Sulzer Bingham Pumps, Inc., a Delaware Corporation v. Lockheed Missiles & Space Company, Inc., a California Corporation

947 F.2d 1362, 37 Cont. Cas. Fed. 76,209, 91 Cal. Daily Op. Serv. 8515, 91 Daily Journal DAR 13169, 1991 U.S. App. LEXIS 24966
CourtCourt of Appeals for the Ninth Circuit
DecidedOctober 25, 1991
Docket91-35315
StatusPublished
Cited by2 cases

This text of 947 F.2d 1362 (Sulzer Bingham Pumps, Inc., a Delaware Corporation v. Lockheed Missiles & Space Company, Inc., a California Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sulzer Bingham Pumps, Inc., a Delaware Corporation v. Lockheed Missiles & Space Company, Inc., a California Corporation, 947 F.2d 1362, 37 Cont. Cas. Fed. 76,209, 91 Cal. Daily Op. Serv. 8515, 91 Daily Journal DAR 13169, 1991 U.S. App. LEXIS 24966 (9th Cir. 1991).

Opinion

SCHROEDER, Circuit Judge:

This appeal arises out of an unusual dispute between a major government contractor and a subcontractor providing components for the United States Navy’s Trident II nuclear submarines. The contractor, Lockheed Missiles & Space Company, awarded a subcontract to the low bidder for the subcontract, the appellee Sulzer Bingham Pumps, Inc. Sulzer Bingham’s bid, however, was in fact millions of dollars lower than it would have been if Sulzer Bingham had not committed a series of errors in preparing the bid. According to the findings of the respected district judge who heard the evidence, Lockheed doubted that Sulzer Bingham could perform the contract at that price, but nevertheless awarded the contract for the bid price, resulting in an unconscionably low price. The district court concluded that Lockheed’s conduct amounted to overreaching in violation of basic contractual principles, and that its failure to ask the subcontractor to verify its bid violated the terms of the subcontract. The district court declined to rescind the contract. The district court did, however, award Sulzer Bingham some equitable relief in the form of the actual costs it incurred above the contract price, in a total amount which was not to exceed the next lowest bid. Lockheed appeals.

In its appeal, Lockheed raises two principal contentions. The first is that the terms of its contract did not incorporate the Federal Acquisition Regulations, and therefore did not require Lockheed to call the underbid to Sulzer Bingham’s attention and ask for verification of the suspect bid. The second is that government contract law does not permit a court ever to adjust the contract price where the underbid is the product of judgment errors as opposed to arithmetic miscalculations. We affirm the district court because we agree with the district court that Lockheed did breach the terms of its contract by failing to ask Sul-zer Bingham to verify the bid, and that Lockheed therefore must bear substantial responsibility for the unconscionably low price. We further agree with the district court that in these circumstances, the court *1364 was not foreclosed from fashioning equitable relief.

FACTUAL BACKGROUND

The facts as determined by the district court are not seriously disputed on appeal. They can be summarized as follows.

Lockheed is the prime contractor for the Navy’s Trident II nuclear submarines. The subcontract at issue involved the production of ballast cans. When the submarines are not carrying nuclear missiles, they need ballast cans for stability. Each ballast can weighs 64,000 pounds and stands 15 feet high.

In 1988, Lockheed sent out a request for quotation to potential subcontractors, seeking bids for the manufacture of 124 ballast cans. In February 1989, Lockheed received eight bids, including one from Sulzer Bingham. Sulzer Bingham was the lowest bidder at $6,544,055. The next lowest bid was $10,176,670, and the bids ranged up to $12,940,540, with one high bid at $17,766,-327. Lockheed estimated that the job would cost about $8.5 million.

Lockheed’s employees were shocked by Sulzer Bingham’s bid and thought it was surprisingly low. Price extensions, submitted to Lockheed by Sulzer Bingham, revealed no arithmetic errors. Lockheed then asked Sulzer Bingham to verify that its bid included shipping charges and First Article Compatibility Testing, but did not ask for verification of the entire bid. Sul-zer Bingham informed Lockheed that its bid was complete. Lockheed then inspected Sulzer Bingham’s Portland facility to evaluate Sulzer Bingham’s technical capabilities. The inspection revealed that Sul-zer Bingham would have to make many modifications to its existing facility in order to complete the contract. The turntable Sulzer Bingham anticipated using for machining and assembling the ballast cans was inadequate, and an entirely new lead pouring facility needed to be constructed. None of these shortcomings were revealed to Sulzer Bingham by Lockheed.

At no time did Lockheed notify Sulzer Bingham that it suspected a mistake in Sulzer Bingham’s bid. Lockheed did not inform Sulzer Bingham that its bid was significantly lower than the next lowest bid, and lower than Lockheed’s own estimate of the cost of the job as well. Lockheed never informed Sulzer Bingham that it suspected that Sulzer Bingham would not be able to complete the contract at the bid price.

Sulzer Bingham made a variety of errors in its bid. It had underestimated the number of hours the job would require, and had used hourly labor rates that were below cost. Sulzer Bingham had not realized that its existing facilities were inadequate for the job, and had overlooked certain costs of the job. Sulzer Bingham’s bid broke down to $30,707 per ballast can. The next lowest bid broke down to $58,137 per can, and Lockheed estimated at least $40,000 per can.

In late February 1989, Lockheed accepted Sulzer Bingham’s bid and Sulzer Bing-ham started work. In November 1989, Sul-zer Bingham revised its estimate of the cost of the job and asked Lockheed for an additional $2,111,000 in compensation. Lockheed rejected Sulzer Bingham’s request for additional compensation.

PROCEEDINGS BELOW

On April 11, 1990, Sulzer Bingham commenced this action against Lockheed in the Multnomah County, Oregon, Circuit Court. Sulzer Bingham sought to reform the contract by increasing the price from $6,534,-055 to $8,645,000. In the alternative Sulzer Bingham sought to rescind its bid.

On April 20, 1990, Lockheed removed the action to the United States District Court for the District of Oregon on the basis of diversity jurisdiction. A bench trial was conducted on December 11 and 12, 1990. On January 22, 1991, the district court issued its opinion ordering judgment for plaintiff.

The district court concluded that United States government contract law governed the contract, and that the Federal Acquisition Regulation, Title 48 of the Code of Federal Regulations, governed the action. The district court also concluded that under *1365 section 14.406-3 of the Federal Acquisition Regulation, Lockheed had a duty to notify Sulzer Bingham when it suspected a mistake in Sulzer Bingham’s bid. The district court further concluded that Lockheed breached this duty, and Sulzer Bingham was therefore entitled to equitable relief.

The district court denied rescission because Sulzer Bingham had delayed its request for rescission and because Sulzer Bingham had already completed about half of the contract. The district court then concluded that it could award Sulzer Bing-ham other equitable relief because Lockheed had breached its duty to verify Sulzer Bingham’s bid, and the resulting contract was unconscionable. The district court required Sulzer Bingham to complete the contract, and ordered that Sulzer Bingham could “recover its actual costs only, including a reasonable amount for depreciation and overhead. Under no circumstances may [Sulzer Bingham’s] recovery exceed the amount of the next lowest bid.”

THE APPLICABILITY OF FEDERAL ACQUISITION REGULATIONS REGARDING BID VERIFICATION

Lockheed argues that the district court erred in holding that the Federal Acquisition Regulations (“FAR”) imposed specific verification duties on Lockheed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
947 F.2d 1362, 37 Cont. Cas. Fed. 76,209, 91 Cal. Daily Op. Serv. 8515, 91 Daily Journal DAR 13169, 1991 U.S. App. LEXIS 24966, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sulzer-bingham-pumps-inc-a-delaware-corporation-v-lockheed-missiles-ca9-1991.