United States v. Hamilton Enterprises, Inc.

711 F.2d 1038, 31 Cont. Cas. Fed. 71,239, 1983 U.S. App. LEXIS 13606
CourtCourt of Appeals for the Federal Circuit
DecidedJune 6, 1983
DocketAppeal 37-82
StatusPublished
Cited by33 cases

This text of 711 F.2d 1038 (United States v. Hamilton Enterprises, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Hamilton Enterprises, Inc., 711 F.2d 1038, 31 Cont. Cas. Fed. 71,239, 1983 U.S. App. LEXIS 13606 (Fed. Cir. 1983).

Opinion

COWEN,

Senior Circuit Judge.

This is an appeal by the United States (Government or Navy) from a decision of the Armed Services Board of Contract Appeals 1 (Board or ASBCA) in which the Board held that it had jurisdiction under the Contract Disputes Act of 1978 (CDA) of the appellee’s (Hamilton or contractor) claim for reformation; that Hamilton’s con *1039 tract was improperly terminated for default; that the excess reprocurement costs which the Government claimed should be disallowed, and that the Government’s claim for the cost of military services furnished in the performance of the contract should be denied. The Board found that Hamilton made a mistake in its bid; that the Government’s request for verification was inadequate, and that the acceptance of Hamilton’s low bid resulted in a contract that was unconscionably priced. In addition to the other relief granted, the Board found that Hamilton was entitled to recover its losses which amounted to $206,101.

We affirm the Board’s denial of the Government’s claims for excess reprocurement costs and for the costs of military services furnished by the Navy. However, we reverse the Board’s award of damages to the contractor and hold that its recovery is limited to the amount retained by the Navy as an offset against the claim for excess reprocurement costs.

I. Background.

On February 28,1979, the Navy awarded Hamilton a fixed price contract to provide mess attendant services for the enlisted men’s dining facility at the Naval Air Station, near Memphis, Tennessee. The initial contract was for 6 months, with an option for an additional 12 months. The contract was to be performed in three phases. Phase I commenced April 1, 1979, and required Hamilton to clean the dining facility. Phase II, which commenced May 1, 1979, continued the responsibilities of Phase I, and also obligated the contractor to set up, operate and secure the serving line. Phase III, which commenced June 1, 1979, continued the duties involved in Phases I and II and in addition, required Hamilton to perform specified duties in the vegetable preparation room. The purpose of the phasing-in periods was to offset the fact that the successful bidder would be the first civilian contractor in the fourth largest mess facility in the Navy.

As the result of formal advertising, 31 bids were received as follows:

Bidder Total Evaluated Bid
Groves Contract Services, Inc. $ 966,037.3173 Aseptic Services, Inc. 1,012,748.77
Trinity Services, Inc. 1,023,397.164
Hamilton Enterprises, Inc. 1,025,178.795
Hume, Inc. 1,034,203.555
United Services, Inc. 1,240,185.60
Space Services of GA. 1,253,842.832
World Wide Services, Inc. 1,389,856.012
Versal Enterprises 1,392,518.00
K & P Food Services, Inc. 1,405,943.99
Allied Industrial Services 1,405,947.04
Tamp Corp. 1,611,057.28
Urban Laboratories 1,630,011.328
TAM, Inc. 1,645,624.857
Jets Services, Inc. 1,658,700.00
Versatile Services, Inc. 1,674,666.873
Palmetto Enterprises 1,682,942.081
Malones Better Management 1,691,396.45
Murphy Super Services 1,703,657.74
Emmanuel Services 1,752,300.00
Industrial Maintenance Services 1,807,387.063 M & M Services 1,812,067.53
T & S Services 1,830,115.98
Management Services 1,900,172.00
Meldick Services 1,910,620.069
Old Hickory Services 1,961,841.50
Diversified Equipment 1,988,040.00
Gill Hill Enterprises 2,024,946.00
TBS Service Co. 2,480,072.00
Ky. Building Maintenance 2,670,757.00
Logistical Support, Inc. 2,770,950.576

The Government’s estimate for the services was $3,251,130, making Hamilton’s bid only 31 percent of that estimate.

The initial low bidder was allowed to withdraw its bid, because of a mistake in its G & A costs. The second low bidder became bankrupt and was determined to be nonresponsible. The third low bidder was disqualified, because of its refusal to extend its bid past the initial acceptance date because of an alleged mistake in its bid.

In response to the Government’s request, Hamilton verified its bid; the Government performed a pre-award bid survey, and then awarded the contract to Hamilton without holding a prebid conference.

Hamilton began performance on April 1, 1979. On May 2, 1979, Hamilton filed a *1040 request with the contracting officer for an equitable adjustment. The claim was for excess hours of work allegedly expended by Hamilton’s employees as a result of the failure of the Government to furnish equipment and supplies it was obligated to provide, and because of work which Hamilton says it was required to perform in violation of the terms of the contract. Except for two small claims, the contracting officer, on May 30, 1979, denied the request for an equitable adjustment.

On June 1, 1979, Hamilton filed a second request for an equitable adjustment, which like the first claim was a request for compensation for the cost of additional hours of work which Hamilton claimed were not required by the terms of the contract and the specifications.

By letter of June 19, 1979, to the contracting officer, the contractor’s attorney stated that in view of the manhours of labor required to perform the contract, Hamilton was losing so much money that it would soon be bankrupt. The letter further stated that since the contracting officer had denied Hamilton’s request to terminate the contract for the convenience of the Government, Hamilton had no alternative but to reduce the manhours performed at the facility to the contractor’s estimate of man-hours (namely 456 manhours per day) furnished to the Government before the bid was accepted.

Beginning on June 28, 1979, Hamilton reduced its staffing to the 456 manhours per day estimated in its manning charts. Prior to that time, Hamilton had been providing about 1,100 manhours per day, which was close to the number of manhours the Government had estimated in preparing the bid package for letting the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Asset Protection & Security v. United States
5 F.4th 1361 (Federal Circuit, 2021)
Zafer Construction Company
Armed Services Board of Contract Appeals, 2017
Caddell Construction Company v. United States
125 Fed. Cl. 30 (Federal Claims, 2016)
Ulysses, Inc. v. United States
110 Fed. Cl. 618 (Federal Claims, 2013)
Lakeshore Engineering Services, Inc. v. United States
110 Fed. Cl. 230 (Federal Claims, 2013)
Hallwood Plaza, Inc. v. United States
84 Fed. Cl. 804 (Federal Claims, 2008)
PHT Supply Corp. v. United States
71 Fed. Cl. 1 (Federal Claims, 2006)
Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)
Efthimiou v. Smith
846 A.2d 216 (Supreme Court of Connecticut, 2004)
Will H. Hall & Son, Inc. v. United States
54 Fed. Cl. 436 (Federal Claims, 2002)
Griffy's Landscape Maintenance LLC v. United States
46 Fed. Cl. 257 (Federal Claims, 2000)
Giesler v. United States
44 Fed. Cl. 737 (Federal Claims, 1999)
Francis v. Recycling Solutions, Inc.
695 A.2d 63 (District of Columbia Court of Appeals, 1997)
Alcan Electrical & Engineering Co. v. United States
37 Cont. Cas. Fed. 76,250 (Court of Claims, 1992)
Goldberger Foods, Inc. v. United States
37 Cont. Cas. Fed. 76,111 (Court of Claims, 1991)
Edwards v. United States
36 Cont. Cas. Fed. 75,822 (Court of Claims, 1990)
Fadeley v. United States
35 Cont. Cas. Fed. 75,583 (Court of Claims, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
711 F.2d 1038, 31 Cont. Cas. Fed. 71,239, 1983 U.S. App. LEXIS 13606, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-hamilton-enterprises-inc-cafc-1983.