James v. Centex Construction Co.

255 F. Supp. 508, 1966 U.S. Dist. LEXIS 8002
CourtDistrict Court, E.D. Arkansas
DecidedJune 24, 1966
DocketNo. LR-64-C-165
StatusPublished
Cited by3 cases

This text of 255 F. Supp. 508 (James v. Centex Construction Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James v. Centex Construction Co., 255 F. Supp. 508, 1966 U.S. Dist. LEXIS 8002 (E.D. Ark. 1966).

Opinion

MEMORANDUM OPINION

HENLEY, Chief Judge.

This is a suit in equity for rescission of a contract for the construction of certain sanitary and storm sewers in a residential subdivision in the City of New Orleans, Louisiana. The defendant denies that plaintiff is entitled to rescission and has filed a counterclaim against plaintiff and the surety on his performance bond seeking damages for alleged breach of contract by plaintiff.

Plaintiff, Worth James, is an individual citizen of Arkansas who does business under the name of Worth James Construction Co. Defendant, Centex Construction Co. (now Centex Corporation), is a corporation domiciled in the State of Texas and with its principal place of business in that State. The amount in controversy is in excess of $10,000, exclusive of interest and costs.

The case has been tried to the Court, and this memorandum incorporates the Court’s findings of fact and conclusions of law. Up to a point the facts are not disputed.

Plaintiff is an experienced public contractor who for a number of years has specialized in the installation of underground utilities such as storm sewers, sanitary sewers, water lines, and the like. In August 1963 plaintiff was invited to submit a bid on a subcontract for the installation of storm sewers and sanitary sewers, with appurtenances, in Section 4 of the New Orleans subdivision known as “Village de l’Est.” The subdivision was owned by a development company known as “New Orleans East,” and the prime contract for the construction of the subdivision, including streets and water and sewer systems, was held by Centex Construction Co., defendant herein.1

The subcontract with which the Court is concerned was to be performed in accordance with plans and specifications prepared by the engineering firm of Adloe Orr, Jr. and Associates of New Orleans, and in accordance with the specifications and requirements of Sewerage and Water Board of the City of New Orleans, hereinafter the Board.

Centex supplied plaintiff with the drawings prepared by the Orr concern, and plaintiff obtained a set of specifications from the Board. Plaintiff also made a one day’s trip to New Orleans in the course of which he examined the job site to some extent and also observed certain storm and sanitary sewer work being done by another contractor in another section of the subdivision immediately adjacent to Section 4 thereof.

On the basis of the documents in his possession, considered in connection with what he had learned on his trip to New Orleans, plaintiff submitted to Centex a low bid which, after adjustments, resulted in the contract being awarded to plaintiff at a basic price of $431,861.81.

. Four other contractors, three of them from New Orleans, submitted bids much in excess of that of plaintiff. Those bids were as follows:

Navajo Constructors, Houston, Texas $773,432.75

Walter Villere Co. and Drennen Construction Co. (Villere-Drennen), New Orleans, Louisiana 569,439.30

Pratt Farnsworth, Inc. (Farnsworth), New Orleans Louisiana 547,654.00

Boh Brothers Construction Co. (Boh Bros.) New Orleans, Louisiana 532,334.50

[510]*510In October 1963 plaintiff moved men, equipment, and material to the job site preparatory to commencing performance of the work, and some work was in fact performed. At this stage of the transaction plaintiff learned for the first time that the Board’s specifications for sewer manholes and for the laying of pipe at certain depths were somewhat more rigorous than the ones set forth in the set of specifications which a representative of the Board had furnished plaintiff when he was in New Orleans prior to submitting his bid.

While plaintiff was not pleased to learn about the more rigorous specifications prescribed by the Board, he probably would have gone ahead with the work except for the fact that in early November he discovered that he would have to excavate on the average more than two feet deeper than he had expected and that he would not be paid for the extra excavation. When plaintiff learned of that fact, he refused to continue and filed this suit for rescission.

When Centex learned that plaintiff was not going to perform, new bids were solicited and the work was re-let to Farnsworth at a price of $99,372.19 in excess of plaintiff’s basic contract price. It is that excess plus certain expenses which Centex by its counterclaim is seeking to recover from plaintiff and from plaintiff’s surety.

Ignoring certain allegations of plaintiff's pleadings which were not relied upon ultimately, it is the theory of the plaintiff that he was induced by Centex to submit a grossly inadequate bid; that the contract into which he entered but did not perform was the result of a non-negligent mistake on his part, induced by Centex, and that he is entitled to rescission.

The position of Centex is that the contract was not the result of any mistake, negligent or otherwise, on the part of plaintiff, and that plaintiff simply refused to perform his obligations when he found that it would not be profitable for him to do so. Alternatively, Centex says that if plaintiff made any mistake when he submitted his bid, the mistake was negligent, and that in any event the mistake, whether negligent or non-negligent, was not induced or brought about by any words or conduct on the part of Centex.

Assuming that plaintiff is not entitled to rescission, it seems clear that he and his bonding company are liable to Centex for breach of contract, and there is no substantial dispute between the parties as to the amount which Centex is entitled to recover, if it is entitled to recover anything.

At the outset the record suggested the presence of an issue as to whether the rights of the parties are governed by Arkansas law or by the law of Louisiana. There does not seem to be any material difference between the relevant law of the two States, and the Court sees no occasion to deal with the conflicts issue.

Counsel on both sides are familiar and do not seem to quarrel with this Court’s views as to the contract rescission on account of unilateral mistake expressed in Standard Accident Insurance Co. v. Wilmans, E.D.Ark., 214 F.Supp. 53, 61-62. It was there said:

“It is settled that a court of equity will in certain circumstances grant rescission of a contract entered into as a result of a unilateral mistake of one of the parties, where that mistake has been produced by the conduct of the other party and where the parties can be put in status quo.

“The general rule is stated as follows in an Annotation appearing in 59 A.L.R. 809:

“Equitable relief from a mutual mistake is frequently given by a reformation of the contract. But a contract will not be reformed for a unilateral mistake. Equitable relief may, however, be given from a unilateral mistake by a rescission of the contract. Essential conditions to such relief are: (1) The mistake must be of so grave a consequence that to enforce the contract as actually made would be un[511]*511conscionable. (2) The matter as to which the mistake was made must relate to a material feature of the contract. (3) Generally the mistake must have occurred notwithstanding the exercise of ordinary diligence by the party making the mistake. (4) It must be possible to give relief by way of rescission without serious prejudice to the other party except the loss of his bargain.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
255 F. Supp. 508, 1966 U.S. Dist. LEXIS 8002, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-v-centex-construction-co-ared-1966.