Vicari v. United States

47 Fed. Cl. 353, 2000 U.S. Claims LEXIS 160, 2000 WL 1171980
CourtUnited States Court of Federal Claims
DecidedAugust 16, 2000
DocketNo. 99-988C
StatusPublished
Cited by5 cases

This text of 47 Fed. Cl. 353 (Vicari v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vicari v. United States, 47 Fed. Cl. 353, 2000 U.S. Claims LEXIS 160, 2000 WL 1171980 (uscfc 2000).

Opinion

ORDER

MILLER, Judge.

This case, initiated under the Contract Disputes Act of 1976, 41 U.S.C.A. §§ 601-613 (West 1987 & Supp.1999) (the “CDA”), is before the court on defendant’s motion to dismiss in part, or, in the alternative, for partial summary judgment. Defendant seeks to dismiss Counts I, III, and IV of plaintiffs complaint for failure to state a claim upon which relief can be granted. The parties briefed the motion as one for summary judgment, see RCFC 12(b), and the court resolves it on that basis.1 The issues turn on whether the items for which plaintiff seeks compensation are barred by various contract clauses or the doctrine of accord and satisfaction. The court rules that defendant is entitled to judgment in its favor because the contract clauses are clear on point and because plaintiff has failed to put forth a genuine issue of material fact that could avoid a prior settlement. Argument is deemed unnecessary.

FACTS

Pete Vicari, General Contractor, Inc. (“plaintiff’), entered into firm fixed-price Contract No. DTCG47-97-3EFK 01, with the United States Coast Guard (the “USCG”) for construction projects on the Coast Guard Station located at Grand Isle, Louisiana. The contract, entered into on March 13,1997, called for constructing the Unaccompanied Personnel Housing (the “UPH barracks”), road resurfacing, and building of a fire lane.

During the course of performance, adverse weather conditions at the site delayed the project’s completion. Consequently, plaintiff submitted a series of requests for equitable adjustment to the contract. On July 22, 1997, plaintiff requested a five-day extension due to rain delays. This request was granted by bilateral Modification 0003 to the contract. By letters dated September 22, 1997, December 9, 1997, and January 15, 1998, plaintiff requested a total of 37 additional days due to adverse weather conditions. Plaintiffs requests resulted in Modification 0004, which extended the contract completion date by 90 days, from April 20, 1998, to July 19, 1998. By letters dated March 2, 1998, and April 20, 1998, plaintiff requested a total of 17 days’ extension due to weather delays. The contracting officer issued bilateral Modification 0006 on May 14,1998, providing for a 19-day extension in satisfaction of weather delays requested in plaintiffs March and April 1998 correspondence. Plaintiff submitted additional requests for three-day, nine-day, one-day, and four-day extensions of time due to weather delays on June 11, August 31, September 8, and September 9,1998, respectively. The contracting officer denied all requested modifications except for the four-day extension requested pursuant to plaintiffs September 9, 1998 letter. By letter dated October 1,1998, plaintiff also requested a 22-day extension due to unforeseen weather conditions in September. By letter dated October 15, 1998, plaintiff was granted an 18-day extension. Unilateral Modification 0010 subsequently issued, formally granting plaintiff a 22-day extension reflecting the four-day extension requested on September 9, 1998, as well as the 18-day extension granted by the contracting officer on October 15,1998.

[356]*356Due to adverse weather conditions of rain and high winds, plaintiff also obtained Builder’s Risk/Wind Insurance. Plaintiff maintained this additional insurance on the property from October 1997 through November 1998, incurring expenses of $72,961.71. Plaintiff was not required by the contract to obtain this type of insurance. On June 18, 1998, the contracting officer reimbursed plaintiff for 17 days’ coverage at the insured’s rate of $95.79 per day, for a total of $1,628.43.

During the course of performance, plaintiff claimed additional reimbursement against the USCG for delays in architect approval and design deficiencies caused by Graves & Carlos Architects Engineers, P.C. (“G & C”). Plaintiff requested modifications to the contract to increase the contract price for the cost of these delays and deficiencies. In the interim the USCG, plaintiff, and G & C negotiated a settlement agreement limited to “structural modifications and associated work on the UPH Barracks.” This January 5, 1999 agreement compensated plaintiff in the amount of $111,410.74 and granted plaintiff an extension of time, from January 18, 1999, to March 31, 1999, to complete the project. The agreement recited that it was in full satisfaction of plaintiffs claims against G & C and the USCG for both delays and design deficiencies. In consideration for plaintiffs release of its claims regarding the design deficiencies, the USCG gave up its right to assess liquidated damages for delay in completion of the project.

Count I of the complaint requests compensation for weather delays through August 31, 1998, constituting 58 days at $378.56 per day, for a total of $86,564.42 in damages. Count III seeks reimbursement in the amount of $72,961.71 for costs of obtaining Builder’s Risk/Wind Insurance, which plaintiff claims was necessary due to adverse weather conditions at the job site. Specifically, plaintiff seeks, the cost of maintaining the additional insurance through November 19, 1998. Count TV arises out of a settlement reached between the USCG, plaintiff, and G & C regarding design deficiencies on the project and claims that the settlement is void on grounds of duress. Plaintiff’s claimed losses arising out of design deficiencies total 82 days of delay for which plaintiff estimates damages of $116,729.01.

DISCUSSION

1. Summary judgment standards

Summary judgment is proper when no genuine issues of material fact are in dispute and the moving party is entitled to judgment as a matter of law. See RCFC 56(c). Genuine disputes over material facts that may significantly affect the outcome of the matter preclude an entry of judgment. See Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986) (finding dispute to be genuine if jury could find in favor of non-moving party). In opposing each other’s motions, plaintiff and defendant are entitled to “all applicable presumptions, inferences, and intendments,” H.F. Allen Orchards v. United States, 749 F.2d 1571, 1574 (Fed.Cir.1984). Yet, because they cross-moved, each party bears the burden of demonstrating entitlement to judgment, as well as the absence of issues of material fact. See Celotex Corp. v. Catrett, 477 U.S. 317, 322-24, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). Each party must provide evidence that is more than merely colorable in response to the other’s motion. See id. at 324, 106 S.Ct. 2548 (noting that evidence need not be admissible at trial); Barmag Barmer Maschinenfabrik AG v. Murar ta Mach., Ltd., 731 F.2d 831, 836 (Fed.Cir. 1984); see also Avia Gkroup Int’l, Inc. v. L.A. Gear California, Inc., 853 F.2d 1557, 1560 (Fed.Cir.1988). However, mere assertions or conclusory allegations are insufficient, see SRI Int’l v. Matsushita Elec. Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
47 Fed. Cl. 353, 2000 U.S. Claims LEXIS 160, 2000 WL 1171980, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vicari-v-united-states-uscfc-2000.