First Nat. Building Co. v. Vandenberg

1911 OK 383, 119 P. 224, 29 Okla. 583, 1911 Okla. LEXIS 346
CourtSupreme Court of Oklahoma
DecidedNovember 14, 1911
Docket763
StatusPublished
Cited by9 cases

This text of 1911 OK 383 (First Nat. Building Co. v. Vandenberg) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First Nat. Building Co. v. Vandenberg, 1911 OK 383, 119 P. 224, 29 Okla. 583, 1911 Okla. LEXIS 346 (Okla. 1911).

Opinion

KANE, J.

This was a suit commenced by the defendant in error, plaintiff below, against the plaintiff in error, defendant below, to recover damages for the breach of a building contract and to foreclose a mechanic’s lien in connection therewith. The plaintiff was the contractor and the defendant the owner of the proposed building, and hereafter they will be so designated. It seems that sometime during the progress of the work the owner exercised a privilege conferred upon it by article 5 of the contract, which reads as follows:

“Should the contractor at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or of materials of the proper quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements herein contained, such refusal, neglect or failure being certified by the architect, the owner shall be at liberty, after five (5) days’ written notice to the contractor, to provide any such labor or materials, and to deduct the cost thereof from any money then due or thereafter to become due to the contractor under this contract; and if the architect shall certify that such refusal, neglect or failure is sufficient ground for such action, the owner shall also be at liberty to terminate the employment of the contractor for the said 'work and to enter upon the premises and take possession, for the purpose of completing the work included under this contract of all materials, tools, and appliances thereon, and to employ any other person, or persons, to finish the work, and to provide the materials therefor; and in case of such discontinuance of the employment of the contractor he shall not be entitled to receive any *585 further payment under this contract until the said work shall be wholly finished, at which time, if the'unpaid balance of the amount to be paid under this contract shall exceed the expense incurred by the owner in finishing the work, such excess shall be paid by the owner to the contractor, but if such expense shall exceed such unpaid balance, the contractor shall pay the difference to the owner. The expense incurred by the owner as herein provided, either for furnishing materials or for finishing the work, and any damage incurred through such default, shall be audited and certified by the architect, whose certificate thereof shall be conclusive upon the parties.”

The contractor alleged, in substance, that the owner, acting in collusion with the architect, fraudulently, corruptly, and in violation of the terms of said contract, and without giving him any notice, and without any default on his part, forcibly took charge of said building and the construction of same, and notified said contractor that it had terminated said contract, thereby causing the contractor damage in the sum of $8,617.17 for labor and material furnished and used by him in the construction of said building; by loss of prospective profits, in the sum of $12,-015.17; and he prayed that he be given judgment for the sum of $10,000, or so much thereof as might be necessary to satisfy all claims or demands made against plaintiff by reason of certain subcontracts which he had made and entered into with various persons for the furnishing of materials and labor in the construction of said building, and that he be decreed a lien upon the lots upon which said building was erected to secure the payment of said judgment.

The answer of the defendant admitted the execution of the contract, but denied that there was any fraud or collusion with the architect. There were other allegations to the effect that the defendant acted in accordance with the terms of said contract between the contractor and the owner; that said owner took charge of said work and materials and appliances thereon and proceeded to employ properly skilled workmen and to purchase proper and suitable materials, and proceeded with the construction of said building in accordance with the plans and specifica *586 tions of said work; that it provided whatever labor and material .essential to the work that it was bound to furnish under said contract between plaintiff and defendant in such a manner and at such times as not to delay the progress of the work and fully in accordance with the terms of said contract; that it paid plaintiff all estimates made upon the said work by the said architect at the time and in amounts specified by said estimates, and thereby paid plaintiff the sum of $16,349.75, being the whole amount due plaintiff at the time plaintiff abandoned said work, and up to and including the present time.

After the issues were joined, the court referred the cause to a master in chancery, who found that the contractor was entitled to recover against the owner for labor and materials furnished up to the time of the forfeiture of the contract, in the sum of $5,617.21; for certain materials purchased by the contractor which had not been paid for by him and which were taken possession of by the owner and used in the construction of said building, in the sum of $6,739.29; for certain materials belonging to the contractor which the owner took possession of and appropriated to its own use, in the sum of $297.20; and for anticipated profits which the contractor would have been entitled to if he had completed the building, in the sum of $5,000. The order of reference was made by the court upon its own motion and the report returned prior to statehood. After statehood the report was approved by the court in all particulars and judgment rendered in accordance with the recommendations of the master. To reverse this judgment this proceeding in error was commenced. •

Several assignments of error are directed to alleged error of the court in referring the cause to the master without the consent of the owner, and error of the master based upon rulings during the trial that involved the question of abuse of discretion on his part. As the case will have to be reversed upon questions that involve its merits, and as those errors are such as will probably not occur again upon a new trial, we will not further notice them.

*587 Upon the question of the breach of the contract, the master found that:

“The defendant First National Building Company, the owner of the building, was guilty of a breach of the contract made with plaintiff contractor, for the following reasons: 1st. Because it failed to make and pay the estimates at the time, in the manner and for the amounts provided for by the terms of the contract. 2nd. Because the defendant building company terminated the contract with the plaintiff contractor, and took possession of the building without right. 3rd. Because the plaintiff contractor had substantially complied with the terms of the contract, up to the date that the defendant took possession of the building, and the reasons assigned by the architect for declaring a forfeiture of the contract were untrue and known to be so by the architect.”

We believe this finding was supported by sufficient evidence. Under such a state of facts the primary damage is the amount of the contractor’s loss, and this loss must consist of two heads or classes of damage — actual outlay and anticipated profits. But failure to prove profits will not prevent the party from recovering his loss and outlay and expenditures. If he goes also for.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

O'Dell v. Nelson & Myers
1938 OK 291 (Supreme Court of Oklahoma, 1938)
Foothill Ditch Co. v. Wallace Ranch Water Co.
78 P.2d 215 (California Court of Appeal, 1938)
Marland Refining Co. v. Dunigan
1924 OK 926 (Supreme Court of Oklahoma, 1924)
Muskogee Electric Traction Co. v. Fore
1920 OK 88 (Supreme Court of Oklahoma, 1920)
Elwood Oil & Gas Co. v. McCoy
1919 OK 61 (Supreme Court of Oklahoma, 1919)
Letcher v. Maloney
1918 OK 231 (Supreme Court of Oklahoma, 1918)
Findley v. State
1917 OK CR 37 (Court of Criminal Appeals of Oklahoma, 1917)
National Surety Co. v. Board of Edu. of City of Hugo
1917 OK 109 (Supreme Court of Oklahoma, 1917)
Muskogee Co. v. Yahola Sand Co.
1916 OK 1061 (Supreme Court of Oklahoma, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
1911 OK 383, 119 P. 224, 29 Okla. 583, 1911 Okla. LEXIS 346, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-nat-building-co-v-vandenberg-okla-1911.