Texas & St. L. Ry. Co. v. Rust

19 F. 239
United States Circuit Court·Decided October 15, 1883·Published·Cited by 13 cases

Opinion

Caldwell, J.,

(charging jury.) On the twenty-second day of April, 1882,the parties entered into a written contract for the construction, by the defendants for the plaintiff, 'of a railroad bridge across the Arkansas river, at the price of $305,000. Differences arose between them as to their relative rights, duties, and obligations under the contract, which resulted in the institution of this suit. The matters in controversy between them can best be brought to your attention by stating the defendant’s claims first, which may be stated thus:

[240]*2401. Contract, price for bridge, ----- $305,000 00

2. For sinking'piers, other than center pier, below 60 feet, at $200 per vertical foot, as per contract, - 1,000 00

3. Extra for sinking center pier 10 feet below 60 feet, 15,000 00

4. Extra for draw protection, ----- 21,530 00

5. Extra for iron stringers, ----- 2,646 00

6. Extra for two shore abutments, - 1,600 00

7. Extra for additional material for piers sunk below 60 feet, 1,900 00

8. Extra for trestle approaches, - 911 70

$349,587 70

Against this sum the defendants admit credits as follows:

1. For reduced height of piers, $ 8,100 00

2. For material and labor to complete bridge after defendants quit work, - -' - - - - 6,000 00

3. Payments on estimates, ----- 267,959 79

$282,059 79

This makes the balance claimed by the defendants as due to them from the plaintiff $67,527.91. The parties agree as to the amount paid defendants on estimates, L e., $267,959.79. The items in the defendants’ accounts which the plaintiff disputes are, the charge for sinking center pier below 60 feet in excess of $200 per vertical foot; the whole of the charge for a draw protection; the whole of the charge for iron stringers for’ draw span; the whole of the charge for extra materials for piers sunk below 60 feet; and the charge for shore abutments is said to be excessive to the amount of $200.

The plaintiff’s claims against the defendants may be stated thus :

1. Payments made on estimates, - $267,959 79

2. Weekly reduction in price of bridge for its non-completion, 39 ' weeks and 4 days, at $1,000 per week, - - 39,570 88

3. Claim for general damages for failure to complete bridge, - 200,000 00

4. For money expended in completing bridge after defendants quit work, ------ 15,075 61

5. Reduction in contract price of bridge on account of reduced height of piers, 8,100 00

The defendants dispute the plaintiff’s claim for damages, including the $1,000 per week specified in the contract, on the ground that plaintiff waived the same; they admit their liability for what it cost the plaintiff to complete the bridge after they quit work upon it, but they say the amount charged therefor above $6,000 is excessive. The provisions of the contract, and the law applicable to the matters in controversy between the parties, will now be stated in their order. The contract contains this provision:

“In case of non-completion of the bridge upon November 1, 1882, or providing a crossing for trains by said date, then in such event the sum of $1,000 per week for the period of time such completion or provision for crossing of trains is delayed shall be deducted from said contract price; and in like manner, should the bridge be completed at an earlier date than November 1, 1882, then in such event the sum of $1,000 per week shall be added, to [241]*241said contract price, for the period by which said fixed date of completion shall be anticipated.”

It is a conceded fact in the case that the bridge was not completed so trains could cross on it until the fourth day of August, 1883, and that no other mode of crossing trains was provided by the defendants before that time; and the plaintiff claims that, under the clause of tho contract I have quoted, it is entitled to a reduction of §1,000 por week in the contract price of the bridge, from the first of November 1882, to the fourth day of August, 1883, when the bridge was so far completed as to admit of the passage of trains over it. It is open to parties when they make a contract to agree on the amount to be paid or allowed by either to the other as compensation for a breach of it. Sometimes stipulations providing for the payment of a fixed sum for a breach of contract are termed penalties, and go for nothing for reasons not necessary to be stated here. But where tho damages, for the breach of the contract are uncertain in their nature, or difficult to be proved with any degree of accuracy, and the amount fixed by the contract is not grossly in excess of a probably just compensation, that sum will be taken as the true amount of the damages, and is called in legal parlance liquidated damages. •'

The difficulty of ascertaining, with any degree of certainty, the damages the plaintiff sustained, is made apparent by the testimony of the witnesses in the case, who estimated the damages from half a million of dollars down to a comparatively small sum. You will observe the contract does not provide for the payment of a large sum in gross for a failure to have the bridge completed on the day named, or for any mere technical breach of the contract, If it had done so a different question would be presented. The damages fixed by the contract do not accrue for failure to complete the bridge on a given day, but for “non-completion of the bridge, or of'providing a crossing for trains by said date,” which latter alternative could have been complied with by providing a boat to transfer trains; and upon failure to do either, the damages are not given in one gross sum the day the default accrues, but are graduated according to the length of time the breach continues, and are not excessive or unreasonable in amount. You are therefore instructed that tho contract fixed the amount of the defendants’ liability for non-completion of the bridge, or failure to provide a crossing for trains by the first of November, 1882, and afterwards. That amount is $1,000 per week from that date until a crossing for trains was provided. As the defendants seem to have acted in good faith, and the delay resulted from causes beyoud their control, the plaintiff will not he permitted to show the damages were more, nor the defendants that they were less, than the stipulated amount. Nor does the fact, if it is a fact, that tho defendants were unexpectedly retarded in the work on the bridge by high water, sickness of hands, and sunken logs, encountered in sinking the piers, excuse them from performance of their contract, or from any of its [242]*242obligations. Against tbe consequences of such casualties they might have guarded by a provision in the contract. Not having done so, it is not in the power of the court or jury to relieve them. Dermott v. Jones, 2 Wall. 1.

The learned counsel for the plaintiff has argued that this clause of the contract relates to the price to be paid for the bridge, which it is said is made to depend on the time of its completion, and that the $1,000 per week is a “deduction from the contract price” of the bridge, and not damages for its non-completion. In construing a contract every part of it must be taken into consideration.

Free access — add to your briefcase to read the full text and ask questions with AI

Texas & St. L. Ry. Co. v. Rust, 19 F. 239 (uscirct 1883).

19 F. 239 (Texas & St. L. Ry. Co. v. Rust) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Continental Oil Company
364 F.2d 516 (Tenth Circuit, 1966)
Sanitary Farm Dairies, Inc. v. Gammel
195 F.2d 106 (Eighth Circuit, 1952)
East Arkansas Lumber Co. v. Swink
194 S.W. 5 (Supreme Court of Arkansas, 1917)
Virtue v. Stanley
151 P. 270 (Washington Supreme Court, 1915)
Caldwell v. Pierce
157 S.W. 692 (Court of Appeals of Kentucky, 1913)
Coal & Iron Ry. Co. v. Reherd
204 F. 859 (Fourth Circuit, 1913)
Kansas City Bridge Co. v. Lindsay Bridge Co.
1912 OK 132 (Supreme Court of Oklahoma, 1912)
Barber Asphalt Paving Co. v. City of Wabash
86 N.E. 1034 (Indiana Court of Appeals, 1909)
Link Belt Engineering Co. v. United States
142 F. 243 (U.S. Circuit Court for the District of Eastern Pennsylvania, 1905)
Wheeling Mold & Foundry Co. v. Wheeling Steel & Iron Co.
51 S.E. 129 (West Virginia Supreme Court, 1905)
Doddridge v. Doddridge
56 N.E. 112 (Indiana Court of Appeals, 1900)
Bailey v. Bond
77 F. 406 (Ninth Circuit, 1896)
Reichenbach v. Sage
43 P. 354 (Washington Supreme Court, 1896)