Five Star Lodging, Inc. v. George Construction, LLC

344 S.W.3d 119, 2010 WL 2976524
CourtCourt of Appeals of Kentucky
DecidedAugust 6, 2010
Docket2009-CA-000990-MR
StatusPublished
Cited by2 cases

This text of 344 S.W.3d 119 (Five Star Lodging, Inc. v. George Construction, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Five Star Lodging, Inc. v. George Construction, LLC, 344 S.W.3d 119, 2010 WL 2976524 (Ky. Ct. App. 2010).

Opinion

OPINION

THOMPSON, Judge:

The issue presented is whether an action against a surety on a performance and payment bond was barred by a two-year time limitation contained in the bond. We agree with the trial court that the action was barred and affirm.

On August 5, 1999, Five Star Lodging, Inc., entered into a construction contract with George Construction, LLC, for the construction of a hotel in Scott County, Kentucky. Pursuant to the terms of the contract, George Construction was required to obtain a performance and payment bond. In anticipation of the contract’s execution, on July 28, 1999, and acting through Cumberland Insurance Company as its agent, George Construction procured a performance and payment bond from Lyndon Property Insurance Company on behalf of George Construction as principal and in favor of Five Star as obligee.

Paragraph 12 of the bond provides:

No suit, action, or proceedings shall be brought hereunder by the Obligee unless as a condition precedent, it shall have been commenced within two (2) years from the earlier of the date of the completion of said Contract or the date of beneficial use or occupancy by the Obligee or owner; and no suit, action, or proceeding shall be brought hereunder by any Claimant unless, as a condition precedent thereto, written notice of its claim shall have been given by such Claimant to the Surety at its home office in the City of St. Louis, Missouri, as *122 required by Paragraph 8 herein; and, subject to the foregoing with respect to giving written notice, no suit, action or proceeding shall be brought by any Claimant hereunder unless commenced within twelve (12) months from the last of the material or labor which was furnished or performed at or upon the Project.

George Construction proceeded with construction of the hotel and on August 31, 2000, a certifícate of occupancy was issued. Five Star’s architect issued an architect’s certificate of substantial completion on September 5, 2000, reflecting that substantial completion was effective on August 28, 2000. Documentation in the record reveals that as early as June 2000, guests were lodged in the hotel.

Dissatisfied with the construction, Five Star began corresponding with George Construction and Cumberland regarding its complaints. As a result of its discussions with Five Star’s attorney, through written correspondence, Cumberland advised George Construction of the two-year limitation provision in the bond. Specifically, the letter stated in part:

This letter is in response to your letter of June 13, 2001, and our subsequent telephone conversation June 27, 2001, regarding the above named parties and the current status of the construction project bonded by Lyndon Property Insurance.
I have spoken with Mr. Gene Price of George Construction and with Mr. Bill Hurt, the attorney for George Construction. The consensus is that there needs to be a meeting, on site, to review any areas of the construction your client claims to be defective. The surety will be glad to participate in this procedure with the goal of resolving potential disputes.
On this bond the Obligee, your client, has two years from the completion date, June 21, 2000, in which to bring suit against the surety, should the surety fail to perform according to the terms and conditions of the bond.
Therefore, the surety has no desire to issue a Waiver for any time related conditions on this project. If there are subcontractors to George Construction approaching the one year warranty on workmanship for items not previously noticed directly or through George Construction, you should give these notices immediately.
The surety reserves all rights and defenses under the bond, the contract and the law.

On May 31, 2002, Five Star filed a complaint against George Construction as a result of its dissatisfaction with the hotel construction. Subsequently, the case was placed in abeyance pending arbitration of the dispute and, as a result, George Construction did not file an answer to the complaint. Five Star moved for a default judgment on January 2, 2007, which was granted on February 19, 2007.

On March 1, 2007, approximately seven years subsequent to the issuance of the occupancy permit, the approval of the construction by Five Star’s architect, and Five Star’s occupancy of the hotel, Five Star sought to amend its complaint against George Construction to add the bond’s surety but erroneously named Cumberland. Lyndon then entered the litigation by its own intervention for the purpose of substituting itself for Cumberland. Because Five Star sought compensation for the surety’s alleged failure to comply with its obligations under the bond and because Lyndon, not Cumberland, was the surety on the bond, the circuit court dismissed Cumberland from the action on February 11, 2008.

*123 In reliance on paragraph 12 of the surety bond and its two-year time limitation, Lyndon moved for summary judgment arguing that Five Star used or occupied the hotel at least by August 2000, when the certificate of occupancy and the architect’s certificate of substantial completion were issued and, therefore, its action was time-barred. The circuit court agreed and sustained Lyndon’s motion for summary judgment. This appeal followed.

The rule in this jurisdiction pertaining to a summary judgment is stated as follows:

The proper standard of review on appeal when a trial judge grants a motion for summary judgment is whether the trial judge correctly found that there were no genuine issues as to any material fact and that the moving party was entitled to a judgment as a matter of law. CR 56.03. It has long been held that a trial judge must view the evidence in the light most favorable to the non-moving party, and summary judgment should be granted only if it appears impossible that the nonmoving party will be able to produce evidence at trial warranting a judgment in his favor. The moving party bears the initial burden of demonstrating that no genuine issue of material fact exists and then the burden shifts to the party opposing summary judgment to produce at least some affirmative evidence showing that there is a genuine issue of material fact requiring trial.

First Federal Sav. Bank v. McCubbins, 217 S.W.3d 201, 203 (Ky.2006) (citations omitted). With this standard as our guide, we turn to the issues presented.

We first dispose of Five Star’s appeal of the order dismissing Cumberland. There is no dispute that the construction project was bonded by Lyndon Property Insurance. Although Five Star was apparently confused as to whether Cumberland or Lyndon bonded the property, the performance and payment bond stated that Lyndon bonded the construction project. If there was any ambiguity as to which company bonded the project, it was clarified by the letter written by Cumberland in 2000 to Five Star’s counsel wherein it was expressly stated that Lyndon bonded the construction project. We agree with the circuit court that Cumberland could not be liable on the bond issued by Lyndon.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
344 S.W.3d 119, 2010 WL 2976524, Counsel Stack Legal Research, https://law.counselstack.com/opinion/five-star-lodging-inc-v-george-construction-llc-kyctapp-2010.