Kemp v. United States

38 F. Supp. 568, 1941 U.S. Dist. LEXIS 3270
CourtDistrict Court, D. Maryland
DecidedApril 29, 1941
Docket903 Civil
StatusPublished
Cited by25 cases

This text of 38 F. Supp. 568 (Kemp v. United States) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kemp v. United States, 38 F. Supp. 568, 1941 U.S. Dist. LEXIS 3270 (D. Md. 1941).

Opinion

WILLIAM C. COLEMAN, District Judge.

This is a suit under the Tucker Act, 28 U.S.C.A. § 41(20), in which the plaintiff claims certain sums due him on account of contracts awarded to him to supply the Post Office and War Departments with certain equipment. A stipulation entered into and filed in the case removes from controversy a good deal of what might otherwise become rather complicated accounting questions.

Plaintiff claims approximately $9,000 with interest. In addition to its denial of a major part of this indebtedness, the Government has set up counterclaims alleging that the plaintiff owes it more than $9,000.

In so far as the claim with respect to the contracts with the Post Office Department is concerned, with the exception of one item relating to a lathe, the parties are not far apart. In fact, plaintiff has agreed, in the course of the trial, to accept a figure admitted by the Government, pursuant to the stipulation, to be due with respect to these various other contracts, namely, $1,279.58. Also, it is stipulated that the Government owes the plaintiff $8,149.41 on certain contracts with the War Department. So the controversy, thus abbreviated, involves only two matters: First, a contract for delivery of a lathe by the plaintiff to the Post Office Department; and, secondly, a contract for delivery by the plaintiff to the War Department of a motor-driven drilling machine for use at the Pickatinny Arsenal, Dover, New Jersey.

As to the first item, the Government contends that although the lathe was delivered, it was not up to specifications, both as respects the machine proper and its mode of operation, and also with respect to various accessories embraced in the contract. Representatives of the Post Office Department have testified that, to their personal knowledge, as a result of operating the machine, it fell far short of the specifications. The plaintiff on his part has denied this, but his testimony is not as con-vincing as that of the Government representatives. We are therefore disposed to accept the Government’s contention as correct. The machine was rejected and returned. Plaintiff has testified- that he believes it does meet the specifications except, possibly, with respect to some of the accessories. But the Government in a contract of this kind has a right to treat the machine and the accessories as a unit, and if the specifications are in fact not met with respect to any part of the contract, the Government has a right to reject the entire order. So, taking the figure of $1,-279.58, agreed as being due the plaintiff on other Post Office contracts, and deducting therefrom the stipulated value of this lathe, $810./7, there is left a balance of $468.81, to which we find the plaintiff is entitled.

Turning now to the other and the major item in controversy, namely, the drilling machine, the material facts surrounding this item are as follows: In response to Government invitation, the plaintiff and two other parties submitted bids for the furnishing of a motor-driven drilling machine to the War Department’s Pickatinny Arsenal, Dover, New Jersey, within one hundred and sixty days from date of the contract. The plaintiff’s bid being the lowest, namely, $2,953.65, the award was made to it. Formal contracts were forwarded for signature by the plaintiff, which were signed and returned. The amounts of the two other bids received were $10,112 (from the Henry Prentiss Company, Inc. of New York City), and $12,133 (from the Kings-bury Machine Tool Corporation, of Keene, New Hampshire).

The plaintiff, not being a manufacturer of this type of machinery, placed an order for the machine with the W. K. Millholland Machinery Company of Indianapolis, Indiana, and not being familiar with either the specifications or the value of such a machine, accepted, without question, the price quoted by the Millholland Company, and incorporated it in the bid filed with the Government. Two days after signing the contracts and forwarding them to the Government, but before the Government had executed them, the plaintiff was notified by the Millholland Company that it had made an error in quoting its price on the machine to the plaintiff, namely, that the manufacturer’s price should have been $20,-813 instead of $2,813, due entirely to an inadvertent typographical error in leaving out one naught, or cipher. Three days later the plaintiff relayed this information to the *570 Government, and asked to be relieved of the contract, the manufacturer having returned the order and requested cancellation. The Government replied that pending receipt of complete details respecting the alleged error, the contract was “suspended.” Thereupon, a good deal of correspondence, passed between the Government and the plaintiff. Additional information was obtained by plaintiff from the Millholland Company, at the request of the Government, and submitted to it with respect to the price quotation and surrounding circumstances. Disclosure by the Government was also made to plaintiff, at his request, of the great disparity between his bid and those of the other bidders. Nevertheless, the Government insisted upon the contract being carried out according to its literal terms, or being paid any damages resulting from the plaintiff’s failure to do so.

The matter dragged on until September, 1939, when the Government notified the plaintiff that unless it received word from him within five days that he was proceeding to fulfill the contract as written, the Government would place an order for the machine with the next lowest bidder and would charge him with the difference in cost. Plaintiff did not reply to this communication, giving at the trial as a reason for not doing so, the fact that he had put the matter squarely up to the Millholland Company for its decision, since its error was the cause of the controversy, and .that he had not yet had a definite reply from that company. Thereupon, the Government relet the contract, notified the plaintiff that his contract was canceled, and on January 13, 1941, he was notified by the Comptroller General’s Office that he was liable to the Government in the sum of $9,338.85, $9,208,89 of which represented excess of the price of the Kingsbury machine over the plaintiff’s bid as originally made, and the balance, $129.96, representing liquidated damages due to 'alleged .delay in securing delivery of a machine.

It appears from the testimony in the case that the machines under the two other bids which, as previously explained, were in the approximate amounts of $10,000 and $12,000, had respectively a production of approximately only 25 per cent and 50 per cent of the plaintiff’s machine. Furthermore, General, then Colonel, Shinkle, of the Ordnance Department, in command of Pickatinny Aráenal, admitted that he thought the result of holding the plaintiff to the contract would be unfair. Also, in the course of the controversy, he wrote to the Chief of Ordnance, War Department, that “the Millholland machine is worth a great deal more than the price at which it was offered.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Hamilton Enterprises, Inc.
711 F.2d 1038 (Federal Circuit, 1983)
Nelson v. United States
341 F. Supp. 1353 (D. Montana, 1972)
Board of Edn. of Chillicothe v. S-W Co.
240 N.E.2d 880 (Ohio Court of Appeals, 1968)
Chicora Construction Co. v. United States
252 F. Supp. 910 (E.D. North Carolina, 1965)
Wender Presses, Inc. v. The United States
343 F.2d 961 (Court of Claims, 1965)
Bethel Plumbing & Heating Co. v. General State Authority
32 Pa. D. & C.2d 533 (Dauphin County Court of Common Pleas, 1963)
Universal Transistor Products Corp. v. United States
214 F. Supp. 486 (E.D. New York, 1963)
McQuagge v. United States
197 F. Supp. 460 (W.D. Louisiana, 1961)
United States v. Sabin Metal Corporation
151 F. Supp. 683 (S.D. New York, 1957)
CN Monroe Manufacturing Company v. United States
143 F. Supp. 449 (E.D. Michigan, 1956)
Puget Sound Painters, Inc. v. State
278 P.2d 302 (Washington Supreme Court, 1954)
United States v. Metro Novelty Manufacturing Co.
125 F. Supp. 713 (S.D. New York, 1954)
M. F. Kemper Construction Co. v. City of Los Angeles
235 P.2d 7 (California Supreme Court, 1951)
Hyde Park Clothes, Inc. v. United States
84 F. Supp. 589 (Court of Claims, 1949)
Saligman v. United States
56 F. Supp. 505 (E.D. Pennsylvania, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
38 F. Supp. 568, 1941 U.S. Dist. LEXIS 3270, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kemp-v-united-states-mdd-1941.