Cincinnati v. Triton Servs., Inc.

2022 Ohio 3832
CourtOhio Court of Appeals
DecidedOctober 28, 2022
DocketC-210475
StatusPublished
Cited by2 cases

This text of 2022 Ohio 3832 (Cincinnati v. Triton Servs., Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cincinnati v. Triton Servs., Inc., 2022 Ohio 3832 (Ohio Ct. App. 2022).

Opinion

[Cite as Cincinnati v. Triton Servs., Inc., 2022-Ohio-3832.]

IN THE COURT OF APPEALS FIRST APPELLATE DISTRICT OF OHIO HAMILTON COUNTY, OHIO

CITY OF CINCINNATI, : APPEAL NO. C-210475 A MUNICIPAL CORPORATION, TRIAL NOS. A-1405757 : A-1500905 Plaintiff-Appellee, : vs. : O P I N I O N. TRITON SERVICES, INC.,

Defendant-Appellant. :

Civil Appeal From: Hamilton County Court of Common Pleas

Judgment Appealed From Is: Affirmed

Date of Judgment Entry on Appeal: October 28, 2022

Taft Stettinius & Hollister LLP and Joseph C. Neff, for Plaintiff-Appellee,

Stites & Harbison, PLLC, and Willian G. Geisen, for Defendant-Appellant. OHIO FIRST DISTRICT COURT OF APPEALS

BOCK, Judge.

{¶1} Defendant-appellant Triton Services, Inc., (“Triton”) appeals the trial

court’s judgment in favor of plaintiff-appellee city of Cincinnati (“the city”). Triton

asserts that the trial court erred by precluding witness testimony, failing to properly

instruct the jury, and refusing to allow the jury to determine whether the city waived

strict compliance with the contract’s notice provisions.

{¶2} Because we find that the “two-issue” rule applies, any alleged error is

rendered harmless. Therefore, we affirm the trial court’s judgment.

I. Facts and Procedure

A. The parties contracted for sewer work

{¶3} In July 2011, Triton and the city entered into a contract whereby Triton

was to serve as the general contractor on a project to replace sewers (“sewer project”).

The contract incorporated a bid booklet, the State of Ohio Department of

Transportation Construction and Material Specifications (“ODOT CMS”), and the

city’s supplement to the ODOT CMS (“city supplement”).

{¶4} The bid booklet incorporated a geotechnical report that stated,

“excavations for the sewer are anticipated to primarily encounter cohesive soils

interbedded occasionally with cohesionless soils.” The report stated that most of the

test borings contained no water. The bid booklet stated that Metropolitan Sewer

District (“MSD”) did not guarantee or warrant “the accuracy, reliability, or

correctness” of the geotechnical report.

{¶5} Soon after Triton began work, it encountered differing soil conditions,

such as sloughing soils, trench cave-ins, excessive groundwater, and extremely wet

conditions, which caused Triton to incur unanticipated expenses.

2 OHIO FIRST DISTRICT COURT OF APPEALS

{¶6} The contract provided that if Triton encountered conditions that

materially differed from either the contract documents or from conditions ordinarily

encountered and generally inherent in this type of work, Triton was required to notify

the city’s engineer before the conditions were disturbed. Moreover, Triton had to

provide “written notice of any circumstance or dispute on the project that may result

in a claim. Give early notice by the end of the second working day following the

discovery of the occurrence of the circumstance or dispute.” The contract warned,

“[f]ailure to give early notice or keep and submit cost records will be a sufficient reason

for the City to deny the claim.”

{¶7} The contract contained a mandatory-dispute-resolution process that

had to be exhausted before Triton could bring a claim. The parties could not proceed

to the next tier of the process until the previous tier was complete:

1. Step 1 of Dispute Resolution (Project Level): The Construction

Engineer will meet with the Contractor’s Superintendent within two

working days of receipt of any early notice. They shall review all

pertinent information and * * * negotiate an equitable settlement *

* *. If settlement is not achieved, the dispute is moved to Step 2.

2. Step 2 of Dispute Resolution (Principal Engineer Level): * * *

[R]equest a meeting with the Principal Construction Engineer

within five working days of completion of Step 1. * * * The City and

Contractor’s personnel shall review the information * * * and

negotiate an equitable settlement according to the Contract

Documents. If settlement is not achieved, the dispute is moved to

Step 3.

3 OHIO FIRST DISTRICT COURT OF APPEALS

3. Step 3 of Dispute Resolution (City Engineer / Chief Engineer Level):

Send the City / Chief Engineer a Notice of Intent to File a Certified

Claim within 14 calendar days of the completion of Step 2. State in

the notice the Contractor’s request for a hearing on the claim or for

an acceptable alternative dispute resolution technique.

{¶8} According to Triton, its director of site development, Brian Gessner,

discussed the differing site conditions with city representatives, including Steve Jones,

the city’s supervising engineer for the sewer project. Triton asserted that Jones

directed Gessner to submit all costs incurred due to differing site conditions at the end

of the project.

{¶9} Triton submitted various change order requests (“COR”) relating to

unforeseen ground conditions. MSD approved all the CORs, except for COR #14,

which was to recoup additional expenses due to undocumented, unsuitable ground

conditions throughout the project, for a total of $534,321.65. The city denied COR #14

and refused to pay Triton for its claimed additional expenses caused by ground

conditions throughout the project. COR #14, and the city’s refusal to pay, is the subject

of this appeal.

{¶10} There is no dispute that Triton did not provide early notice of the

differing site conditions. But Triton asserts that it did not provide early notice because

Jones had waived the early-notice requirement.

B. Both parties sue

{¶11} The city sued Triton for unjust enrichment, breach of contract, and

indemnification. Triton sued the city, the Hamilton County Board of County

Commissioners, and MSD, alleging breach of contract and unjust enrichment due to

4 OHIO FIRST DISTRICT COURT OF APPEALS

the city’s refusal to approve COR #14. The city counterclaimed for breach of contract

and a declaration that Triton must indemnify the city. The trial court consolidated the

cases.

{¶12} Triton and the city resolved some claims and agreed to a bench trial. The

trial court granted the city’s motion for a directed verdict. Triton appealed the court’s

judgment. This court remanded the case for a new trial. City of Cincinnati v. Triton

Servs., Inc., 2019-Ohio-3108, 140 N.E.3d 1249 (1st Dist.).

{¶13} On remand, the court held a jury trial. The parties agreed to the

following jury interrogatories:

1) Did Triton encounter differing site conditions throughout the

[sewer] Project?

2) Was the City contractually obligated to compensate Triton for the

differing site conditions encountered throughout the [sewer]

Project?

3) If so, what sum of money, if any, would fairly and reasonably

compensate Triton for its resulting damage?

{¶14} The jury returned a verdict in the city’s favor. The jury interrogatories

reflected that, though the jury found that Triton had encountered differing site

conditions, the city was not required to compensate Triton. The interrogatories did not

specify which contract provisions led the jury to its verdict.

{¶15} This appeal followed.

II. Law and Analysis

{¶16} Triton’s three assignments of error assert that the trial court 1)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ragouzis v. Madison House Condominium Owners Assn.
2026 Ohio 290 (Ohio Court of Appeals, 2026)
State v. Gray
2025 Ohio 4607 (Ohio Court of Appeals, 2025)
Kaiser v. Goff
2022 Ohio 4725 (Ohio Court of Appeals, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
2022 Ohio 3832, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cincinnati-v-triton-servs-inc-ohioctapp-2022.