Will H. Hall & Son, Inc. v. United States

54 Fed. Cl. 436, 2002 U.S. Claims LEXIS 311, 2002 WL 31574318
CourtUnited States Court of Federal Claims
DecidedNovember 14, 2002
DocketNo. 99-1000C
StatusPublished
Cited by1 cases

This text of 54 Fed. Cl. 436 (Will H. Hall & Son, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Will H. Hall & Son, Inc. v. United States, 54 Fed. Cl. 436, 2002 U.S. Claims LEXIS 311, 2002 WL 31574318 (uscfc 2002).

Opinion

OPINION

WILSON, Judge.

This contract dispute is before the Court on cross-motions for summary judgment, pursuant to RCFC 56(c), on plaintiffs claim for reformation of a construction contract based on alleged mistake in bid. For the reasons discussed below, defendant’s motion for summary judgment is GRANTED, and plaintiffs cross-motion for summary judgment is DENIED.

BACKGROUND

In November 1995, the Employment and Training Administration of the Department of Labor (the “DOL”) issued a solicitation of bids for Contract No. E-5715-6-00-82-20. The contract called for the construction of five buildings (the “base bid”) at the Job Corps Center in Flint, Michigan, and in addition, three options (for the construction of two other buildings and an addition to a third), and thirteen alternate projects. Four contractors submitted bids to the DOL by the 2:00 p.m. deadline on January 11, 1996. Plaintiff Will H. Hall and Son, Inc. submitted the lowest bid of $17,230,000. The second lowest bid was $18,305,000. The acceptance period for plaintiffs bid expired in sixty days, unless the contracting officer requested an extension pursuant to Federal Acquisition Regulation (FAR), 48 C.F.R. § 14.404-1(d) (1995).

In preparing its bid, plaintiff solicited and received quotes from subcontractors for specification sections 07410-Manufactured Metal Wall Paneling, 07415-Manufaetured Metal Roof Panels, and 07420-Composite Metal Panels. These sections required the fabrication of custom metal wall and roof panels both for the base bid buildings and the option buildings.

On January 17, 1996 (six days after the DOL opened the bids), plaintiff notified the DOL that it had mistakenly failed to include any estimate in its bid for section 07420-Composite Metal Panels.1 Plaintiffs bid allegedly relied on a quote from subcontractor C.L. Rieckhoff Co., Inc. (“Rieckhoff’) for sections 07410, 07415, and 07420. However, the Rieckhoff quote included work under sections 07410 and 07415 only and expressly excluded the work required under section 07420. In its haste to meet the bid deadline, plaintiff alleges it mistakenly assumed that the Rieckhoff quote included all three sections, overlooking the express language to the contrary.

[438]*438Upon notification by plaintiff, the DOL contracting officer advised plaintiff to provide evidence of its alleged mistake, pursuant to 48 C.F.R. § 14.407-3(g). Plaintiff subsequently submitted computer-generated bid summaries dated January 17,1996 (one week after the deadline for bids), together with copies of the Rieckhoff quote and three other subcontractor quotes. Plaintiff annotated by hand the relevant portions of these documents to demonstrate the nature of its mistake and the impact on the amount of its bid. The Rieckhoff quote indicated a price for sections 07410 and 07415 of $351,030 for the base bid, $1,220 for option one, and $10,850 for option two.2

Plaintiff initially advised the contracting officer that its mistaken use of Rieckhoffs quote, which excluded section 07420, had reduced plaintiffs total bid by $438,000, and plaintiff asked for an upward adjustment of its bid in that amount.3 Pursuant to 48 C.F.R. § 14.407-3(g) and the contracting officer’s request, plaintiff provided copies of its original, handwritten bid tabulation worksheets.4 Plaintiffs original worksheets include items entitled “wall and roof panels” under the base bid and options one and two. Plaintiff allegedly intended this item to be a category inclusive of sections 07410,' 07415, and 07420. The amount entered for the base bid “wall and roof panels” item was $351,030. Unlike the majority of items on plaintiffs worksheets, no contractor is identified next to the quote. However, $351,030 is precisely the amount of the Rieckhoff quote upon which plaintiff allegedly relied. The “wall and roof panel” items for the option one and two worksheets are devoid of both contractor names and prices. Plaintiffs worksheet for option three does not list a “wall and roof panel” item at all. (Stipulated Material Facts at ¶¶19-20; App. to Def.’s Mot. for Summ. J. at 15, 30, 47.)

Although the contracting officer advised plaintiff telephonically to submit worksheets documenting its alleged mistake, he did not advise plaintiff in writing to submit a written request to correct or withdraw its bid as required by 48 C.F.R. 14.407-3(g)(2). The parties dispute whether the contracting officer ever told plaintiff that the option of withdrawal was available, but plaintiff never requested withdrawal, written or otherwise. The contracting officer maintains that he informed plaintiff that it could request withdrawal, and that plaintiff “emphatically rejected that option and declared that [plaintiff] would perform at its original bid price.” (3d App. to Pl.’s Compl. at 2.) In their affidavits, plaintiffs secretary and treasurer, Troy W. Hall, and an assistant, Brenda R. Williams, deny ever being in[439]*439formed that they could request withdrawal. (App. B to Pl.’s Statement of Genuine Issues at 1; App. C at 2) The government concedes that the contracting officer did not submit plaintiffs claim to the head of the agency or another higher authority for decision as required by 48 C.F.R. § 14.407-3(g)(2)-(3) and (c)(2). However, before the contract was awarded, the contracting officer advised plaintiff by telephone that it would not be permitted to correct its alleged bid mistake because it could not meet the requirements of the FAR. (Stipulated Material Facts at ¶27.)

On March 11, 1996 (the sixty-day bid acceptance deadline), the DOL awarded the contract to plaintiff at the original bid price of $17,230,000. Plaintiff began performance of the contract, but later made a written request to the contracting officer for reconsideration of its original request to correct the mistake in bid. By letter dated October 6, 1996, the contracting officer denied plaintiffs request, stating that “although there was evidence of a mistake in [plaintiffs] bid, there was no evidence of the intended bid as required by FAR [48 C.F.R.] 14.407-3(c)(1).” In a final decision dated March 24, 1997, the contracting officer reaffirmed his denial of plaintiffs claim, based on a lack of clear and convincing evidence of both the existence of a mistake and the intended bid.

Plaintiffs initial suit in this court alleged damages of $526,260 plus “markups for general conditions, bond and profit” in unspecified amounts.5 However, the suit was voluntarily dismissed without prejudice because plaintiff did not properly certify its claim. Plaintiff subsequently submitted a certified claim to the contracting officer for $555,191.67 (the CEI quote of $526,260 plus 5.5% in markups for general conditions, bond, and profit), which was denied in a second final decision dated August 16, 1999.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
54 Fed. Cl. 436, 2002 U.S. Claims LEXIS 311, 2002 WL 31574318, Counsel Stack Legal Research, https://law.counselstack.com/opinion/will-h-hall-son-inc-v-united-states-uscfc-2002.