Fadeley v. United States

35 Cont. Cas. Fed. 75,583, 15 Cl. Ct. 706, 1988 U.S. Claims LEXIS 183, 1988 WL 116346
CourtUnited States Court of Claims
DecidedNovember 1, 1988
DocketNo. 95-87C
StatusPublished
Cited by1 cases

This text of 35 Cont. Cas. Fed. 75,583 (Fadeley v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fadeley v. United States, 35 Cont. Cas. Fed. 75,583, 15 Cl. Ct. 706, 1988 U.S. Claims LEXIS 183, 1988 WL 116346 (cc 1988).

Opinion

OPINION

NAPIER, Judge:

This suit arises out of a contract between Allsteel Products Company, Inc. (“Allst-eel”), as the principal and contractor, and the Department of the Army. Allsteel seeks reformation of the subject contract in the amount of $42,678.72, based on a mistake in its bid of the same amount. The parties have stipulated the relevant facts of the case and have made cross-motions for summary judgment.

Facts

The parties’ agreed statements of uncon-troverted facts, insofar as pertinent, are as follows. On September 25,1985, the Office of the Directorate of Contracting, Fort Jackson, South Carolina, requested that Allsteel submit a bid for Solicitation No. DABT47-85-B-0102, a project involving the repair of latrine facilities. Allsteel complied with the Government’s request, and bid opening took place 2 days later, on September 27, 1985.

Of the two bids received by the Government, Allsteel’s was the lower by 13 percent, and was $575 less than the Government’s estimate for the job. Specifically, Allsteel’s offer amounted to $370,000 while the Government’s estimate for the project was $370,575, and the only other bid, submitted by Energy Management Company, was in the amount of $418,000.

Those present at the bid opening on September 27, 1985, were Juanita H. Mercer, Contract Specialist for the Government; Coles Dwight, Estimator/Project Manager for Allsteel; and Mr. Hutto, an Energy Management Company employee. Upon opening the bids, Ms. Mercer did not consider the 13 percent price differential significant enough to warrant a bid verification. Nor did any other unusual objective factors suggest to her that bid confirmation may be necessary. Ms. Mercer did notice, however, that Mr. Dwight of Allst-eel appeared uncomfortable with the difference between the two bids. She thereupon requested that Mr. Dwight confirm Allst-eel’s bid. Mr. Dwight was provided with a blank sheet of paper upon which to verify his company’s offer. Later that same day, he returned a signed confirmation of Allst-eel’s bid.

The subject contract was awarded to Allsteel the following Monday, on September 30, 1985, somewhat more expeditiously than would have been the case were not the fiscal year coming to a close. On or about October 1,1985, Allsteel discovered a mistake in its bid whereby a price for 6,720 square feet of ceramic tile had been omitted. The parties stipulate that plaintiff’s bid mistake was caused by an error in estimating the materials necessary for the project. Allsteel claims that it would have charged the Government $42,678.72 for this tile. Two weeks later, on October 15,1985, Allsteel notified the Government of its mistake and requested permission to withdraw its bid. The Government denied this request. Allsteel then submitted a request for an increase in the contract price of $42,678.72, the amount of the mistake. On February 27, 1986, the contracting officer issued its final decision denying Allsteel’s claim for said amount. Upon reconsideration of the claim and supporting documentation, the Government informed Allsteel on May 28, 1986, that the error was a unilateral mistake in estimating the materials necessary for the project, and as such was not compensable.

By letter of June 6, 1986, Allsteel again protested the contracting officer’s adverse [708]*708decision, and several weeks later on June 27, 1986, notified the Government that it was commencing work under protest. Allsteel timely filed a complaint with this Court on February 24, 1987. The Court has jurisdiction to entertain plaintiff’s suit under the Tucker Act, 28 U.S.C. § 1491, and the Contract Disputes Act, 41 U.S.C. § 608.1

Discussion

Where the parties have based their joint motion for summary judgment upon a statement of undisputed facts and exhibits, which leaves the Court with no question as to any material fact, summary judgment is appropriate.2 Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986); see Aydin Corp. v. United States, 229 Ct.Cl. 309, 322, 669 F.2d 681, 689 (1982).

Plaintiff presents three alternative arguments for relief to the Court. Plaintiff first argues that the price omission was a mutual mistake, made jointly by plaintiff and the Government. Secondly, plaintiff contends that even if the mistake were made unilaterally by plaintiff, the Government representative knew or should have known of it. As a last alternative, plaintiff argues for the application of equitable principles. In this argument, plaintiff attempts to convince the Court that good faith and fair dealing require monetary relief where, as here, the Government has rushed plaintiff into bid submission and subsequent verification.

Defendant submits that plaintiffs bid mistake was unilateral, a mistake of which the Government neither knew nor had reason to know. The Government advocates the application of a “reasonableness” standard for the Court’s determination of whether the Government official should have been alerted to Allsteel’s bid mistake. Furthermore, according to defendant, the bid verification procedures which took place upon bid opening were appropriate under the circumstances.

A mutual mistake is an error for which each party is partly responsible, or, a unilateral mistake which the other party knew or had reason to know of prior to consummation of the contract. Doke, Mistake In Government Contracts — Error Detection Duty of Contracting Officer, 18 Sw.L.J. 1 (1964) [hereinafter referred to as “Doke”.] Plaintiff claims that a mutual mistake occurred here, where the Government, anxious to appropriate funds before the end of the fiscal year, caused plaintiff to speed up its bidding process, resulting in the omission of the price for the ceramic tile.

Plaintiff is unable to cite the Court to any law where a mistake has been found to be “mutual” and the Government held responsible for a bid error when, in order to meet contractual deadlines imposed by the end of the fiscal year, the Government allows little time for a bidder to prepare and submit its bid. To the contrary, it is a contractor’s sole responsibility to exercise due care during bid preparation. If a contractor is not certain that his bid is true and correct, under no circumstances should he represent that it is, by signing the bid.

There is no evidence that the Government was directly responsible for Allsteel’s bid mistake. At issue, then, is whether the Government knew or should have known of the error, and, thus, was indirectly responsible for it.

Plaintiff correctly calls upon the Court to consider all factors surrounding the bid opening while making this determination:

[709]*709[T]he test here, as in so many areas, must be that of reasonableness, i.e., whether under the facts and circumstances of “the particular case there were any factors which reasonably should have raised the presumption of error in the mind of the contracting officer....”

Wender Presses, Inc. v. United States, 170 Ct.Cl. 483, 486, 343 F.2d 961, 963 (1965), quoting Welch,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Griffin & Griffin Exploration, LLC v. United States
116 Fed. Cl. 163 (Federal Claims, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
35 Cont. Cas. Fed. 75,583, 15 Cl. Ct. 706, 1988 U.S. Claims LEXIS 183, 1988 WL 116346, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fadeley-v-united-states-cc-1988.