Niko Contracting Co. v. United States

42 Cont. Cas. Fed. 77,244, 39 Fed. Cl. 795, 1997 U.S. Claims LEXIS 299, 1997 WL 804610
CourtUnited States Court of Federal Claims
DecidedDecember 23, 1997
DocketNo. 95-424C
StatusPublished
Cited by2 cases

This text of 42 Cont. Cas. Fed. 77,244 (Niko Contracting Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Niko Contracting Co. v. United States, 42 Cont. Cas. Fed. 77,244, 39 Fed. Cl. 795, 1997 U.S. Claims LEXIS 299, 1997 WL 804610 (uscfc 1997).

Opinion

OPINION

BRUGGINK, Judge.

This action, brought under the Contract Disputes Act, 41 U.S.C. §§ 601-13 (1994), arises out of a contract between the plaintiff and the Smithsonian Institution, whereby plaintiff was to replace the roof of the Cooper-Hewitt Museum in New York City. Plaintiff Niko Contracting Company (Niko) claims that, although the work is complete, Niko has not been fully compensated for all “change” work and for Government-caused delays. On May 7, 1997, the court denied defendant’s motion for summary judgment without prejudice. The matter is presently before the court on the Government’s renewed motion for summary judgment on all counts of the complaint. Further argument is deemed unnecessary. For the reasons expressed below, the Government’s motion for summary judgment is granted.

[797]*797BACKGROUND

On September 25, 1990, the Smithsonian Institution’s Office of Procurement & Property Management (Smithsonian) awarded Contract No. FC-0070020000 to the plaintiff. Under the terms of the contract, Niko was to “furnish all supervision, labor, materials, and equipment needed for the Roof Replacement of the Cooper-Hewitt Museum, located at # 2 East 91st Street, New York, New York.” (Def.’s Renewed Mot. for Summ. J., app., at 1 [hereinafter Appendix].) The award to Niko, a firm-fixed-price contract in the amount of $1,586,696.00, was to “commenee[] within 7 calendar days after receipt of the Notice to Proceed and ... [be] completed in every respect within 600 calendar days therefore.” (Appendix at 8.) The contract was signed for Niko by its president, Nicholas Lardas, and for the Smithsonian by the Contracting Officer (CO), Robert Perkins.

The Government concedes that, during the performance of the contract, the contractor encountered problems with the existing roof of the museum, resulting in work that was beyond the original contract. On such occasions, Niko would forward a proposal for a change request to the Contracting Officer’s Technical Representative (COTR), who would then evaluate the proposal and negotiate with the contractor to add the additional work to the contract via a contract modification. Assuming the contractor and the COTR reached an acceptable agreement, a contract modification would be drafted for Niko’s signature. Once Niko accepted the terms of the modification and signed the agreement, it was forwarded to the CO for final approval and signature. Niko claims that it sent over fifty such proposal letters to the Smithsonian. The Government asserts that this number was “over thirty.” It is not clear from the evidence before the court precisely how many proposal letters or individual change requests were forwarded to the COTR. However, it is clear that at least thirty-two individual change requests became the subjects of seven bilateral modifications to the contract (Modifications One, Two, Three, Four, Five, Seven, and Eight), which increased the value of the contract to $2,179,-282.95 and also extended the completion date by approximately 319 calendar days, to April 22,1993.1

Each of these seven modifications contained a release clause providing:

In consideration of the modification agreed to herein as complete equitable adjustment for the Contractor’s letter of proposal for adjustment ..., the Contractor releases the Smithsonian Institution from any and all liability under this contract for further equitable adjustment attributable to such facts or circumstances giving rise to the proposals for adjustment.

(See, e.g., Appendix at 90.) In each case the date or dates of the contractor’s relevant proposal letters were entered into the release provision.

The contract was accepted by the Smithsonian as substantially complete on June 3, 1993. However, negotiations over additional change requests continued for some time. Modification Nine, which covered six change request proposals, was negotiated between Niko and the COTR, was signed by Niko on October 18, 1993, but was not executed by the CO because Niko had stricken the release language. The negotiated amount was $30,332.06. On June 3,1994, Niko submitted a claim to the CO requesting a final decision; it claimed that the contract modifications did not adequately compensate it for the change work and that it was entitled to additional payment of $1,064,391.91. On July 18, 1994, Niko submitted a revised claim in the amount of $1,131,210.25.

By written decision dated December 20, 1994, the CO denied Niko’s claim in part and sustained it in part. The CO found that Niko was entitled to an equitable adjustment of $43,800.32 including interest, which represented the $30,332.06 initially addressed by the ninth contract modification along with some additional direct-cost items. The balance of the claim was denied on the basis of [798]*798the releases. On December 21,1994, the CO unilaterally executed Modification Nine.

On June 26, 1995, plaintiff filed its present claim in this court. The substance of Niko’s ten-count complaint is that the contract design contained numerous defects that were not evident to the contractor prior to beginning performance, that Niko was called on to do work that was not within the original scope of the contract, and that both phenomena caused delays. Although Niko agrees that it was compensated to some degree for these delays and defects through the nine contract modifications, it alleges here, as it did to the CO, that the release clauses contained in seven of the modifications do not operate to foreclose Niko from seeking additional compensation — primarily profit and overhead — for work related to the modifications. Niko asserts that, despite the apparent effect of the release clauses,2 it entered a separate oral agreement with the Smithsonian whereby it would be allowed to seek additional compensation for profit and overhead once an audit was performed. In the alternative, if the court views the release language of the modifications as evidence of a valid accord and satisfaction, Niko also maintains that each of the contract modifications was forced upon it by the Smithsonian’s exercise of improper economic duress.

For its part, the Government relies on the release language of the first seven bilateral modifications as evidence of an accord and satisfaction on the change work at issue there. It asserts that neither the project COTRs nor the CO made any representations to Mr. Lardas that Niko would be allowed to claim additional profit and overhead on any of the eight bilateral contract modifications. The Government further claims that it did not unduly coerce Niko into signing any of the contract modifications, and that Niko was always free to refuse the proposed modification if it did not agree with the terms. In addition, the Government argues that Niko has been fully compensated for the change work addressed in Modification Nine, which was unilaterally executed by the CO after substantial completion of the contract.

The Government moved for summary judgment once before, primarily in reliance on the language of the releases. Niko responded to the earlier motion with the contentions that the releases were unenforceable either because of duress or because representations were made prior to their execution that they would not preclude the later submission of larger claims arising out of the same facts. That motion was denied without prejudice because it was unclear what the facts were with respect to those representations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cavalier Clothes, Inc. v. United States
51 Fed. Cl. 399 (Federal Claims, 2001)
Vicari v. United States
47 Fed. Cl. 353 (Federal Claims, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
42 Cont. Cas. Fed. 77,244, 39 Fed. Cl. 795, 1997 U.S. Claims LEXIS 299, 1997 WL 804610, Counsel Stack Legal Research, https://law.counselstack.com/opinion/niko-contracting-co-v-united-states-uscfc-1997.