Liebherr Crane Corporation v. The United States

810 F.2d 1153, 33 Cont. Cas. Fed. 75,072, 55 U.S.L.W. 2456, 1987 U.S. App. LEXIS 20
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 5, 1987
DocketAppeal 86-903
StatusPublished
Cited by44 cases

This text of 810 F.2d 1153 (Liebherr Crane Corporation v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Liebherr Crane Corporation v. The United States, 810 F.2d 1153, 33 Cont. Cas. Fed. 75,072, 55 U.S.L.W. 2456, 1987 U.S. App. LEXIS 20 (Fed. Cir. 1987).

Opinion

DAVIS, Circuit Judge.

Liebherr Crane Corporation (Liebherr) appeals from a decision of the Armed Services Board of Contract Appeals (ASBCA or Board), Liebherr Crane Corporation, 85-3 BCA ¶ 18,353 (1985), that upheld the contracting officer’s denial of Liebherr’s claim for price relief. We affirm.

I.

The facts found by the Board, all supported by substantial evidence and the extensive and detailed ASBCA findings, show this: On February 13, 1976, the Great Lakes Branch, Northern Division, of the Naval Facilities Engineering Command (Navy), issued a competitive solicitation seeking bids for the construction of two 50-gross ton portal cranes, with an option to provide and secure an additional 50-gross ton portal crane. The request for proposals included a 98-page technical specification which set forth detailed design requirements.

Mr. Heinz Schiller, president of Liebherr, assumed responsibility for the preparation of Liebherr’s proposal. There is no doubt that Schiller was careless in his perusal of the specification. Because he limited his examination to the principal performance requirements in the specification (3 or 4 pages out of 98), he overlooked certain special sections of substance which pertained to industry and military specification standards. The short of it is that Schiller’s cursory examination convinced him that Liebherr’s light-weight standard commercial crane, with minor modifications, would satisfy the Navy’s design specifications. Accordingly, he formulated a bid based upon the approximate weight of Liebherr’s standard Form 1500 crane (270 tons) multiplied by a factor of $4.00 per kilogram. 1 However, a careful reading of the specifications and the performance requirements would have disclosed the need for a much heavier crane. Although there were no *1155 explicit weight requirements prescribed by the specifications, in actual fact they required Liebherr to provide custom-designed cranes weighing between 705 and 786 tons each. Not surprisingly, Liebherr’s bid of $3,725,600 was dramatically lower than the next lowest bid of $7,131,860. 2 Indeed, the Government’s own estimate was $6,963,-950, a figure which did not include a 24 percent escalation and 5 percent Washington state sales tax.

The Navy immediately noted the wide disparity between Liebherr’s bid and the range of the other responsive proposals, and requested Liebherr to confirm its bid. (The discrepancies between the various bids and estimates were not then pointed out to Liebherr.) By telegram dated May 5, 1976, Liebherr responded:

We confirmed [sic] herewith that all prices which we quoted to you under the ... solicitation ... are as intended and remain unchanged. Our prices and our proposal, as submitted, present full technical performance to all contracts, specifications as stated therein. We further inform you that we are complying with your request to submit in writing, evidence of our previous experience in accordance with Clause Number J-9 as stated in your solicitation. Please be advised that we have been building portal cranes since 1948, and that since 1948 we are one of the world’s largest crane manufacturers.

Liebherr’s confirmation failed fully to reassure the Navy. On two separate occasions, the Navy sought further verification of Liebherr’s intent to honor its bid and perform the contract according to specifications. First, by letter dated May 14, 1976, the Navy invited all bidders to submit “a best and final offer” before May 25, 1976. Liebherr’s response of May 20, 1976 reiterated the same prices quoted in its original proposal and even included an alternate proposal offering a discount of $30,000 per crane.

Because the submission of “best and final offers” did nothing to reduce the great disparity between Liebherr’s price and the range of other bids, the Navy summoned Liebherr representatives, including Schiller, to a pre-award conference on May 27, 1976. Apparently, the intended purpose of the meeting was to determine whether Lie-bherr understood the specification requirements and was capable of performing.

During the meeting, Navy personnel reviewed four drawings and miscellaneous brochures furnished by Liebherr. In addition, the parties discussed certain technical matters including the design engineering requirements and several individual specification elements. Also, part of the meeting was devoted to discussion of the drawing submission requirements under the contract. 3

Although the Navy’s Procuring Contracting Officer previously had instructed Schiller to bring cost data to the conference, the latter failed to do so. Instead, he broke Liebherr’s bid down into its component parts, assigning relative percentages to engineering, materials and labor. Schiller estimated the cost of crane erection alone to be 5 percent of the total cost ($60,000). When Navy personnel remarked that this was quite low, Schiller commented that an error of $10,000 to $12,000 for this component was relatively small when compared to the total amount of procurement involved. 4

*1156 Based on the information obtained at that meeting, the Navy concluded that Lie-bherr had both the ability and intent to perform the contract in accordance with the specifications. This conclusion was bolstered in part by Schiller’s emphatic reassurances during the course of the meeting that Liebherr intended to provide the crane as described in the specifications. On June 24, 1976, the Navy awarded the contract to Liebherr.

During the 15 months following the contract award, Liebherr submitted approximately 30 preliminary drawings. Nevertheless, the Navy was unable to discern Liebherr’s intended crane design from these initial drawings, many of which were of poor quality, annotated in German and conflicted with one another. At one point, the Navy suspected that Liebherr was attempting to inveigle the Government into joint participation in the design effort, a duty explicitly reserved by the contract to Liebherr. Eventually, unable to determine whether the drawings submitted were merely proposed alternatives or intended for final review and approval, the Navy refused to accept any further informal drawings submitted by Liebherr.

By the fall of 1977, Schiller realized that Liebherr was going to lose money under the contract. As a result, he wrote to the Navy and admitted an unspecified “calculation error.” According to that letter, in order for Liebherr to continue under the contract it was essential that the company obtain some price relief. The Navy responded to Schiller’s letter by summoning Liebherr representatives to a meeting held on October 3, 1977.

During the course of that meeting, the Navy voiced its concern that, as matters stood, Liebherr would be unable to complete delivery of the cranes within the time frame set forth in the contract. Because of the contract’s high defense priority, the Navy stressed the importance of timely completion of the contract and the serious consequences of default.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A4 Construction Company, Inc
Armed Services Board of Contract Appeals, 2025
Asset Protection & Security v. United States
5 F.4th 1361 (Federal Circuit, 2021)
LKJ Crabbe Inc.
Armed Services Board of Contract Appeals, 2018
Zafer Construction Company
Armed Services Board of Contract Appeals, 2017
Ulysses, Inc. v. United States
110 Fed. Cl. 618 (Federal Claims, 2013)
Lakeshore Engineering Services, Inc. v. United States
110 Fed. Cl. 230 (Federal Claims, 2013)
P & K Contracting, Inc. v. United States
108 Fed. Cl. 380 (Federal Claims, 2012)
East Porter County School Corp. v. Gough, Inc.
965 N.E.2d 684 (Indiana Court of Appeals, 2012)
Virgin Islands Paving, Inc. v. United States
103 Fed. Cl. 292 (Federal Claims, 2012)
Hallwood Plaza, Inc. v. United States
84 Fed. Cl. 804 (Federal Claims, 2008)
Enron Federal Solutions, Inc. v. United States
80 Fed. Cl. 382 (Federal Claims, 2008)
La Gloria Oil & Gas Co. v. United States
72 Fed. Cl. 544 (Federal Claims, 2006)
Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)
Mid-States General & Mechanical Contracting Corp. v. Town of Goodland
811 N.E.2d 425 (Indiana Court of Appeals, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
810 F.2d 1153, 33 Cont. Cas. Fed. 75,072, 55 U.S.L.W. 2456, 1987 U.S. App. LEXIS 20, Counsel Stack Legal Research, https://law.counselstack.com/opinion/liebherr-crane-corporation-v-the-united-states-cafc-1987.