* Writ of error granted. *Page 798 Appellant, American Construction Company, brought this suit against appellees, Oswald J. Lassig and Southern Surety Company, to recover on debt and for damages for breach of a building contract. Appellant was contractor for the construction of a hospital building in the city of Houston. It sublet the stonework, estimated at 9,600 cubic feet, to appellee Lassig for $48,000. Lassig was to deliver 2,000 cubic feet of stone per month, beginning with August 1, 1923, and to continue his deliveries at that rate until the work was finished. He was given, however, 160 days in which to finish the work under his contract, and was to pay liquidated damages at the rate of $50 per day for each and every day his part of the work was unfinished after the expiration of the 160 days. Lassig executed to appellant a bond with appellee Southern Surety Company as his surety, to secure the performance of his obligations under the contract. On the ground that Lassig had defaulted in delivering the required stone, appellant, on the 15th of February, 1924, canceled his contract. Lassig had not in any month while his contract was in force delivered the amount of stone required of him, but from the inception of his contract until the time it was canceled delivered only 1,442.6 cubic feet of stone, for *Page 799 which appellant paid him at the rate of $4 per cubic foot.

After canceling Lassig's contract, appellant relet the unfinished work to another contractor, paying therefor practically the difference between the original contract price of $48,000 and the amount paid Lassig for the 1,442.6 cubic feet actually delivered. Appellant was delayed in the construction of the building, and was forced thereby to pay $5,035 in extra labor bills, which it charged against Lassig. Appellant also claimed liquidated damages against Lassig for 150 days at $50 per day. At the inception of the contract, appellant advanced Lassig $10,000, and furnished him, at his request, the necessary setting drawings and models. On the facts stated, appellant instituted this suit against appellee Lassig and his surety, praying for judgment for the $10,000 advancement, the liquidated damages in the sum of $7,500, extra labor expense in the sum of $5,035, the value of the setting drawings in the sum of $1,100, and of the models in the sum of $1,167.28. Appellant also prayed for interest on these several items. Lassig answered by general demurrer, general denial, and by way of cross-action that appellant wrongfully breached the contract, causing him damages in the loss of profits in the sum of $12,000. The Southern Surety Company answered as did Lassig, and, in addition, pleaded unauthorized novations in the contract on which it was surety.

The trial was to a jury, and, on appellant's demands against Lassig, the Jury found against its plea for liquidated damages and for the extra labor expense, that is, the extra labor expense was not proximately caused by any delay on the part of Lassig in furnishing the stone as called for in the contract. We affirm these findings as having support in the evidence. We say further, on the question of liquidated damages, that this issue was foreclosed against appellant by the terms of the contract itself, in that it was therein provided that liquidated damages were to be allowed only after the expiration of the 160 days, and, as appellant canceled the contract before the 160 days expired, no liquidated damages were recoverable. The judgment of the trial court denying appellant recovery on these two items is affirmed.

The jury fixed the value of the setting drawings at $720, and the trial court, on the undisputed evidence, fixed the value of the models at $1,167.28. In its judgment the trial court awarded appellant recovery for these two items in the sums stated, with interest as pleaded, and, as no assignment is before us attacking the correctness of the judgment as to these two items, it is affirmed in this respect.

Without dispute, it was shown that appellant advanced Lassig $10,000, on which Lassig had paid, under the terms of his contract, 15 per cent. of the value of the stone delivered, which the trial court found to be $722.41, and no assignment is before us against this allowance. This sum was allowed as a credit against the $10,000, leaving a balance of $9,277.59, which was awarded to appellant in the judgment of the trial court, but without interest. Appellant insists that it should have been awarded interest on this item from the 15th of February, 1924. This assignment is sustained. It was provided in the contract between appellant and Lassig that "in the event this contract is cancelled, any unpaid balance of said Ten Thousand ($10,000.00) Dollars advanced shall then be immediately due and payable to contractor." The trial court's judgment as to the item of $9,277.59 is reformed by allowing interest thereon from the 15th of February, 1924, at 6 per cent. per annum, and, as so reformed, affirmed.

Appellant challenges Lassig's pleadings in his cross-action as being bad on general demurrer. These assignments are overruled, but, if the objections to the pleadings should be presented on another trial as special exceptions, they should be sustained. Lassig's cross-action was bad on special exceptions if properly presented, but good on general demurrer.

Lassig's cross-action was based on the theory that appellant breached the contract by failing and refusing to receive stone properly prepared and properly delivered by him. The facts were as follows: Lassig was very slow in delivering the stone. One time in the early part of the contract the architect refused a large quantity of stone that had been delivered, of which Lassig made complaint. The architect and appellant then agreed that a man named Ulrich, one of appellant's servants, should be detailed to work with Lassig and inspect Lassig's stone before it was prepared for the building and before it was delivered. Ulrich entered upon the discharge of this duty, with Lassig's consent, about October. The relations between him and Lassig were not pleasant. At one time, after Lassig had prepared a large quantity of stone, Ulrich made a wholesale rejection of all of it, offering no explanation of his action, but the issue was raised that he was arbitrary, unreasonable, and wilful in his conduct. The jury found that Ulrich rejected stone that was according to the samples furnished the architect; that this rejection was the cause of some of the delay by Lassig in delivering the stone, and that this delay extended from the "time of the wholesale rejection in November, 1923, to cancellation of contract."

The jury found further that Ulrich rejected the stone with knowledge that it was according to the samples furnished the architect, and that this rejection prevented Lassig from completing the performance of his contract. The jury further found that Ulrich instructed Lassig to deliver the stone in different quantities than that specified in the contract, that Lassig delivered the stone as required by *Page 800 Ulrich, and that Ulrich was authorized to instruct Lassig to make the deliveries as actually made by him. The jury further found that it would have reasonably cost Lassig $33,600 to furnish the stone required by his contract. The jury's findings on all the issues submitted to it have abundant support in the evidence. On this last finding Lassig would have had a profit on his contract of $14,400 had he been permitted to finish it, but, as he limited his damages by his plea to $12,000, the trial court limited his recovery against appellant to that sum, and found against appellant for that sum.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ford v. Thomas D. MacKey Co.
70 S.W.2d 1021 (Court of Appeals of Texas, 1934)
Southern Surety Co. v. American Const. Co.
36 S.W.2d 212 (Texas Commission of Appeals, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
20 S.W.2d 797, 1929 Tex. App. LEXIS 964, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-const-co-v-lassig-texapp-1929.