL MOTION FOR SUMMARY JUDGMENT

The United States Army Corps of Engineers (USACE or government) awarded two contracts to A4 Construction Company, Inc. (A4) to design and construct training facilities for the United States Special Forces at Fort Carson, Colorado. The government terminated Contract No. W9128F-19-C-0016 (the Mountaineering Contract) for default (Mountaineering R4, tab 3). 1 A4 appealed that default termination to the Board, and the Board docketed the appeal as ASBCA No. 63252. A4 then submitted numerous claims on the Mountaineering Contract to the USACE contracting officer (Mountaineering R4, tab 86). The USACE contracting officer denied the claims, and A4 appealed that decision to the Board (Mountaineering R4, tab 88). The Board assigned ASBCA No. 63456 to the appeal. On March 28, 2022, the USACE terminated Contract No. W9128F-19-C-0018 (the HPTC Contract) for default (HPTC R4, tab 99). A4 appealed that termination for default to the United

1 The R4 file citations are to the government’s revised Rule 4 file submitted May 16, 2024. In that Rule 4 file, the government listed the documents related to the Mountaineering Contract as “Tab 2-XXX”. The government listed the documents related to the HPTC Contract as “Tab 3-XXX”. For ease of reference, the Board drops the references to “Tab 2” and “Tab 3” and cites these documents as “Mountaineering R4, tab X” and “HPTC R4, tab X”). States Court of Federal Claims. 2 A4 then submitted various equitable adjustment claims on the HPTC Contract to the USACE contracting officer (HPTC R4, tab 2). The USACE contracting officer subsequently denied those claims (HPTC R4, tab 3). A4 appealed that denial to the Board, and the Board docketed the appeal as ASBCA No. 63626.

In October 2023, the USACE filed a motion to dismiss ASBCA No. 63456 for failure to state a claim. The Board partially granted the government’s motion and struck three complaint paragraphs from that appeal due to A4’s failure to provide a sum certain amount for each of those distinct claims. 3 A4 subsequently submitted new claims for those items with sum certain amounts which the contracting officer summarily denied. A4 appealed that denial to the Board, and the Board assigned ASBCA No. 63961 to the appeal. The Board consolidated all four appeals. 4

Now pending before the Board is the government’s partial motion for summary judgment on eight of A4’s claims in ASBCA Nos. 63252 and 63456 and five of A4’s claims in ASBCA No. 63626. 5 The government contends the parties previously resolved those claims through bilateral modifications many of which contained specific releases. A4 responds that some of those modifications do not address the subject matter of its claims, there was no meeting of the minds on the modifications, and it signed the modifications under duress following the government’s assurance that A4 could later bring similar claims. For the reasons discussed below, we partially grant the government’s motion.

2 The parties indicate the Court of Federal Claims suspended that proceeding pending the outcome of the Board appeals. 3 See A4 Construction Company, Inc., ASBCA No. 63252 et al., 24-1 BCA ¶ 38,578. 4 While ASBCA No. 63961 is consolidated with ASBCA Nos. 63252, 63456 and 63626, this motion does not apply to that appeal. ASBCA No. 63961 involves the three equitable adjustment claims the Board previously dismissed for failing to state a sum certain amount. Those claims include the Mountaineering Contract earthquake delay and impact claim, the COVID-19 related impacts, and delays resulting from replacing the subcontractor BZ Phase. 5 In its summary judgment motion, the government initially lists six mountaineering contract claims (gov’t mot. at 5). The government, however, does not include A4’s earthquake delay claim in this listing even though the government discusses that claim in its argument (id. at 34-35). In addition, the government lists A4’s BZ Phase subcontractor and July 2021 flood claims as one item (id. at 5). In our decision, we separately address each of A4’s eight Mountaineering Contract claims for which the government moves for summary judgment.

2 STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

The government included a statement of undisputed material facts with its motion (gov’t mot. at 6-23) (GSUMF). In its opposition, appellant responded to the government’s statement of undisputed material facts and provided some additional material facts (app. opp’n at 29-38) (ASUMF). The following facts are undisputed or uncontroverted.

The Contract Awards

1. On April 19, 2019, the USACE awarded the fixed-price Mountaineering Contract to A4 to design and construct a special operations forces mountaineering facility (the mountaineering project) at Fort Carson, Colorado (Mountaineering R4, tab 4).

2. On May 3, 2019, the USACE awarded the fixed-price HPTC Contract to A4 to design and construct a special operations forces human performance training center (the HPTC project) at Fort Carson, Colorado (HPTC R4, tab 5).

3. The USACE issued A4 notices to proceed (NTP) for both contracts on June 11, 2019 (Mountaineering R4, tab 6; HPTC R4, tab 6). The original contract completion date (CCD) for both contracts was May 31, 2021 (gov’t mot. at 7; GSUMF ¶ 3).

The Eight Mountaineering Contract Claims

March 2020 Earthquake & COVID-19 Claim

4. On June 11, 2020, A4 submitted a letter to the USACE requesting a 60 working day no cost time extension to the Mountaineering Contract due to a March 2020 earthquake and COVID-19 impacts (Mountaineering Contract R4, tab 86 at 7101-02). A4 claimed an earthquake in Utah resulted in its architect being out of communication for two days (id. at 7101). A4 also claimed the COVID-19 pandemic caused workflow disruptions (id. at 7101-02).

5. A4 and the USACE subsequently agreed to Mountaineering Contract bilateral Modification No. A00001, with an effective date of July 17, 2020, to address the adverse weather, earthquake and COVID-19 impacts during the period of March 1, 2020, through June 30, 2020 (Mountaineering R4, tab 8). Modification No. A00001 increased the contract duration by 14 days – two days due to the earthquake and 12 days due to COVID-19 (id. at 4336). The modification indicated the parties “understood and agreed” the contract would be extended zero days for the weather impact during that period (id.) Mr. Shawn Anderson electronically signed the

3 modification on A4’s behalf (id. at 4335). Mr. Anderson was A4’s vice president (gov’t mot. at 7; GSUMF ¶ 5).

6. Page three of the modification contained a standard release. That release stated:

In consideration of the modification(s) agreed to herein, the contractor hereby releases the government from any and all liability under this contract for further equitable adjustments attributable to such facts or circumstances. It is understood and agreed that the adjustment to the contract price and time for performance set forth herein is inclusive of all costs and time incurred by the contractor as a consequence of this modification individually and collectively with other modifications including, but not limited to, those for delay, impact, inefficiency and extended field and home office overhead.

(Mountaineering R4, tab 8 at 4337)

7.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Enzo Biochem, Inc. v. Applera Corp.
599 F.3d 1325 (Federal Circuit, 2010)
United States v. Diebold, Inc.
369 U.S. 654 (Supreme Court, 1962)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Holland v. United States
621 F.3d 1366 (Federal Circuit, 2010)
Bell Bci Co. v. United States
570 F.3d 1337 (Federal Circuit, 2009)
Pure Gold, Inc. v. Syntex (u.s.a.), Inc.
739 F.2d 624 (Federal Circuit, 1984)
Liebherr Crane Corporation v. The United States
810 F.2d 1153 (Federal Circuit, 1987)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Maxima Corporation v. The United States
847 F.2d 1549 (Federal Circuit, 1988)
McAbee Construction, Inc. v. United States
97 F.3d 1431 (Federal Circuit, 1996)
Am-Pro Protective Agency, Inc. v. United States
281 F.3d 1234 (Federal Circuit, 2002)
Johnson, Drake & Piper, Inc. v. United States
531 F.2d 1037 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
A4 Construction Company, Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a4-construction-company-inc-asbca-2025.