Cincinnati v. Triton Servs., Inc.

2019 Ohio 3108
Ohio Court of Appeals·Decided August 2, 2019·No. C-170705·Published·Cited by 7 cases

Opinion

IN THE COURT OF APPEALS

FIRST APPELLATE DISTRICT OF OHIO HAMILTON COUNTY, OHIO

CITY OF CINCINNATI, : APPEAL NO. C-170705 TRIAL NO. A-1405757

Plaintiff-Appellee/Counterclaim- :

Defendant, OPINION.

:

vs.

:

TRITON SERVICES, INC., :

Defendant-Appellant/ Counterclaim-Plaintiff, :

OHIO FARMERS INSURANCE : COMPANY, :

and :

MAJID H. SAMARGHANDI, :

Defendants/Counterclaim-

Plaintiffs, :

and : TRITON PROPERTIES, LLC, :

Defendant. :

TRITON SERVICES, INC., : APPEAL NO. C-170705 TRIAL NO. A-1500905

Plaintiff-Appellant/Counterclaim- :

Defendant, :

vs.

:

CITY OF CINCINNATI, A MUNICIPAL : CORPORATION, :

Defendant-Appellee/ Counterclaim-Plaintiff. :

Civil Appeal From: Hamilton County Court of Common Pleas

Judgment Appealed From Is: Affirmed in Part, Reversed in Part, and Cause Remanded

Date of Judgment Entry on Appeal: August 2, 2019

Paula Boggs Muething, City Solicitor, Joseph C. Neff, Assistant City Solicitor, and Taft Stettinius & Hollister, LLP, Earl K. Messer and Nicolas J. Pieczonka, for the City of Cincinnati,

Stites & Harbison, PLLC, William G. Geisen and Andrew J. Poltorak, for Triton Services, Inc., Ohio Farmers Insurance Company, and Majid H. Samarghandi.

WINKLER, Judge.

{¶1} Appellant Triton Services, Inc., (“Triton”) appeals several orders

entered against it in favor of appellee city of Cincinnati (“the city”) in two consolidated cases. We find merit in four of Triton’s eight assignments of error. We therefore affirm the trial court’s judgment in part and reverse it in part.

The Wesselman/Carroll Projects

{¶2} The record shows that in April 2008, Triton entered into a contract with the city, acting on behalf of the Metropolitan Sewer District (“MSD”). Under the contract, Triton was the general contractor performing sewer work for the Wesselman Road Interceptor Sewer Phase 1A-3 and 1B project (“Wesselman Project”). Subsequently, Triton entered into another contract with the city to perform the Carroll Avenue Sewer Replacement Project (“Carroll Project”). Ohio Farmers Insurance Company provided surety bonds for both projects.

{¶3} In June 2011, the city issued three checks totaling $496,256.09 to Triton for the work it had performed on the Wesselman and Carroll Projects. Triton deposited the checks into its bank account. Several months later, the city discovered that Pavement Management, one of Triton’s subcontractors, had not been paid. The city took steps to stop payment on the checks it had issued to Triton. The city was erroneously informed by its bank that the payment had been stopped.

{¶4} Subsequently, Pavement Management filed suit against Triton and the city, seeking the money that it was owed for its work on the projects. To resolve that lawsuit, the city paid $396,756.09 to Triton and $99,500 to Pavement Management.

{¶5} In January 2014, the city discovered that the checks for the original payments of $496,256.09 had not been stopped because the stop-payment orders had been issued too late. After the city discovered the accidental double payment, it

sent numerous letters to Triton requesting the return of the original payment of $496,256.09. Triton never returned the payment.

{¶6} Subsequently, in the case numbered A-1405757, the city filed a complaint against Triton alleging unjust enrichment and breach of contract. The city also named Ohio Farmers Insurance Company (“Farmers”) as a defendant and made a claim under the surety bonds on the projects. In conducting discovery, it learned that Triton knew that the city’s checks were fully deposited into Triton’s checking accounts and that the relevant funds were never returned to the city. In fact, the overpayment was transferred between numerous bank accounts.

{¶7} Consequently, the city amended its complaint to add claims for fraud and punitive damages against Triton and Majid H. Samarghandi, Triton’s CEO. In response, Triton and Samarghandi asserted counterclaims for abuse of process and frivolous conduct, in which they alleged that the city had filed the fraud claim to harass them and force them to surrender the payment.

{¶8} Eventually, the city withdrew its fraud and punitive-damages claims.

The trial court granted summary judgment in favor of the city on its unjust- enrichment claim and awarded the city $496,256.09. The court also granted summary judgment in favor of the city on Triton’s claim for abuse of process. As to the claim for attorney fees for frivolous conduct, the court found that the issue should have been raised by motion rather than in Triton’s counterclaim. The court stated that the evidence related to frivolous conduct should not be presented to the jury, but that it would allow Triton to raise the issue by motion after the trial of the other issues raised in a consolidated case.

The Sagebrush Project

{¶9} In July 2011, Triton entered into a contract with the city to perform work on the Sagebrush Lane, Susanna Drive, and Yellowstone Drive sewer project (“Sagebrush Project”). The original contract amount was $2,698,440. The contract incorporated the bid booklet, the State of Ohio Department of Transportation Construction and Material Specifications (“ODOT CMS”), and the city of Cincinnati’s supplement to the ODOT CMS.

{¶10} A geotechnical report was incorporated into the bid booklet. It provided that “excavations for the sewer are anticipated to primarily encounter cohesive soils interbedded occasionally with cohesionless soils.” The report stated that no water was found at a majority of the test borings, which led to the recommendation that trench excavations be performed in 50-foot sections with each section being backfilled before proceeding to the next trench excavation. The bid booklet stated that the geotechnical report was for informational purposes only and that the report was not a substitute for actual site inspection.

{¶11} Triton began work on the Sagebrush Project in September 2011. Soon after, it discovered differing soil conditions than it had expected. Triton claimed that it had encountered sloughing soils, trench cave-ins, excessive groundwater, and extremely wet conditions, which caused it to incur substantial increased expenses.

{¶12} The contract spelled out what should occur if Triton encountered differing site conditions. ODOT CMS ¶ 104.02(B) provided:

During the progress of the Work, if subsurface or latent physical conditions are encountered at the site differing materially from those indicated in the Contract Documents or if unknown physical conditions of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in

the Work provided for in the Contract Documents, are encountered at the site, notify the Engineer as specified in 104.05 of the specific differing conditions before they are disturbed or the affected Work is performed.

Upon notification, the Engineer will investigate the conditions and if it is determined that the conditions materially differ and cause an increase or decrease in the cost or time required for the performance of any Work under the Contract, the Department will make an adjustment and modify the Contract as specified in 108.06 and 109.05. The Engineer will notify the Contractor of the determination whether or not an adjustment of the Contract is warranted.

The “Engineer” was defined as a “[d]uly authorized agent of the Department acting within the scope of its authority for purposes of engineering and administration of the Contract.” ODOT CMS ¶ 101.03.

{¶13} ODOT CMS 104.05(D), as amended by the city supplement, required the contractor to:

Free access — add to your briefcase to read the full text and ask questions with AI

Cincinnati v. Triton Servs., Inc., 2019 Ohio 3108 (Ohio Ct. App. 2019).

2019 Ohio 3108 (Cincinnati v. Triton Servs., Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Meadows v. Durrani
Ohio Court of Appeals, 2026
Potts v. Durrani
2023 Ohio 4195 (Ohio Court of Appeals, 2023)
Cincinnati v. Triton Servs., Inc.
2022 Ohio 3832 (Ohio Court of Appeals, 2022)
Payson v. Phipps
2022 Ohio 1525 (Ohio Court of Appeals, 2022)
Canfield v. United Airlines, Inc.
2021 Ohio 4460 (Ohio Court of Appeals, 2021)
Setters v. Durrani
2020 Ohio 6859 (Ohio Court of Appeals, 2020)
Vogel v. Albi
2020 Ohio 5242 (Ohio Court of Appeals, 2020)