E&I Global Energy Services, Inc. v. United States

CourtUnited States Court of Federal Claims
DecidedJanuary 10, 2022
Docket19-244
StatusPublished

This text of E&I Global Energy Services, Inc. v. United States (E&I Global Energy Services, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E&I Global Energy Services, Inc. v. United States, (uscfc 2022).

Opinion

In the United States Court of Federal Claims No. 19-244C Filed: January 10, 2022

E&I GLOBAL ENERGY SERVICES, INC.,

Plaintiff,

v.

THE UNITED STATES,

Defendant.

Joseph Whitcomb, Whitcomb, Selinsky, P.C., Denver, CO, for Plaintiff.

Christopher L. Harlow, Trial Attorney, Patricia M. McCarthy, Assistant Director, Commercial Litigation Branch, Civil Division, U.S. Department of Justice, Washington, D.C., with whom were Thomas Cardova, and Trevor Upderaff, Western Area Power Association, Denver, CO, Of Counsel, for Defendant.

POST-TRIAL OPINION AND ORDER

TAPP, Judge.

This contract dispute stems from construction of a high voltage substation in South Dakota. Plaintiff, E&I Global Energy Services, Inc. (“E&I”), seeks damages for breach of contract. (Compl. at ¶ 36, ECF No. 1). Many issues in this case were resolved on dispositive motions. E & I Glob. Energy Servs., Inc. v. United States, 144 Fed. Cl. 508 (2019) (Bruggink, J., granting the United States’ Motion to Dismiss Counts 1–3 for failure to state a claim); E&I Glob. Energy Servs., Inc. v. United States, 153 Fed. Cl. 459 (2021) (granting in part and denying in part the United States’ Motion for Summary Judgment and granting the United States’ Motion for Judgment on the Pleadings). Those decisions detail much of the factual and procedural history of this case.

The remaining issues at trial were simple: whether the United States breached its contract with E&I by (1) denying E&I’s request for payment on nine contract line item numbers (“CLINs”) contained in Table 17 of E&I’s certified claim; and (2) denying payment for Invoice No. 1422. The Court tried these issues in Sioux Falls, South Dakota on October 25, 2021. After considering the evidence presented, the Court concludes that the United States is entitled to judgment on both issues. I. Background and Procedural History

In March 2017, E&I entered a Completion Agreement with its sureties, Liberty Mutual Insurance Company and The Insurance Company of the State of Pennsylvania, whereby E&I agreed to complete construction of the VT Hanlon Substation at a firm-fixed price of $5,428,625.69. (Joint Stipulations of Fact (“JSOF”) ¶ 1, ECF No. 85).

Project Specifications, Amendment 002; Solicitation No. DE-SOL-0007930 (Publicly Available)

After entering the completion agreement, E&I’s sureties tendered E&I to the Western Area Power Administration (“WAPA”) as the new prime contractor for construction of the substation. (JSOF ¶ 2). In April 2017, E&I signed a Follow-On Contract with WAPA. (JSOF ¶ 3). Thirteen months later, on May 18, 2018, WAPA terminated E&I for default. (JSOF ¶ 7). Several months later, on October 1, 2018, E&I submitted a Contracts Dispute Act (“CDA”) claim seeking $3,336,932.79. (JSOF ¶ 8). The Contracting Officer denied E&I’s claim on December 17, 2018. (JSOF ¶ 9). This litigation ensued.

After previous disposition of many of E&I’s claims, two categories of claims remain. First, E&I’s Complaint, Paragraph 36(1) references a table that seeks payment for CLINs. 2, 30, 31, 32, 40, 41, 46, 47, and 48. (Compl. ¶ 36; Compl. Ex. 17). Through these CLINs, E&I seeks approximately $284,000 in breach of contract damages. (E&I Pre-trial Memo at 1, ECF No. 75). Second, E&I seeks reimbursement on Invoice No. 1422 for adding “pull wires” at a cost of $32,113.37. (Id.). As the Court explained in its decision partially granting summary judgment to the United States, the first claim turns on whether E&I actually performed the work that would

2 entitle it to payment under the nine CLINs, and the second claim turns on whether adding the pull wires was part of either the original fixed price contract or a change order.

E&I presented evidence on each of those issue during the single-day trial. After the close of E&I’s case, the United States moved for partial judgment under RCFC 52(c) with respect to the nine CLINs. The Court took that motion under advisement and permitted the United States to present its case regarding Invoice No. 1422. The parties have each filed post-trial briefs and this case is now ripe for decision. (E&I Trial Brief, ECF No. 97; USA Trial Brief, ECF No. 96).

II. Findings of Fact

During trial, the Court heard testimony from only two witnesses. Jeffrey Bruce, an electrician by trade, was the president of E&I who signed and certified E&I’s CDA claim. 1 (Bruce, TR at 29:17–164:4, 107:5–17). He has 34 years of experience, but the substation project was his first as a prime contractor for the Federal Government. (Id. at 30:3–32:25).

Jonathan Dittmer is the procurement manager and Contracting Officer for the Upper Great Plains Region of WAPA. (Dittmer, TR at 165:20–256:3). He has been a contracting officer since 1992 and oversaw numerous substation projects. (Id. at 166:13–167:5). WAPA assigned Mr. Dittmer as the Contracting Officer to the substation project. (Id. at 167:9–12). As the Contracting Officer, Mr. Dittmer first awarded the contract to Isolux Corsan, LLC (“Isolux”) in 2015. (Id. at 167:13–15). After Isolux defaulted in 2016, Mr. Dittmer executed the Tender Agreement on behalf of WAPA to accept E&I as the new prime contractor. (Id. at 172:23– 173:2).

A. CLINs. 2, 30, 31, 32, 40, 41, 46, 47, and 48

E&I submitted its certified claim seeking approximately $3.3 million. (JSOF ¶ 8). Within that claim, E&I submitted a table of CLINs with five columns, denoting the CLIN, the work or material at issue, bid price, the amount E&I invoiced, and the amount WAPA paid. (DX01 (E&I’s certified claim); see also Compl. Ex. 17, ECF No. 1-17). E&I claimed that WAPA failed to pay $284,110.88 for work E&I invoiced as described in the table. (DX01.003; see also Compl. ¶ 36(1)).

For CLINs 2, 30, 31, 32, 40, 41, 46, 47, and 48 E&I invoiced $0.00 each. (DX01.009– .010; Bruce, TR at 111:7–113:9, 121:4–14). For the other 39 CLINs, E&I conceded that it had invoiced and been paid the full amount. (Bruce, TR at 124:6–11).

In the “Totals” row at the bottom, E&I stated it was paid $5,059,114.81, leaving an unpaid balance of $284,110.88. (DX01.011). However, in reviewing the table from the certified claim and recalculating on the witness stand, Mr. Bruce was unable to determine how he arrived at the $284,110.88 figure. (Bruce, TR at 116:24–120:24). Mr. Bruce speculated that the “paid amount” figures were wrong. (Id. at 120:11–12). Though Mr. Bruce testified that he completed

1 A transcript of the trial is docketed at ECF No 94. The Court will reference the witness’s name in trial citations to reflect their time on the stand, but quotations may reflect questions or statements of counsel where appropriate.

3 the work with respect to the nine CLINs, E&I offered no documents to support those bald assertions, but more importantly, those assertions are contradicted by E&I’s contemporaneous documentation. (See, e.g., Bruce, TR at 78:5–18 (CLIN 40), 84:13–85:5 (CLIN 2), 90:5–92:25 (CLIN 30), 93:8–25 (CLIN 31), 94:15–95:16 (CLIN 32), 95:19–97:15 (CLIN 41), 97:23–99:8 (CLIN 46), 99:9–100:16 (CLIN 47)).

E&I submitted its last invoice to WAPA on May 15, 2018. (Bruce, TR at 122:21–123:9). That invoice, Pay Application No. 13, contained a table of CLINs 1–48 with several columns, including two showing “payment this period” and “balance to finish.” (DX03.057). “Balance to finish” represented the work remaining to complete performance under the listed CLIN. (Bruce, TR at 124:22–125:4). “Payment this period” represented the amount E&I billed for the listed CLIN. (Id. at 124:18–21). This invoice listed $0.00 in the “payment this period” column for CLINs 2, 31, 41, 47, and 48. (DX03.057). The invoice also listed a positive “balance to finish” for CLINs 2, 31, 40, 41, 46, 47, and 48, indicating work had yet to be completed for those items. (DX03.057).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

James H. Clack v. The United States
395 F.2d 773 (Court of Claims, 1968)
Liebherr Crane Corporation v. The United States
810 F.2d 1153 (Federal Circuit, 1987)
Edge Systems LLC v. Aguila
635 F. App'x 897 (Federal Circuit, 2015)
Johnson v. Office of Personnel Management
664 F. App'x 919 (Federal Circuit, 2016)
Persyn v. United States
34 Fed. Cl. 187 (Federal Claims, 1995)
Howard Industries, Inc. v. United States
115 F. Supp. 481 (Court of Claims, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
E&I Global Energy Services, Inc. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ei-global-energy-services-inc-v-united-states-uscfc-2022.