Saligman v. United States

56 F. Supp. 505, 1944 U.S. Dist. LEXIS 2221
CourtDistrict Court, E.D. Pennsylvania
DecidedAugust 25, 1944
Docket3378
StatusPublished
Cited by11 cases

This text of 56 F. Supp. 505 (Saligman v. United States) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Saligman v. United States, 56 F. Supp. 505, 1944 U.S. Dist. LEXIS 2221 (E.D. Pa. 1944).

Opinion

KALODNER, District Judge.

The plaintiffs have brought this action against the United States of America under the Tucker Act, 36 Stat. 1093 (1911) as amended, 28 U.S.C.A. § 41(20). The sole question for determination is whether the plaintiffs are entitled to recover damages for their unilateral mistake in the preparation of a bid contract accepted by the United States and now fully performed.

The cause was heard without a jury and was submitted for consideration upon the pleadings, additional testimony and arguments of counsel. Accordingly, I make the following

Findings of Fact

1. On or about February 12, 1942, in response to an invitation sent out by the Philadelphia Quartermaster Depot to bid for the award of a contract for the manufacture of 55,900 head bands, plaintiffs submitted their bid to be awarded this, contract, in accordance with the specifications contained in the invitation, at a unit price of $.164 per head band, containing 50% foreign wool and 50% domestic wool..

2. On February 14, 1942, plaintiffs’ bid was accepted by the Quartermaster Depot,, which, on that date, issued Purchase Order No. 6773 awarding the contract to plaintiffs.

3. The next highest bids were $.222 and $.2487 per unit, both for all domestic wool.

4. About two weeks after the acceptance of their contract and before they had begun work thereunder, plaintiffs discovered that in computing the cost for the manufacture of the head bands prior to the submission of their bid they had omitted the cost of the wool to be used, which amounted to approximately $.125 per head band, and immediately notified, by telephone, the Quartermaster Depot of this error.

5. Plaintiffs’ aforesaid telephone call was transferred to the Legal Department of the Quartermaster Depot and they were advised that they could either refuse to perform and be held accountable in damages, or complete the contract and make claim for adjustment.

6. On February 28, 1942, plaintiffs wrote to the Quartermaster Depot explaining the error made and setting forth the alternatives which the Legal Department of the Quartermaster Depot had advised were open to them, and stating that they intended to perform the contract and file claim for relief.

7. Under date of March 4,' 1942, the Quartermaster Depot replied that the claim should be addressed to the Comptroller General. Plaintiffs acted accordingly. Their claim was rejected by the Comptroller General.

8. Plaintiffs have completed the contract and in fact manufactured 62,340 head bands.

9. The mistake of plaintiffs was unilateral.

*507 10. The defendant had no notice prior to its acceptance of plaintiffs’ bid that there was any error in the bid submitted.

11. Plaintiffs’ bid was “in line” with the higher bids and defendant was not and should not have been put on notice that plaintiffs had made a mistake in the submission of their bid.

12. No promise was made to the plaintiffs that they would be afforded relief.

13. No person authorized to bind defendant promised plaintiffs any relief.

Discussion

There is no dispute as to the law applicable in this controversy. Ordinarily no relief will be granted to a party to an executory contract in the case of a unilateral mistake. In such case when a bid has been accepted the bidder who has made a mistake will be bound and must bear the consequences thereof. Ellicott Machine Co. v. United States, 44 Ct.Cl. 127; American Water Softener Co. v. United States, 50 Ct.Cl. 209; United States v. Conti, 1 Cir., 119 F.2d 652; Steinmeyer et al. v. Schroeppel, 226 Ill. 9, 80 N.E. 564, 10 L.R.A..N.S., 114, 117 Am.St.Rep. 224; Leonard v. Howard et al., 67 Or. 203, 135 P. 549; Star-Chronicle Pub. Co. v. New York Evening Post, Inc., et al., 2 Cir., 256 F. 435, 442; and Moffett, Hodgkins & Clarke Co. v. City of Rochester, 2 Cir., 91 F. 28.

However, if the party receiving the offer or the bid, knows or has reason to know because of the amount of the bid, or otherwise, that the bidder made a mistake, the contract is voidable by the bidder. 5 Williston, Contracts, Sec. 1598; 2 Restatement, Contracts, Sec. 503; Alta Electric & Mechanical Co. v. United States, 90 Ct.Cl. 466; Kemp v. United States, D.C.D.Md., 1941, 38 F.Supp. 568; Slate of Connecticut v. F. H. McGraw & Co., D.C.D.Conn., 1941, 41 F.Supp. 369. The Kemp case is an excellent illustration of the application of this principle. In that case the government solicited bids on a motor-driven drilling machine. Plaintiffs’ bid was the lowest, namely, $2,953.65, and the contract was awarded to him. The other bids were for $10,112 and $12,133. After entering into the formal contract, plaintiff discovered that he had made a gross error. The government refused to permit him to avoid the contract and subsequently deducted the additional cost incurred from the payment due plaintiff on other contracts. The court held that the plaintiff was entitled to recover, for not only was the difference in the bids sufficient to put one on notice that something was wrong, but the Army officer in charge also admitted that he was struck by the great discrepancy and that the government was obviously getting something for nothing.

Can we say the same situation holds in the case at bar? Here the plaintiffs’ bid was $.164 per unit containing 50% domestic wool. The next higher bid was $.222 for 100% domestic wool. Lieut. Col. William A. Peterson, the contracting officer for the Quartermaster Depot, who passed upon the bids in question and signed the purchase order to plaintiffs, testified (by deposition) that by comparing all bids submitted the bid of plaintiffs was “in line.” All domestic wool is more expensive than 50% domestic, although the witness Saligman testified that the difference is only one-eighth of a cent per head band, Lieut. Col. Peterson’s testimony was that the fact that plaintiffs’ bid was not for all domestic wool was among the considerations for rejection of plaintiffs’ claim by the Comptroller, and “ * * * the difference in price (of the bids) was not such as to make it appear that an error had been made in the bid because the bid was reasonable.”

Considering all the circumstances, I am of the opinion the government had no reason to suspect that plaintiff had made a mistake. It is true that plaintiffs’ testimony that the difference between 50% domestic and 50% foreign wool and all domestic wool is only one-eighth of a cent per unit is uncontradicted; that Lieut. Col. Peterson testified that he was acquainted with the prices of wool at the time of the consideration of the bids (although he did not have the information at the time of the depositions) ; and that the government has its experts on valuation and costs; yet I must agree with the defendant that the government is not obligated to act as “nursemaid” for bidders when the price is “in line.” Plaintiffs rest the heaviest weight of their argument on the fact that the error should have been apparent because the contracting officer had a staff of experts to aid him.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lulus Ostrich Ranch
Armed Services Board of Contract Appeals, 2019
Tony Downs Foods Co. v. United States
530 F.2d 367 (Court of Claims, 1976)
James v. Centex Construction Co.
255 F. Supp. 508 (E.D. Arkansas, 1966)
Wender Presses, Inc. v. The United States
343 F.2d 961 (Court of Claims, 1965)
Bethel Plumbing & Heating Co. v. General State Authority
32 Pa. D. & C.2d 533 (Dauphin County Court of Common Pleas, 1963)
United States v. Sabin Metal Corporation
151 F. Supp. 683 (S.D. New York, 1957)
CN Monroe Manufacturing Company v. United States
143 F. Supp. 449 (E.D. Michigan, 1956)
Johnson v. Federal Housing Administration
261 P.2d 161 (Supreme Court of Colorado, 1953)
Graham v. Clyde
61 So. 2d 656 (Supreme Court of Florida, 1952)
School District of Scottsbluff v. Olson Const. Co.
45 N.W.2d 164 (Nebraska Supreme Court, 1950)
Hyde Park Clothes, Inc. v. United States
84 F. Supp. 589 (Court of Claims, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
56 F. Supp. 505, 1944 U.S. Dist. LEXIS 2221, Counsel Stack Legal Research, https://law.counselstack.com/opinion/saligman-v-united-states-paed-1944.