Lamont Gas & Oil Co. v. Doop & Frater

1913 OK 558, 135 P. 392, 39 Okla. 427, 1913 Okla. LEXIS 520
CourtSupreme Court of Oklahoma
DecidedSeptember 23, 1913
Docket2876
StatusPublished
Cited by17 cases

This text of 1913 OK 558 (Lamont Gas & Oil Co. v. Doop & Frater) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lamont Gas & Oil Co. v. Doop & Frater, 1913 OK 558, 135 P. 392, 39 Okla. 427, 1913 Okla. LEXIS 520 (Okla. 1913).

Opinion

Opinion by

SEIARP, C.

On the 20th day of December, 1909, in the district court of Grant county, Doop & Erater, a partnership, brought suit against the Lamont Gas & Oil Company, on account of an alleged indebtedness, due said partnership, arising out of a contract to drill two oil or gas wells for the defendant company. Plaintiff’s petition alleged that there was due it the sum of $1,078.75 for drilling and $1,064 for reaming a well by it drilled under said contract, and an additional cash bonus of $300, or a total of $2,442.75. The drilling contract relied upon by plaintiff was in writing, and a copy thereof is attached to plaintiff’s petition, and made a part thereof. The provisions of the contract bearing upon the controversy between the parties are as follows:

“That in consideration of one dollar and twenty-five cents ($1.25) per lineal foot, the parties of the second part agree to drill two wells for gas or oil for the party of the first part, to a depth of eight hundred and fifty (850) feet unless sooner stopped by party of the first part. In event that the said party of the first part should stop drilling before a depth of six hundred and fifty (650) feet is reached, as a result of striking gas or oil, then said party of the first part agrees to pay said party of the second part one dollar and twenty-five cents ($1.25) per lineal foot to the depth of six hundred and fifty (650) feet, termed in that event, the completion of the well. It is agreed that the said second party shall use all due diligence and care to enter all gas sand in as dry condition as possible.
“Should it be necessary, and possible, to drill said well deeper than eight hundred fifty (850) feet, said parties of the second part agree to drill the same deeper at the same price per lineal foot as herein before mentioned, to such depth as is deemed satisfactory to said party of the first part, or to water.”
*429 “Advances.
“Said party of the first part agrees to pay the said parties of the second part the sum of seventy-five (75) dollars when drilling rig is in position ready to begin work, at each of said wells, same to be deducted from the cost of well when final settlement is made and parties, of the- first part to furnish fuel for said wells, this also to be deducted when final settlement is made.”
“Payment.
“All money shall be due and payable on this contract for drilling and completing said wells, when each well is turned over to and accepted by said party of the first part, less such sums as have been advanced. In case of only one well drilled then party of the first part agrees to pay party of the second part a cash bonus of three hundred (300) dollars.”
“Reaming.
“Said party of the first part to pay for all reaming necessary at twenty-five ($25.00) per day, labor of 24 hrs. for two (2) men.”

Defendant’s answer denies any liability to plaintiff, on account of the latter’s failure to comply with the terms of said written contract, and asked judgment in the sum of $1,000 damages, caused by plaintiff’s breach of said contract. The trial resulted in a verdict in favor of plaintiff in the sum of $1,392.50.

Considering the assignments of error in the order presented in the brief of counsel for plaintiff in error, we shall first consider the paragraphs of the court’s charge complained of. Construing the drilling contract, the court gave the jury the following charge:

“You are instructed, gentlemen of the jury, that under and by virtue of the contract entered into by and between the plaintiff and the defendant all money was due and payable under said contract for drilling and completing said well when said well was turned over to and accepted by the party of the first part — that is to say, the defendant in this case — less such sums as had been advanced, but in this regard you are instructed as a matter of *430 law that if you find from a preponderance of the evidence that the plaintiff dug or sunk said well to the depth of 850 feet, said well, under and by virtue of the terms of the contract was completed, and the amount due for the construction of said well, including the amount due for necessary reaming, was then and there payable, and an arbitrary refusal upon the part of the defendant to accept said well could not avail the defendant in this case.”

It is not denied but that plaintiff had drilled said well to a depth of 863 feet. The court’s charge told the jury that if said well had been drilled to a depth of 850 feet, then under and by virtue of the terms of the contract it was completed, and that both the amount due for drilling and necessary reaming was then and there payable. Obviously this was error, as the contract provided that, should it be necessary and possible to drill said well deeper than 850 feet, the plaintiff should do so, to such a depth as was deemed satisfactory to said party of the first part, or to water, and at the same price per lineal foot as thereinbefore provided. The court’s charge does not take into consideration the latter part of the first provision of the contract, hereinbefore set out. Nor does it consider the further provision of said contract, providing that all money shall be due and payable on said drilling contract when each well is turned over to and accepted by said party of the first part, less such sums as have been advanced under authority of another provision. It is not contended that the well drilled was at any time accepted by .defendant, but that on the other hand, acting through its officers, it at all times demanded of plaintiff that it drill said well to a greater depth, as it had agreed and undertaken to do. No oil or gas had been found when the depth of 863 feet was reached. It does not appear that further. drilling was impossible, so that, if the prospecting for oil and gas was to be continued further, as was the purpose of the contract, it was necessary to drill the well deeper. It was doubtless this very thought that prompted the parties to expressly provide for the continuation of the drilling until either the owner of the well was satisfied, or water was reached, and for which further drilling additional consideration was provided. No payment, other than $75 and the cost of fuel, was to be paid until *431 the well being drilled was turned over to and accepted by the company. This included, not only the cost of drilling, but the incidental work of reaming as well.

In construing a contract the intention of the parties must be deducted from the entire agreement, and not from any part or parts thereof, because where a contract has several stipulations, it is plain that the parties agreed that their intention was not expressed by any single part or stipulation of it, but by every part and provision in. it, considered together, and so construed as to be consistent with every other part. Kansas City Bridge Co. v. Lindsay Bridge Co., 32 Okla. 31, 121 Pac. 639.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cities Service Oil Co. v. Geolograph Co., Inc.
1953 OK 69 (Supreme Court of Oklahoma, 1953)
Cities Service Gas Co. v. Kelly-Dempsey & Co.
27 F. Supp. 547 (N.D. Oklahoma, 1939)
Phoenix Oil Co. v. Mid-Continent Petroleum Corp.
1936 OK 250 (Supreme Court of Oklahoma, 1936)
Continental Supply Co. v. Levy
1926 OK 449 (Supreme Court of Oklahoma, 1926)
Cooksey v. Cooksey
1922 OK 95 (Supreme Court of Oklahoma, 1922)
Gross v. Lincoln
1921 OK 110 (Supreme Court of Oklahoma, 1921)
Ludeman v. English
1920 OK 183 (Supreme Court of Oklahoma, 1920)
Prowant v. Sealy
1919 OK 304 (Supreme Court of Oklahoma, 1919)
Drumright v. Brown
1919 OK 214 (Supreme Court of Oklahoma, 1919)
Creek Coal Mining Co. v. Paprotta
1918 OK 394 (Supreme Court of Oklahoma, 1918)
Gem Oil Co. v. Callendar
1918 OK 269 (Supreme Court of Oklahoma, 1918)
Withington v. Gypsy Oil Co.
1918 OK 236 (Supreme Court of Oklahoma, 1918)
Ford v. Perry
1917 OK 465 (Supreme Court of Oklahoma, 1917)
Hess v. Sturdavent
1916 OK 712 (Supreme Court of Oklahoma, 1916)
North Healdton Oil & Gas Co. v. Skelley
1916 OK 659 (Supreme Court of Oklahoma, 1916)
Brown v. Coppadge
1915 OK 1064 (Supreme Court of Oklahoma, 1915)
Gault v. Thurmond
1913 OK 654 (Supreme Court of Oklahoma, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
1913 OK 558, 135 P. 392, 39 Okla. 427, 1913 Okla. LEXIS 520, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lamont-gas-oil-co-v-doop-frater-okla-1913.