Kansas City Bridge Co. v. Lindsay Bridge Co.

1912 OK 132, 121 P. 639, 32 Okla. 31, 1912 Okla. LEXIS 214
CourtSupreme Court of Oklahoma
DecidedFebruary 6, 1912
Docket1575
StatusPublished
Cited by18 cases

This text of 1912 OK 132 (Kansas City Bridge Co. v. Lindsay Bridge Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kansas City Bridge Co. v. Lindsay Bridge Co., 1912 OK 132, 121 P. 639, 32 Okla. 31, 1912 Okla. LEXIS 214 (Okla. 1912).

Opinion

Opinion by

SHARP, C.

On May 28, 1907, the Kansas City Bridge Company, of Kansas City, Mo., a corporation, made and entered into a written contract with the Lindsay Bridge Company, of Lindsay, Ind. T., a corporation, for the construction of three bridges across the Washita river near Lindsay. The provisions of said contract, out of which this controversy has arisen, are as follows:

“The said first party agrees to have the substructures and superstructures completed on or before October the first, 1907, provided that if by reason of the violence of the elements, or from cause unavoidable and beyond the control of the first party, it should be impossible to perform said work within the time limited, then the time for the fulfillment of this contract shall be extended for a period not less than that caused by such delays.
“And it is agreed by and between the parties hereto that party of the first part is to furnish bond to party of the second part in the sum of $5,200, conditioned that party of the first part will well and truly perform its part of this contract, and party of the second part is to furnish security for the payment of this contract price herein specified, satisfactory to party of the first part.
“And it is further agreed by party of first part that, if the three spans are not completed in accordance with the plans and specifications hereto attached within four months from the date of the approval by party of the first part of the security of the party of the second part, then party of the first part shall pay to party of the second part a penalty of $7.50 each day thereafter until bridges are completed for each of said bridges which are not completed in accordance with the plans and specifications hereto attached within the said four months, and any amount due party of the first part may be deducted by party of the second part from any payment which may at any time become due from party of the second part to party of first part, and, if at the final settlement there shall be greater amount of penalty due party of the second part than the balance then due *33 on the contract price, party of the first part shall pay the party of the second part the difference between said amounts.”

These paragraphs, for convenience, will be numbered 4, 8, and 9, respectively.

Suit was brought to recover a balance of $555 on the contract. Defendant alleged that this balance was originally due plaintiff, but that by reason of the fact that plaintiff had breached said contract there was due said defendant $617.50 liquidated damages, and asked judgment over and against plaintiff in the sum of $62.50. Plaintiff’s testimony being excluded by the court, the jury under the court’s directions returned a verdict in favor of defendant and against plaintiff in the sum of $60.

The assignments of error may all properly be considered under the head: Did the court err in excluding the depositions of plaintiff? These depositions were offered, presumably, for the purpose of showing that the bridges were not completed on or before October 1, 1907, due either to the violence of the elements or from causes unavoidable, and beyond the control of the first party, making it impossible to perform the work within the time limited. Defendant contended that, under the terms of the contract, the plaintiff bound itself at all hazards to complete the bridges on or before October 20th, and that it made no difference what reasons it had for not completing them at that time, that it was liable on the contract for liquidated damages at the rate of $7.50 per day for each bridge not completed by October 20th. There is no dispute as to the time at which the bridges were in fact completed.

The question in this case is whether the plaintiff agreed to pay the defendant the liquidated damages stipulated in the contract during the time that it was delayed in completing its contract by the unavoidable contingencies named in the agreement, and that question must be determined by a fair construction of the contract. The purpose of a written contract is to evidence the terms upon which the minds of the parties to it meet when they make it. Hence the true end of a contractual interpretation is to ascertain that intention, and when it is found, it prevails *34 over verbal inaccuracies, in'apt expressions, and the dry words of the stipulations. Section 4 provides that the party of the first part should have the substructures and superstructures com-, pleted on or before October' 1st, not absolutely, but conditionally. What was the condition? That it be not delayed on account of the elements or from unavoidable causes beyond its control, and, in the event of the occurrence of either or both of such contingencies, the time should be extended for a period not less than that caused by such delay. Section 8 provided, among other things, that the party of the second part should furnish security for the payment of the contract price satisfactory to the party of the first part, while section 9 provided that, if the three spans were not- completed according to plans and specifications attached within four months from the date of the approval by the party of the first part of the security of the party of the second part, then the party of the first part should pay to the second party the penalty of $1’.50 each day thereafter for each bridge not so completed within said four months.

The only real conflict lies in the language used in the first part of section 4, fixing October 1st as the time for the completion of the substructures and superstructures, and that part of section 9 providing that the penalty should attach if the bridges were not completed within four months of the approval of the security. Section 4 expressly provides that, in the event of certain expressed contingencies, the time should be extended. Time for what? The fulfillment of the contract. The contract included the terms of the whole engagement entered into bv the parties, as expressed by their entire writings. Enforced delay, due to the causes mentioned, conferred, by the express terms of the contract, additional time as an equivalent of the time lost. Thus the exact time was four months and two days in which the work was to be completed, unless for the reason named additional time should be required. In fixing the time for the attaching of the penalty, instead of being made to attach October ■1st, it was fixed at four months from the date of the approval of the security. This it is alleged and shown by defendant was *35 furnished June 20, 1907, and presumably was on said date approved by the plaintiff, and, to use the language of the contract, “found satisfactory to party of the first part.” The penalty, then, in no event would attach until four months from June 20th, or October 20th; but, in the event of the happening of one or the other of the contingencies guarded against, then could it be said that the penalty would attach until the first party was in default? This it would be according to defendant’s contention, if, in fact, the bridges, for whatsoever cause, were not completed by October 20th.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aetna Life Ins. Co. v. Home
1943 OK 388 (Supreme Court of Oklahoma, 1943)
Cities Service Gas Co. v. Kelly-Dempsey & Co.
27 F. Supp. 547 (N.D. Oklahoma, 1939)
Phoenix Oil Co. v. Mid-Continent Petroleum Corp.
1936 OK 250 (Supreme Court of Oklahoma, 1936)
Ft. Dearborn Trust & Sav. Bank v. Skelly Oil Co.
1930 OK 196 (Supreme Court of Oklahoma, 1930)
Continental Supply Co. v. Levy
1926 OK 449 (Supreme Court of Oklahoma, 1926)
Frazer v. City of Ardmore
1924 OK 804 (Supreme Court of Oklahoma, 1924)
Barnett v. Merchants' Life Ins. Co.
1922 OK 182 (Supreme Court of Oklahoma, 1922)
Prowant v. Sealy
1919 OK 304 (Supreme Court of Oklahoma, 1919)
Liverpool London Globe Ins. Co., Ltd. v. Biggers
1918 OK 517 (Supreme Court of Oklahoma, 1918)
Gem Oil Co. v. Callendar
1918 OK 269 (Supreme Court of Oklahoma, 1918)
Withington v. Gypsy Oil Co.
1918 OK 236 (Supreme Court of Oklahoma, 1918)
Union Trust Co. v. Shelby Downard Asphalt Co.
1916 OK 160 (Supreme Court of Oklahoma, 1916)
Rogers v. Herndon, County Treasurer
1916 OK 89 (Supreme Court of Oklahoma, 1916)
Wever v. Pioneer Fire Insurance Co.
1915 OK 1046 (Supreme Court of Oklahoma, 1915)
Brown v. Coppadge
1915 OK 1064 (Supreme Court of Oklahoma, 1915)
Rider v. Helms
1915 OK 389 (Supreme Court of Oklahoma, 1915)
Lamont Gas & Oil Co. v. Doop & Frater
1913 OK 558 (Supreme Court of Oklahoma, 1913)
Pacific Mut. Life Ins. Co. of Cal. v. O'Neil
1913 OK 110 (Supreme Court of Oklahoma, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
1912 OK 132, 121 P. 639, 32 Okla. 31, 1912 Okla. LEXIS 214, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kansas-city-bridge-co-v-lindsay-bridge-co-okla-1912.