Holloway & Son Construction Co. v. Mattingly Bridge Co.

581 S.W.2d 568, 1979 Ky. LEXIS 259
CourtKentucky Supreme Court
DecidedMay 1, 1979
StatusPublished
Cited by4 cases

This text of 581 S.W.2d 568 (Holloway & Son Construction Co. v. Mattingly Bridge Co.) is published on Counsel Stack Legal Research, covering Kentucky Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holloway & Son Construction Co. v. Mattingly Bridge Co., 581 S.W.2d 568, 1979 Ky. LEXIS 259 (Ky. 1979).

Opinions

STERNBERG, Justice.

This litigation grew out of a contract for highway construction. For convenience, we will refer to Holloway & Son Construction Company, Inc., as “Holloway,” to Mattingly Bridge Company, Inc., as “Mattingly,” and [569]*569to the Commonwealth of Kentucky, Department of Transportation, Bureau of Highways, as “Department.”

In January, 1971, Holloway entered into a contract with the Department for the construction of an 8-mile section of the Bowling Green-Somerset Parkway. On February 9, 1971, Holloway entered into two contracts with Mattingly for the bridge and concrete structures. The two contracts will be referred to as “Contract A” and “Contract B.” Contract A is a “place only” contract and Contract B is what is known as a “place and furnish” contract. In other words, under the terms and provisions of Contract A, Holloway agreed to furnish the materials and Mattingly was obligated to place them, while under Contract B Mat-tingly was obligated to furnish and place the materials. Both contracts contained the provision: “This subcontract is entered into subject to the approval of the Kentucky Department of Highways.” As between the parties, however, this provision was a farce. They both knew and agreed at the time of the execution of the two contracts that only Contract A would be submitted to the Department for approval and that they would actually operate under the conditions of Contract B. Contract A was submitted to and approved by the Department; Contract B was not submitted to nor approved by the Department. For all practical purposes, the contracts are identical as to the items of construction. They differ greatly, however, in the manner in which they were to be performed. For example, under Contract B, page 3a, there is an item, No. 8.0, dealing with “Furnishing 12 BP 53 Steel Piles,” while under Contract A there is no such item. Item Numbers 3, 4, 10, 11, 14, 15, 16 and 17 of Contract B differ from the corresponding numbered items in Contract A. Furthermore, under Contract B, Item Number 15(2), page 5, provides, “The contractor will pay for all materials at the prices negotiated by the subcontractor and deduct same in full from payments due subcontractor.” The corresponding numbered item in Contract A provides, “The Contractor will furnish ready mix concrete for item numbers 3 and 4, precase prestressed concrete beam type 3 for item number 10, high strength handrail for item number 11, steel reinforcement for item number 14, and structural steel for item numbers 15, 16, and 17.”

Shortly after the date of the approval of Contract A, Mattingly commenced to work, and the project was completed in the late summer or early fall for 1972. On or about May 19, 1972, Mattingly filed a mechanic’s and materialman’s lien against Holloway in the office of the County Court Clerk of Franklin County, Kentucky. KRS 376.195. On June 2, 1972, Mattingly filed an amended statement of lien, and again on August 9, 1972, filed a second amended statement of lien. The original statement of lien charged that Holloway was indebted to Mattingly “. . . for labor and materials furnished by the claimant-lienor (Mat-tingly) at the instance and request of the debtor-lienee (Holloway) for the prosecution of work required of the debtor-lienee under its contract . . . . In addition, it is anticipated that the claimant-lienor will furnish and deliver to the debtor-lienee further labor and materials for incorporation into the above referenced projects . . .” Each of the amendments likewise charged that Mattingly performed work and furnished materials in the performance of the said contract.

On June 16, 1972, Mattingly filed suit in the Franklin Circuit Court, in which Holloway and the Department were named defendants. The complaint charged that Mat-tingly furnished labor and materials to Holloway, which labor and materials were used in the performance of the contract. In its complaint Mattingly sought to recover from Holloway for “labor and materials” furnished by Mattingly to Holloway. By an amended complaint Mattingly charged that he continued to furnish labor and materials to Holloway for use on the subject project. Holloway filed an answer, counterclaim and cross-complaint. It was a general traverse of the indebtedness claimed by Mattingly, other than for a retainer which was being properly held by Holloway. By counterclaim, Holloway sought to recover compen[570]*570satory and punitive damages from Mattingly for the wrongful filing of the lien statement and the amendments thereto. Holloway also, sought to recover from Mattingly for liquidated damages assessed against Holloway by the Department for the delay in the completion of the project. In the cross-complaint Holloway charged that an actual controversy existed regarding what funds were due Holloway from the Department, to which the lien of Mattingly attached. Holloway charged that the Department refused to release to it monies rightfully belonging to it which are not subject to the Mattingly lien. It requested that the Department be directed to pay to it the amount of such monies being held by the Department over and above any claim of Mattingly’s.

The case was tried to the court. On July 3, 1974, the trial judge filed a “Memo Opinion” and on July 11,1974, filed “Findings of Fact, Conclusions of Law and Judgment.” The trial court held that the rights of the parties were fixed by the terms and conditions of Contract A; that Holloway acquiesced in and waived the failure of Mat-tingly to execute a performance bond called for by the subcontract; that Mattingly should not recover interest on any retain-age; that there is no evidence to support Holloway’s claim against Mattingly for liquidated damages by reason of delay in the performance of the contract; that Mattingly performed and completed all work required of it under the terms and conditions of its subcontract; that Holloway’s claim against Mattingly for damages by reason of the filing of the lien statement was not supported by law or evidence; and that Mattingly should recover of Holloway the sum of $198,110.06. The judgment of the Franklin Circuit Court was affirmed on appeal. Review was granted on June 27, 1978.

The question for primary inquiry is whether the parties intended to operate under, and be bound by, the terms and conditions of Contract A or Contract B. The trial court refused to recognize Contract B and limited the inquisition and the determination as to the rights of the parties pursuant to Contract A. With respect to Contract B, the Court of Appeals said: “We think contract 'B’, relied upon by appellant, has a tendency to be injurious to the public and against the public good and is therefore not enforceable.” In other words, the Court of Appeals held that Contract B was against public policy and not enforceable. It also held that Contract B was in violation of KRS 176.100.

KRS 176.100 provides:

“No contractor shall deviate from the provisions, plans or specifications upon which a contract has been awarded without first having obtained written authority from the department to do so. If the contractor does deviate without such authority, neither the state of Kentucky, the department of highways, the department of finance nor the state treasurer shall pay or be liable for any work or material not fully provided for in the original contract.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mattingly Bridge Co. v. Holloway & Son Construction Co.
694 S.W.2d 702 (Kentucky Supreme Court, 1985)
Apex Contracting, Inc. v. William Robinson Construction Co.
581 S.W.2d 573 (Kentucky Supreme Court, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
581 S.W.2d 568, 1979 Ky. LEXIS 259, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holloway-son-construction-co-v-mattingly-bridge-co-ky-1979.