Preferred National Insurance v. United States

54 Fed. Cl. 600, 2002 U.S. Claims LEXIS 330, 2002 WL 31718706
United States Court of Federal Claims·Decided December 2, 2002·No. No. 99-129C·Published·Cited by 6 cases

Opinion

OPINION

WIESE, Judge.

This case is before the court on defendant’s motion to dismiss the complaint for [601] lack of subject matter jurisdiction, or, in the alternative, for summary judgment. Oral argument was heard on November 18, 2002. For the reasons set forth below, defendant’s alternative motion for summary judgment is granted with respect to plaintiffs claim of duress, and defendant’s motion to dismiss for lack of subject matter jurisdiction is granted with respect to all other claims.

FACTS

Plaintiff, Preferred National Insurance Company, was a surety to a contract executed on February 27,1991, between the United States Department of the Air Force (the Air Force) and A.W. & Associates, Inc./3M Masonry, a joint venture (the contractor). The contract was for Simplified Acquisition of Base Engineering Requirements (SABER) in connection with maintenance and repair services to be performed at Patrick Air Force Base in Florida (the SABER contract). The SABER contract was an indefinite quantity contract with a guaranteed minimum value of $200,000. After the close of the base year, the SABER contract provided for four option years, to be exercised at the Air Force’s discretion. On April 18, 1991, the Air Force modified the contract to extend the base year to March 7,1992.

In conformity with the Miller Act, 40 U.S.C. §§ 270a-270d (2000), the SABER contract mandated that the contractor obtain a performance bond with a penal sum of 100 percent of the guaranteed minimum contract value, or $200,000, and a payment bond with a penal sum of 50 percent of the guaranteed minimum contract value, or $100,000. Additionally, Paragraph H-8(c) of the contract provided that upon exhaustion of the guaranteed minimum, separate performance and payment bonds would be required for each individual delivery order over $25,000.

On March 8, 1991, the Air Force issued a blanket delivery order in the amount of $200,000. Regency Insurance Company, the initial surety to the contract, posted performanee and payment bonds in favor of the contractor, the principal obligor, in the amounts required by the SABER contract. Subsequently, on July 8, 1991, plaintiff, the follow-on surety, posted performance and payment bonds in favor of the contractor with penal sums of $300,000 and $150,000, respectively (the July bonds). On October 31, 1991, plaintiff furnished an additional set of performance and payment bonds with penal sums of $200,000 and $100,000, respectively (the October bonds). Neither the July bonds nor the October bonds included expiration dates.

In November 1991, the Air Force and the contractor agreed to delete Paragraph H-8(c) from the contract. By mutual agreement of the parties, but without involvement of the surety, that deletion was made retroactive as of October 31, 1991. On March 5, 1992, the Air Force unilaterally exercised its option to extend the contract through March 7, 1993. Plaintiff did not bill the contractor for any additional premiums after March 31, 1992.

Shortly after the Air Force exercised the first option year, subcontractors and suppliers on the SABER contract began experiencing payment problems with the contractor. The Air Force responded to their complaints of nonpayment by referring them to plaintiff as the contractor’s surety. However, plaintiffs agent, Americlaim Adjustment Corporation (Americlaim), took the position that all of plaintiffs bonds had expired when the base year of the SABER contract came to a close in March 1992. Consequently, according to Americlaim, plaintiff was not liable as payment or performance surety for any delivery orders issued after that date. The Air Force did not accept Americlaim’s assessment. Instead, in September 1992, the contracting officer sought assurance that the October bonds remained in effect from Michael W. Brown of Brown Insurance Agency, Inc., the individual who had acted as plaintiffs agent when the bonds were issued.1 The substance [602] of Mr. Brown’s response is in controversy. Internal Air Force memoranda indicate that Mr. Brown stated that plaintiffs October bonds would be effective through October 31, 1992. Both plaintiff and Mr. Brown, however, claim that no such statement was made.

During the next ten months, the contractor, the Air Force, and plaintiff went back and forth on the subject of the bonds. In November 1992, A.W. & Associates, Inc., advised the Air Force that plaintiffs bonds had been valid through October 31, 1992. The Air Force then repeated this position to Mr. Brown, referring to his “verbal assurance” that the bonds had been valid through that date.

In May 1993, A.W. & Associates, Inc., filed for bankruptcy under Chapter 11 of the Bankruptcy Act. The Air Force subsequently terminated the SABER contract for default. In a June 2, 1993, letter, the Air Force notified plaintiff of the bankruptcy filing. Attached to that letter was a list of open delivery orders “covered by [plaintiffs] bonds.” The delivery orders ranged in date from September 26, 1991, to May 4, 1993, and totaled in excess of $3 million. Plaintiff responded by reiterating that its bonds had expired at the end of March 1992. Again, the Air Force disagreed.

In early July 1993, the Air Force contacted plaintiff with a request that plaintiff honor its performance bond obligations by entering into a takeover agreement for the SABER contract. Plaintiff declined on the ground that it was not the “bonding company of record.” In a July 15, 1993, letter, the Air Force advised plaintiff of its opinion that both the July and October bonds had been in effect through November 17, 1992. The letter explicitly identified Mr. Brown as the source of that date, stating that “Mr. Brown has always maintained your bonds were in effect through 17 Nov 92.”2 The Air Force also warned that plaintiff would be held responsible for any costs incurred as a result of its “apparent unwillingness to honor its obligations.” The Air Force continued to refer unpaid subcontractors and suppliers to plaintiff.

At some point between July 15 and August 27, 1993, the Air Force renewed its request that plaintiff take over the SABER contract. The Air Force informed plaintiff that it would seek to have plaintiff removed from the Treasury Department’s approved surety list if it did not honor its performance and payment bonds.

On August 27, 1993, plaintiff and the Air Force entered into a construction contract takeover agreement. The parties agreed that plaintiff would be reimbursed from the unpaid balance of the contract price for the costs and expenses of assuming performance, and that expenses in excess of the unpaid balance would be credited against the penal limit of plaintiffs performance bond.

Free access — add to your briefcase to read the full text and ask questions with AI

Preferred National Insurance v. United States, 54 Fed. Cl. 600, 2002 U.S. Claims LEXIS 330, 2002 WL 31718706 (uscfc 2002).

54 Fed. Cl. 600 (Preferred National Insurance v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

M.E.S., Inc. v. United States
99 Fed. Cl. 239 (Federal Claims, 2011)
Nelson Construction Co. v. United States
79 Fed. Cl. 81 (Federal Claims, 2007)
Nova Casualty Co. v. United States
72 Fed. Cl. 755 (Federal Claims, 2006)
National American Insurance v. United States
72 Fed. Cl. 451 (Federal Claims, 2006)
Wagner v. United States
71 Fed. Cl. 355 (Federal Claims, 2006)
American Insurance v. United States
62 Fed. Cl. 151 (Federal Claims, 2004)