Hollywood Golf Estates, Inc. v. Nello L. Teer Company and United States Fidelity & Guaranty Company, Nello L. Teer Company and United States Fidelity & Guaranty Company v. Hollywood Golf Estates, Inc.

353 F.2d 485, 1965 U.S. App. LEXIS 3955
CourtCourt of Appeals for the Fifth Circuit
DecidedNovember 15, 1965
Docket21983_1
StatusPublished

This text of 353 F.2d 485 (Hollywood Golf Estates, Inc. v. Nello L. Teer Company and United States Fidelity & Guaranty Company, Nello L. Teer Company and United States Fidelity & Guaranty Company v. Hollywood Golf Estates, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hollywood Golf Estates, Inc. v. Nello L. Teer Company and United States Fidelity & Guaranty Company, Nello L. Teer Company and United States Fidelity & Guaranty Company v. Hollywood Golf Estates, Inc., 353 F.2d 485, 1965 U.S. App. LEXIS 3955 (5th Cir. 1965).

Opinion

353 F.2d 485

HOLLYWOOD GOLF ESTATES, INC., Appellant,
v.
NELLO L. TEER COMPANY and United States Fidelity & Guaranty
Company, Appellees.
NELLO L. TEER COMPANY and United States Fidelity & Guaranty
Company, Appellants,
v.
HOLLYWOOD GOLF ESTATES, INC., Appellee.

No. 21983.

United States Court of Appeals Fifth Circuit.

Nov. 15, 1965.

L. J. Cushman, Lewis Horwitz, Shepard Broad, Broad & Cassel, Lewis Horwitz, Miami Beach, Fla., for appellant and cross-appellee Hollywood Golf Estates, Inc.

Joseph A. McGowan, Wesley G. Carey, Miami, Fla., Charles B. Nye, Durham, N.C., Carey, Terry, Dwyer, Austin, Cole & Stephens by Edward A. Perse, Miami, Fla., for appellees-appellants Teer and U.S.F. & G.

Before TUTTLE, Chief Judge, THORNBERRY, Circuit Judge, and CARSWELL, District Judge.

THORNBERRY, Circuit Judge:

This is the second appeal of this case to this Court, the case having been affirmed in part and reversed and remanded in part when considered previously. See Nello L. Teer Company v. Hollywood Golf Estates, Inc., 324 F.2d 669 (5th Cir. 1963).

On December 23, 1959, Hollywood Golf Estates (hereinafter referred to as Estates) and the Nello L. Teer Company (hereinafter referred to as Teer) entered into a written contract whereby Teer agreed to raise the level of certain land at Hollywood, Florida for Estates, by using a minimum of 1,250,000 cubic yards of fill. The contract provided for a unit price of 45 cents per cubic yard of fill. Teer stopped operations in July, 1961, after placing 275,936 cubic yards of fill, and sued Estates for rescission of the contract plus recovery on quantum meruit, claiming misrepresentations by Estates as to the amount of 'hard' digging, and also claiming mutual mistake of fact as to the nature of the soil. Estates impleaded Teer's surety, United States Fidelity & Guaranty Company, and counterclaimed for damages, interest and attorney fees, on the ground that Teer had breached its contract.

After Teer stopped work, Estates entered into a new contract with Arundel Corporation to complete the dredging and filling at a unit price of 62.5 cents per cubic yard.

At the first trial, the district court found that Teer's claims were without merit, and that Estates was entitled to recover on its counterclaim and against Teer's surety. These holdings were affirmed by this Court, but the case was reversed and remanded because further proof was needed to determine the amount of damages to which Estates was entitled, and also because the district court awarded attorney fees to Estates in excess of the maximum permitted by Florida law. With respect to the question of the proper amount of damages, this Court stated:

'Yet, there is no proof in the record as to how much fill, if any, Arundel actually delivered, or whether its price of 62.5cents per cubic yard was the best obtainable after diligent efforts to mitigate thedamages had been made by Estates. Moreover, whereas the Teer contract recited that 470 acres were to be filled, the proof showed that Estates actually owned only 72 acres and had a purchase option on 97 more, a total of 169 acres. There was no evidence as to what rights or obligations Estates had as to the remaining 301 acres.' (324 F.2d 669, at 671)At the second trial, the district court found that Arundel's price of 62.5 cents was the best obtainable after diligent efforts to mitigate the damages had been made by Estates. It was also established that the contract with Arundel had been completed, and that Estates had paid Arundel for all fill delivered at the rate of 62.5 cents per cubic yard. The parties stipulated that Arundel had actually delivered 984,536 cubic yards of fill on the 470 acres; that Teer delivered 275,936 cubic yards, or a total of 1,260,475 cubic yards, an excess of 10,475 cubic yards over the 1,250,000 cubic yards called for by the contract between Estates and Teer.

Estates attempted to show at retrial that it had been given a ten-year oral option to purchase the 301 acres mentioned above from Mailman Brothers (the owners of the 301 acres, and the persons who had sold or optioned the other acreage to Estates). The district Court, however, found that Estates had failed to establish the existence of any such oral option. The court then awarded Estates the amount of $63,158.90, which was the difference between the Teer price and the Arundel price for the fill deposited by Arundel on the 72 acres owned by Estates and the 97 acres under written option to Estates. The court did not allow Estates' claim for damages with regard to fill placed by Arundel on the remaining 301 acres. When interest was added to the $63,158.90, the total awarded Estates was $74,527.50. The court then allowed Estates $9,250.00 as attorney fees, as being within the 12 1/2% Limitation imposed by Section 627.0905(2) Florida Statutes, F.S.A. From this judgment, both sides now appeal.

It is contended by Teer on appeal that the provisions of the contract between Estates and Arundel differed substantially from those in the contract between Estates and Teer, and that in failing to offer Teer the opportunity to rebid with Arundel under the modified plan, Estates failed to properly mitigate damages.

This contention was considered by the district court, and while there is a conflict in the testimony, there is evidence that Teer refused to negotiate a price to complete the contract, and that Teer insisted on 90 cents a yard to finish the contract. The trial court disposed of Teer's contention by stating:

'I am less impressed with the after default-- after suit for fraud and misrepresentation-- claim now made by Teer that he could have completed on the same basis as Arundel than I am impressed with his statement just before, at the time of and soon after default and suit, that on advice of counsel they would stop work and litigate.'

We agree with the district court, and affirm its finding of diligent mitigation by Estates.

Concerning the finding by the district court that Estates failed to establish the existence of a valid oral option to purchase the 301 acres from Mailman Brothers, we feel that such finding cannot be said to be clearly erroneous. The question remains, however, whether that finding is sufficient to dispose of Estates' claim that it is entitled to recover the difference between the Teer contract price and the Arundel price for the fill deposited by Arundel on the 301 acres. (It is conceded by Estates that it is limited to claim damages in the sum of $170,461.20, although it paid Arundel more than that amount, because Arundel deposited 10,475 cubic yards of fill in excess of the 1,250,000 cubic yards required by the Teer contract.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
353 F.2d 485, 1965 U.S. App. LEXIS 3955, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hollywood-golf-estates-inc-v-nello-l-teer-company-and-united-states-ca5-1965.