Thaler v. I C I United States, Inc.

476 F. Supp. 67, 28 U.C.C. Rep. Serv. (West) 16, 1979 U.S. Dist. LEXIS 11201
CourtDistrict Court, W.D. Kentucky
DecidedJuly 6, 1979
DocketCiv. A. C 77-0081 L(A)
StatusPublished
Cited by3 cases

This text of 476 F. Supp. 67 (Thaler v. I C I United States, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thaler v. I C I United States, Inc., 476 F. Supp. 67, 28 U.C.C. Rep. Serv. (West) 16, 1979 U.S. Dist. LEXIS 11201 (W.D. Ky. 1979).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

ALLEN, Chief Judge.

This action is submitted to the Court for a decision on the merits after a trial which lasted one and one-half days.

Plaintiff brought its action praying for damages in the amount of $29,484.53, plus interest from May 8, 1974. The complaint is predicated on an alleged breach of defendant’s duty to pay plaintiff a balance of $8,314, and on the claim, under the terms of the contract, which specified a total payment of $27,552. It is stipulated by the parties that $19,238 has been paid under the terms of the contract.

Plaintiff also alleges that he relied upon the assurances of defendant that an additional four to five powder dumping machines would be purchased, and that he spent $48,244.53 in reliance upon these promises and to fulfill his contractual agreement to furnish one powder dumping machine to the defendant.

Defendant filed an answer and counterclaim stating, in substance, that the plaintiff failed to properly install and equip the powder dumping machine, and that, as a result thereof, it was compelled to expend $10,147.46 in order to replace defective parts and materials.

The evidence produced by the parties reveals that they originally agreed upon a contract of $24,818 for the purchase of the powder dumping machine, and its delivery to the defendant in Indiana. Subsequently, because of costs incurred as a result of inflation, the parties agreed to a modification of the contract, which then provided that defendant would pay plaintiff $27,552. It should be noted that the contract was entered into pursuant to a competitive bid made by the plaintiff following the submission to him and other parties of what was known as the specification for a powder dumping system dated March 26, 1973. When plaintiff bid on the specifications, it separated its bid into four components, which were as follows:

1. Design, Completion, Review, ICIA Approval $9,870.
2. Purchase, Building and Demonstrastration 8,780.
3. Ship and Install 3,728.
4. Acceptance Test and Completion of Project 2,440.

Plaintiff, in May and June, 1974, completed the first two components set out above. In May, 1974, it demonstrated the system to defendant’s representatives in Louisville, and after receiving their suggestions and comments, modified the system accordingly, and again showed the system to defendant’s representatives in Louisville in June. At that time the system was approved for shipping to Indiana, and the shipping took place on June 1, 1974, plaintiff having sent its truck and one employee to the plant of the defendant.

At this point the evidence produced by the parties takes widely divergent paths. Plaintiff’s evidence is to the effect that it *69 sent Earl Martin, a mechanic, to defendant’s plant, along with one other mechanic, to install the machine under the directions of Charles Troutman, an employee of the defendant. Plaintiff admits that Martin and the other mechanic were at the defendant’s plant on 8 or 9 occasions in June, 1974, in order to help with the installation of the system.

It further appears from plaintiff’s evidence that Earl Martin was dispatched to the defendant’s plant in October, 1974, and that the alleged reason for his being there was to help the defendant with problems which had arisen concerning a hydraulic pump. Plaintiff’s evidence is to the effect that the hydraulic pump burned out because of improper use by the defendant, to wit: the furnishing of oil which was not the type of oil which should have been used in the machine. Defendant counters this argument by stating that the machine, as originally designed, contained oil which was combustible and in violation of safety regulations which were called for in the contract.

James Thaler, the president of the plaintiff company, testified that finally, in January, 1975, since no payment had been received on the $8,314 balance owing to his company, he wrote a letter demanding payment of that amount. Defendant responded by a letter dated January 25, 1975, the substance of which was that some specified defects existed in the system and that these defects had been remedied by the defendant at a cost of $4,805.84, and that defendant offered in payment to plaintiff the balance owing on the contract price of $8,314, minus the $4,805.84 for back charges, resulting in a net amount of $3,509, for which defendant enclosed its check. Plaintiff refused to cash the check, taking the position which it has maintained throughout this case, that it was entitled to the balance of $8,314.

It is undisputed that plaintiff was never formally notified that there was a default in the contract or a breach of warranty, but defendant consistently maintains that it discovered many defects in the system upon its arrival, and that finally, in the fall of 1974, Mr. Page, its purchasing agent, discussed the matter with James Thaler and obtained his approval to correct the defects in the system and to back charge the expenses of the corrections to plaintiff. No written documents or memoranda were kept by Page or any other employee of defendant to substantiate their testimony that Thaler had agreed to have defendant repair the defects and back charge him for the reasonable costs of repairs.

The parties have stipulated that the Court should decide the case by applying Kentucky law. They are also in agreement that the Uniform Commercial Code, which has been adopted by Kentucky, governs the conduct of the parties and the results of this case. Plaintiff contends that it is entitled to judgment on the $8,314 claim, because it attached to its bid a warranty statement which, in part, is as follows:

“No allowance will be granted for any repairs or alterations made by Purchaser or at Purchaser’s direction without Company’s written consent, and no claims for labor or consequential damages or any other damages to persons or property will be allowed.”

Plaintiff contends that since there is no writing between the parties relating to the question of repairs or alterations, that this warranty controls. Plaintiff points to UCC Sec. 2-207 which is as follows:

“UCC 2-207(1), a definite and seasonable expression of acceptance or a written confirmation which is sent within a reasonable time operates as an acceptance even though it states terms additional to or different from those offered or agreed upon, unless acceptance is expressly made conditional on assent to the additional or different terms.”
“(2) The additional terms are to be construed as proposals for addition to the contract. Between merchants, such terms become a part of the contract unless: (a) [t]he offer expressly limits acceptance to the terms of the offer; (b) [t]hey materially alter it; or (c) [notification of objection to them has already been given or is given within a reasonable time after notice of them is received.”

*70 Comment (3) to the above provisions of UCC Sec. 207(1) and (2) is, in pertinent part, as follows:

“Whether or not additional or different terms will become part of the agreement depends upon the provisions of subsection (2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wehr Constructors, Inc. v. Steel Fabricators, Inc.
769 S.W.2d 51 (Court of Appeals of Kentucky, 1988)
In Re Morweld Steel Products Corp.
8 B.R. 946 (W.D. Michigan, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
476 F. Supp. 67, 28 U.C.C. Rep. Serv. (West) 16, 1979 U.S. Dist. LEXIS 11201, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thaler-v-i-c-i-united-states-inc-kywd-1979.