Starr v. Gregory Consolidated Mining Co.

6 Mont. 485
CourtMontana Supreme Court
DecidedJanuary 15, 1887
StatusPublished
Cited by2 cases

This text of 6 Mont. 485 (Starr v. Gregory Consolidated Mining Co.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Starr v. Gregory Consolidated Mining Co., 6 Mont. 485 (Mo. 1887).

Opinion

MoLeaby,- J.

This suit was brought by the respondent against the appellants to recover the balance of twenty thousand dollars ($20,000) alleged to be due on a contract for the erection of smelting works at the mines of the defendant company, and to foreclose a builder’s and mechanic’s lien thereon fixed to secure the same. The case was tried below before a jury, and, after a verdict and judgment in favor of the plaintiffs for fifteen thousand dollars ($15,000) and interest, an appeal was duly taken therefrom to this court, alleging errors in the introduction and exclusion of evidence, in overruling the motion for a nonsuit, and in giving and refusing instructions to the jury. We will consider these specifications of error in a little different order from that pursued in the briefs of counsel, or in the record of the case presented.

1. As to overruling the motion for a nonsuit. This motion is based on the ground (1) that the sums of money sued for were, according to the contract, to be paid in sixty and ninety days after the acceptance of the mill by the defendant, and that no acceptance had been proven; and (2) that the contract provided that the mill was to have been completed within four months from the date of the contract, and that time was of the essence of the contract, and that no legal excuse for the failure to complete the mill within the time specified was shown.

The evidence in regard to the acceptance of the mill is clear and explicit enough, if Hesse had any authority to make the acceptance. His letter of the 18th of April, 1884, is unequivocal, and to the point. Nothing could be more definite. His testimony is also to the same effect as is the deposition of Halter. Then this objection turns on the authority of Hesse to make the acceptance. His authority also appears from the evidence. It is shown that he was superintendent of the company’s works; that he prepared the plans and specifications for the concentrating mills; that numerous changes in the machinery were ordered by him, and wei’e made to meet his views, and that the extra charges [487]*487therefor were paid for by the'company; that the president and the assistant general manager of the company had said to the agent of the ./Etna Iron Works, the plaintiff’s firm, that whenever the mill was acceptable to Hesse, it would be acceptable to the company; and that Hesse, after writing the certificate of acceptance, had shown a letter-press copy of it to Child, the assistant general manager of the company, and he had raised no objection to it whatever. All these facts, taken together, clearly show the authority of Hesse to accept the concentrating mill on behalf of the defendant company. Corporations, in the nature of their constitution, must act through their officers and agents. There is no other mode possible in which they can act. The act of any officer is the act of the company, and even the acts of very many mere agents are considered the acts of the company. The authorities are numerous and uniform on this point. Merchants’ Bank v. State Bank, 10 Wall. 644 et seq.; Wood’s Field on Corp. §§ 181-183, 220; Tayl. Corp. §§ 193, 201.

The other ground relied upon for a nonsuit has no better foundation in fact. The language of the contract on this point reads: The whole mill, with all machinery, shall be completed and delivered in perfect running order within four (1) months from date; provided, the lumber required to be used in constructing the building and placing the machinery therein is delivered on the ground at Gregory, aforesaid, at the price of twenty-five dollars ($25) per thousand feet within forty (10) days after the receipt of the bill for said lumber by H. W. Child, representing said party of the second part.” This, the only limitation of time made in the contract, was conditional, on the delivery of the requisite lumber within forty days after the reception of the bill. The evidence clearly shows that this condition was not complied with by the defendant company, and thereby the restriction as to time became inoperative, and to complete the works within a reasonable time was all that was [488]*488required of the plaintiff. This he did. as far as the evidence shows, and no damage accrued to the defendant from any delay. Time was in no sense of the essence of this contract, and the defendant company, being itself in default, has no right to complain of any delay on the part of the plaintiff in this cause. The motion for nonsuit was very properly overruled.

2. But the admission of improper evidence is complained of by the appellant. So far as relates to the overruling of the motion to suppress the deposition of 0. ITesse, the bill of exceptions is based on the notice given to take the deposition, and the notice nowhere appears in the transcript, so that this specification requires no further consideration. When a bill of exceptions is taken to any ruling of the court, everything necessary to sustain the bill of exceptions must be contained in the transcript; otherwise the bill of exceptions is incomplete.

The objections made to the testimony of the witness Malter are insufficient, many of them frivolous, and none-of them well taken. As to the agency or authority of 0. Hesse to accept the concentrator, it has been repeatedly held by this court that it is within the discretion of the trial court to direct the order of proof. It was not necessary that the authority of Hesse should be shown before the letter or certificate of acceptance signed by him was introduced in evidence. If this was done afterwards, the appellant has-no reason to complain. That it was so done amply appears from the testimony. The objections made to the testimony of the witness Hesse are in fact not borne out by the record, and are not in any case well founded.

3. The question asked by the appellant of the witness-Child was properly excluded by the court for the reasons stated in the record. It was not a matter material to this case as to what time the machinery arrived at Helena or Gregory. No stipulation in regard thereto is contained in the contract, and no time for the completion of the mill [489]*489itself was agreed upon, except in the event that the lumber should be delivered at a certain time by the defendant, which was not done, as has been already stated herein.

Appellant further insists that the court erred in refusing to permit it to prove the daily expense incurred by it while said mill stopped running. This position seems to be based on the claim that the works were not completed within four months from the date of the contract, which we have already shown the plaintiff was not bound to do, because the lumber was not delivered within the forty days specified. There was no evidence introduced to show that the concentrator was not completed within a reasonable time, and the plaintiff not having been shown to have been in default, there was no predicate laid for proof of any damages on the part of the defendant company. This was presumably the reason for the exclusion of the evidence by the trial court, though the record is silent as to that. Nor does the exception state the reasons alleged by the appellant for its exception, and the same might well be disregarded by this court on that account. Eut we have seen fit to notice it to this extent.

The court at the trial correctly excluded the letter written by Child to the plaintiff, and the letters written by Hesse to Child. It is an elementary principle that neither party can thus make evidence for himself.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Noyes v. Clifford
94 P. 842 (Montana Supreme Court, 1908)
Long v. Pierce County
61 P. 142 (Washington Supreme Court, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
6 Mont. 485, Counsel Stack Legal Research, https://law.counselstack.com/opinion/starr-v-gregory-consolidated-mining-co-mont-1887.