CCI, Inc. v. McHugh

608 F. App'x 937
CourtCourt of Appeals for the Federal Circuit
DecidedApril 10, 2015
Docket2014-1470
StatusUnpublished
Cited by2 cases

This text of 608 F. App'x 937 (CCI, Inc. v. McHugh) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CCI, Inc. v. McHugh, 608 F. App'x 937 (Fed. Cir. 2015).

Opinion

HUGHES, Circuit Judge.

CCI appeals the Armed Services Board of Contract Appeals’ denial of its Type I claim for equitable relief under Differing Site Condition Clause FAR 52.236-2. The Board concluded that CCI had not proven any of the four elements necessary to establish a Type I equitable adjustment claim. Accordingly, to prevail on appeal, CCI must show the Board erred. on all four elements. Because substantial evidence supports the Board’s decision on at least two of these elements — whether the site conditions were reasonably foreseeable *938 to CCI and whether CCI relied on the alleged site representations — we find that CCI has not met this burden. Accordingly, we affirm.

I

On April 25, 2008, the Army issued a Request for Proposals (RFP) to plan, design, and construct an L-shaped pier and perform related work at Umm Qasr, the only deep-water seaport in Iraq. The Army found that Umm Qasr was “a critical link towards the import of life-providing assistance being provided to the people of Iraq.” J.A. 4859.

Attached to the RFP was a 2007 engineering report from Andrea Engineering Tests Laboratory (the Andrea Report). The Andrea Report describes a field investigation of an area including the Umm Qasr project site, and included results obtained from disturbed samples 1 , undisturbed samples 2 , and a Standard Penetration Test 3 performed on three boreholes.

In the “Discussion of Results” section, the Andrea Report includes several descriptions of the soil, such as:

• “The site subsoil consists mainly from two layers, the first layer of very soft, soft to medium gray sandy silty clay with amount of soluble salts and organic matter overlaying on a layer of medium, dense to very dense gray silty sand.” J.A. 4809.
• “[T]he site was within the ebb and tide zone of the sea. The saturated soil condition below the water table makes the problem of settlement significant. ...” Id.
• “The low bearing capacity of the soft clayey layer; could lead to excessive settlement to go out of control.” J.A. 4810.
• “[The] samplers that extruded from shelby tubes of the soft clayey layer ... exudes between the fingers when squeezed in the fist so this could described as very soft to soft sandy clayey soil.” Id.
• “Investigation of the site area has produced evidence of some kind of collapse due to the reaction between fundamental compounds of the soil (sandy clayey layer) with organic matter, this collapse is impact the settlement of shallow foundation about (2-5)%.” J.A. 4810-11.

Appendix B of the Andrea Report includes soil descriptors and the blow count data obtained from the Standard Penetration Test. The parties agree that Appendix B of the Andrea Report contains inconsistent information, because the soil descriptors indicate the soil is very soft to soft, but the blow count data indicates the soil is harder.

Another attachment to the RFP is a U.S. Agency for International Development report entitled “Umm Qasr Port Assessment” (the USAID Report). The *939 USAID Report was prepared as a “general assessment of functions at the port and historical dredging operations at the port.” J.A. 18854. It describes the history of dredging at the site, the need for continuous dredging at the site, and the locations of the dredged material disposal sites. The report also includes the following site condition description:

The streams are alluvial and the channels are apparently composed primarily of sand and silt. Clay may be present, but no clay balls were seen in the dredged material disposal areas. There is a thin film of sun-cracked silt or clay at some of the final settlement ponding areas. Boring information shows the materials encountered in the original “new” port excavation as silty sand with small fine gravel and clay. Infill sediments since then may be of a finer, more silty nature.

J.A. 4863.

After the RFP issued, CCI agreed to join two other companies, PolyEarth Construction, International LLC (PCI) and PND Engineers, Inc. (PND), in preparing a bid proposal for the Umm Qasr project. PND and PCI were responsible for the engineering and logistical aspects of the proposal, and CCI was responsible for the financial aspects of the proposal.

During the Umm Qasr bidding period, a number of questions were submitted to, and subsequently answered by, the Army. Two are relevant to this appeal:

Question 11: Soil investigation not enough we need more point of locations.
Answer 11: The best soil investigation data available to the government is provided in Appendix-C Geotechnical Investigation of the SOW. The contractor should assume the data provided in Appendix C is representative of the project site.
Question 42: Geotechnical Conditions: Will the government be providing any bidding assumptions associated with the existing geotechnical conditions? For bidding purposes, should the contractor assume the three borings provided are representative of the entire site?
Answer 42: The contractor should assume the three borings provided are representative of the entire site for the purposes of developing a proposal. However, additional geotechnical information may be required during the design phase of this project.

J.A. 4833; J.A. 4838/

In May 2008, CCI submitted an initial proposal for the Umm Qasr project. In August 2008, CCI submitted a revised proposal. On September 10, 2008, the Army awarded CCI the contract for the Umm Qasr project. The contract incorporated Differing Site Conditions Clause FAR 52.236-2 and Site Investigations Affecting the Work Clause FAR 52.236-3.

In 2009, CCI began construction on the Umm Qasr project. CCI initially used land-based construction methods and encountered difficulties building a crane pad due to the soil conditions at the project site. It ultimately switched to marine-based construction to complete the project.

In August 2009, CCI submitted a Type I request for equitable adjustment- to the Army, alleging that it incurred additional costs as a result of soil conditions that were different than represented in the Andrea Report. The Army denied CCI’s claim, and CCI appealed to the Board. The Board also denied CCI’s claim. CCI appeals. We have jurisdiction under 28 U.S.C. § 1295(a)(10).

II

To receive an equitable adjustment for a Type I differing site condition, a contrac *940

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Asi Constructors, Inc. v. United States
129 Fed. Cl. 707 (Federal Claims, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
608 F. App'x 937, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cci-inc-v-mchugh-cafc-2015.