Southern Surety Co. v. American Const. Co.

36 S.W.2d 212
CourtTexas Commission of Appeals
DecidedMarch 4, 1931
DocketNo. 1386-5564
StatusPublished

This text of 36 S.W.2d 212 (Southern Surety Co. v. American Const. Co.) is published on Counsel Stack Legal Research, covering Texas Commission of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Surety Co. v. American Const. Co., 36 S.W.2d 212 (Tex. Super. Ct. 1931).

Opinion

HARVEY, P. J.

This is a suit brought by the American Construction Company against Oswald J. Las-sig and his surety, 'the Southern Surety Company, on a surety bond.

The construction company was the contractor for the construction of the Herman Hospital in Houston. On July 26, 1923, the company sublet to Lassig a portion of the work, consisting of the supplying of stone for the construction of the building; and the construction company and Lassig entered into the' contract which is involved in this suit. A bond was given to the construction company by Lassig, as principal, and the Southern Surety Company, as surety. The condition of the bond reads: “Now, therefore, the condition of the foregoing obligation is such that if the said principal shall well and truly indemnify and save harmless the said obligee from any pecuniary loss resulting from the breach of any of the terms, covenants and conditions of said contract on the part of said principal to be performed, then this obligation shall be void; otherwise to remain in full force and effect in law.”

Under the contract secured by this bond, Lassig was bound to supply the construction company with approximately 10,000 cubic feet of finished and carved stone. The stone was required to be delivered on the building site, within 160 working days from the date of the contract, at the rate of not less than 2,000 cubic feet per month, beginning August 1, 1923. The contract between Lassig and the construction company provided for certain advancements of money to be made by the company to Lassig in order to enable him to carry on the work. These advancements were duly made by the company as called for by the contract: The contract' also required Lassig to furnish certain setting drawings and models to be used by him in doing the work. ' He procured the construction company to prepare these setting drawings and models for him. The construction company sues herein for the amount of said advancements and the value of the setting drawings and models,- and also for stipulated damages for delay in performance of the work. Las-sig, in his answer to the suit, set up a cross-action against the construction company for damages alleged to have been suffered by him as a result of alleged wrongful acts of the construction company in wantonly condemning and rejecting a large quantity of stone in November and December of 1923, which Lassig had finished and prepared for delivery. These alleged wrongful acts of the construction company are also set up as a defense to the company’s suit. The- Southern Surety Company entered various defenses against liability under the bond, which will be noticed further on. The case was tried to a jury, and upon their verdict on special issues, and the independent fact findings of the trial court, that court rendered judgment that the construction company take nothing, and that Lassig recover damages on his cross-action, in an amount stated in the judgment. The Court of Civil Appeals [20 S.W.(2d) 797] reversed this latter' part of the judgment and remanded the cause for a retrial of Lassig’s cross-action. The latter court also reformed that part of the judgment which denied a recovery by the construction company, so as to allow a recovery by that company against Lassig, of the amount of the said advancements and the value of the setting drawings and models, and, as so reformed, the judgment of the trial court respecting the construction company’s suit was affirmed. In so far as the trial court’s judgment was in favor of the Southern Surety Company, it was reversed by the Court of Civil Appeals, and the cause, as between the surety company and the construction company, was remanded. ' These two companies, respectively, applied for writ of error, and both applications were granted.

Article 4 of the Lassig contract provides as follows: “Should the sub-contractor (Las-sig) at any time * * * fail in the performance of any of the terms, stipulations and ’ agreements obligatory upon said subcontractor, contained in this 'agreement, then in such event, at the option of the contractor (the Construction Company), if such failure be continued four days after notice in writing to the subcontractor, or anyone representing it on the work, such notice stating the nature of the violation of the contract, the contractor (the Construction Company) may proceed thereupon to complete the work, under the terms of said contract, at the cost and expense of the said sub-contractor, or, at the option of the contractor, the work may be re-sublet at the cost and expense of said subcontractor. ⅜ * * ”

Lassig failed to supply the stone at the rate of 2,000 cubic feet per month, and, while he was in default in this respect, the Construction Company, on November 19, 1923, wrote and delivered a letter to Lassig and delivered a copy thereof to the Southern Surety Company. In this letter the construction company gave notice of Lassig’s default, and declared that the construction company “had elected to proceed to supply the stone for the Herman Hospital, which under your contract of July 26, 1923, you agree to furnish. * * * The work will be completed at your cost and expense. We will either supply the stone ourselves or resublet the contract, as to us may, under all the circumstances, seem most advantageous.”

[214]*214Upon receiving this letter, Lassig immediately appealed to the construction company to allow him to continue work under the contract in an effort to supply the required amount of stone. The construction company allowed him to do this, and thereafter he supplied a small quantity of stone in November; about 200 cubic feet in December; about 53 cubic feet in January; and none thereafter. The total quantity of stone supplied by Las-sig under the contract was 1,442.6 cubic feet. On February 15, 1924, which was some 10 clays before 160 working clays from the date of the contract had elapsed, the construction company wrote another letter to Lassig, a copy of which was delivered to the Southern Surety Company. The body of this letter reads as follows:

“This is to serve formal notice to you that under terms of our contract with you dated July 26th, 1923, wherein you were to furnish the cut stone for Hermann Hospital building which we have under contract with the Trustees of Hermann Estate, is now cancelled because of your failure and default in the carrying out of the terms of the contract, you having failed to supply the stone at the time and in the quantities required by the contract.
“We gave you notice of the cancellation of this contract on November 19th, 1923, but since that time we accepted and paid you for a small amount of material which you had on hand and in the course of manufacture for the purpose of showing you every consideration possible. The work will be completed at your cost and expense as provided in the contract.”

The construction company thereupon proceeded, on the same day, to enter into a contract with the Bedford-Carthage Company by which the latter became bound to supply and did subsequently supply the remainder of the designated quantity of stone called for by the Lassig contract, at about the same cost as if Lassig had completed his contract.

The surety company contends that it was released from its engagement as surety because of a change in the terms of the Las-sig contract in this: After the Lassig contract was made, and the surety bond was given, the construction company, with Las-sig’s consent, made progress payments to the latter, while he was going forward with the work, in amounts less than stipulated in the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Axman
234 U.S. 36 (Supreme Court, 1914)
Smith v. . Molleson
42 N.E. 669 (New York Court of Appeals, 1896)
American Const. Co. v. Lassig
20 S.W.2d 797 (Court of Appeals of Texas, 1929)
American Bonding Co. v. United States
167 F. 910 (Ninth Circuit, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
36 S.W.2d 212, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-surety-co-v-american-const-co-texcommnapp-1931.