J.C. Equipment Corporation v. Gordon R. England, Secretary of the Navy

360 F.3d 1311, 2004 U.S. App. LEXIS 4290, 2004 WL 406399
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 5, 2004
Docket02-1472
StatusPublished
Cited by16 cases

This text of 360 F.3d 1311 (J.C. Equipment Corporation v. Gordon R. England, Secretary of the Navy) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.C. Equipment Corporation v. Gordon R. England, Secretary of the Navy, 360 F.3d 1311, 2004 U.S. App. LEXIS 4290, 2004 WL 406399 (Fed. Cir. 2004).

Opinion

FRIEDMAN, Senior Circuit Judge.

In this government contract case, the Armed Services Board of Contract Appeals (Board) rendered two lengthy opinions: one on the contractor’s entitlement to recover on the many claims for additional compensation it had submitted to the contracting officer, and the second on the amount of recovery on those claims on which it prevailed (the “quantum” decision). J.C. Equip. Corp., 97-2 B.C.A, (CCH) ¶ 29,197, 1997 WL 545496 (A.S.B.C.A.1997) (J.C.Equip.Corp.I); J.C. Equip. Corp., 2002-1 B.C.A. (CCH) ¶ 31,-810, 2002 WL 415627 (A.S.B.C.A.2002) (J.C.Equip.Corp.II). The contractor challenges both of these decisions on numerous grounds. We affirm both of them.

I

The basic facts, as found by the Board in its first (entitlement) decision, are not disputed. They may be summarized as follows:

In August 1984, the appellant J.C. Equipment (“J.C.”) entered into a fixed-price contract to repair the fresh water system and tank at a Navy base in Calif or- *1313 nia for $623,078. J.C. Equip. Corp. I, 97-2 B.C.A. (CCH) ¶ 29,197 at 145,257 (Finding of Fact (“FF”) 1). The contract also required J.C. to “maintain ... two sets of contract drawings showing any deviations, including buried or concealed construction and utility features revealed during construction, and upon completion of the work to deliver the marked-up sets of drawings to” the contracting officer. Id. at 145,274 (FF 116). Work was to begin on August 30, 1984 and be completed by May 27, 1985. Id. at 145,257 (FF 1).

Because of what J.C. described as a “large number of unknown obstructions and pipelines being encountered,” work did not proceed smoothly. Id. at 145,259 (FF 14). The parties negotiated and executed “[f]orty-two (42) change order modifications” during the performance of the contract, most of which provided for additional payments to J.C. Id. at 145,283 (FF 175). As the contract provided, each of these “bilaterally executed modifications ... release^] the Government from further payment to J.C.” for the matters covered. Id. at 145,284.

By early 1986, relations between the parties had deteriorated. In an April letter, the Navy directed J.C. to show cause why the contract should not be terminated because of its “failure to diligently prosecute the work.” Id. at 145,260 (FF 24). The letter stated that although several unexpected problems were encountered, J.C. “had been fully compensated for each changed condition and the amount of change order work would not be considered an adequate defense for failing to diligently prosecute the work.” Id.

Although it is unclear what followed, it is undisputed that in a May 8, 1986 letter, the Navy ordered J.C. to stop work, and on May 15, 1986, “base security removed JC from the base” and work ceased. Id. (FF 25). Subsequently, the “Government acknowledged” that the revised contract completion date was May 9, 1986. Id. (FF 27).

J.C. then filed with the contracting officer a formal claim for an equitable adjustment of slightly more than two million dollars, id. at 145,261 (FF 32), which later was reduced to $1,251,040, id. at 145,288 n. 1. The contracting officer rejected most of these claims but awarded J.C. $17,820. Id. at 145,261 (FF 34).

In its appeal to the Board, J.C. sought recovery on forty-four separate claims. After a hearing that produced a “voluminous” record “consisting of approximately 10 to 15 thousand pages and 1,000 pages of transcript,” id. at 145,288 n. 3, the Board allowed nineteen claims in whole or in part and rejected the remaining twenty-five claims. The claims on which J.C. prevailed were “remanded for negotiation and settlement.” Id. at passim.

When the parties were unable to settle those claims, J.C. filed a quantum complaint with the Board seeking an equitable adjustment of $289,969.08. J.C. Equip. Corp. II, 2002-1 B.C.A. (CCH) ¶ 31,810 at 157,153. It also contended that “the issuance of the stop work order and termination of the contract was erroneous and must be converted into a termination for the convenience of the Government.” Id.

After a further evidentiary hearing, the Board awarded J.C. $10,563.41 but did not extend its time for performance. Id. at 157,203. The Board also held that it lacked jurisdiction to consider J.C.’s request to change the character of the contract termination because J.C. had not raised that issue before the contracting officer. Id. at 157,157-58.

II

The government contends that to the extent J.C.’s appeal challenges the *1314 Board’s denial of twenty-five of its claims in the entitlement decision, it is untimely, and we therefore have no jurisdiction to consider it. Relying upon our precedent, the government argues that the entitlement decision was a “final” one that J.C. could have appealed and that its failure to do so within the 120-day period for appeal under the Contract Disputes Act of 1978, 41 U.S.C. § 607(g)(1)(A) (2000), precludes it from challenging that decision in its appeal from the Board’s quantum decision.

The government’s conclusion, however, does not follow from its premise. The fact that the Board’s earlier entitlement decision may have had sufficient finality to make it immediately appealable does not mean that the contractor’s failure to take such appeal precludes it from challenging that ruling in its appeal from the Board’s second decision, which was the Board’s “final” action in the case.

Our recent decision in Brownlee v. Dyn-Corp, 349 F.3d 1343 (Fed.Cir.2003), is dis-positive of this issue and requires rejection of the government’s contention. In that case the Board held for a contractor and remanded for the parties to attempt to settle the amount of recovery — the same procedure it followed in the present case. Id. at 1346. On remand, the government stipulated to the amount it owed, and the Board entered a final judgment for that amount. Id. at 1346-47. The government then appealed from that judgment, challenging only the Board’s earlier entitlement ruling in favor of the contractor. Id. at 1347.

This court rejected Dyncorp’s contention that the government’s challenge to the Board’s entitlement ruling was untimely because it was not filed within 120 days of its rendition. The court pointed out that although prior decisions had permitted the parties to appeal from entitlement decisions under similar circumstances, see, e.g., Dewey Electronics Corp. v. United States, 803 F.2d 650, 653-58 (Fed.Cir.1986), no cases “h[e]ld [ ]or suggested] that appeals [wejre required

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A4 Construction Company, Inc
Armed Services Board of Contract Appeals, 2025
Jones v. MSPB
98 F.4th 1376 (Federal Circuit, 2024)
The Boeing Company v. Secretary of the Air Force
983 F.3d 1321 (Federal Circuit, 2020)
CCI, Inc. v. McHugh
608 F. App'x 937 (Federal Circuit, 2015)
Buckner v. United States Postal Service
554 F. App'x 906 (Federal Circuit, 2013)
Fiori v. United State Postal Service
292 F. App'x 22 (Federal Circuit, 2008)
Babauta v. Dept. Of Defense
Federal Circuit, 2008
Babauta v. Department of Defense
270 F. App'x 996 (Eleventh Circuit, 2008)
First Annapolis Bancorp, Inc. v. United States
75 Fed. Cl. 280 (Federal Claims, 2007)
C.D. Hayes, Inc. v. United States
74 Fed. Cl. 699 (Federal Claims, 2006)
Armour of America v. United States
69 Fed. Cl. 587 (Federal Claims, 2006)
Roxco, Ltd. v. United States
60 Fed. Cl. 39 (Federal Claims, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
360 F.3d 1311, 2004 U.S. App. LEXIS 4290, 2004 WL 406399, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jc-equipment-corporation-v-gordon-r-england-secretary-of-the-navy-cafc-2004.