Wheeling Mold & Foundry Co. v. Wheeling Steel & Iron Co.

51 S.E. 129, 58 W. Va. 62, 1905 W. Va. LEXIS 80
West Virginia Supreme Court·Decided May 27, 1905·Published·Cited by 9 cases

Opinion

Cox, Judge:

By a contract in writing bearing date the 16th day of September, 1901, entered into by and between the Wheeling Steel and Iron Company, designated therein as the “owner,” and the Wheeling Mold and Foundry Company, designated therein as the “contractor,” the latter Company was to manufacture and deliver to the former Company, certain Pipe Mill Machinery. The contract recited that the contractor had full knowledge of the owner’s requirements in regard to the machinery, and full knowledge that the building of the machinery was to be begun forthwith and that it was necessary that it should be delivered at Benwood, West Virginia, on or before noon of January 14, 1902. Among other things, the contract provided, in effect, that the contractor should not further engage its capacity so as to militate against the manufacture and delivery of the machinery at Benwood, West Virginia, by noon of January 14, 1902; that neither party should be liable to the other in damages for delays due to wars, strikes, fires or accidents beyond their control; that, in case of delay from any of said causes, a certificate for time lost should be required; that all drawings furnished the contractor should remain the property of the owner and be returned to it on completion of the work; that the owner should furnish certain materials including motors to be used in, and in connection with the manufacture of the machinery to be manufactured and delivered by the contractor; that all foundations should be prepared by the owner; that in consideration of the faithful carrying out of said contract, together with all its various stipulations, and the delivery of the machinery at Benwood, West Virginia, by noon of January 14, 1902, the owner should pay the contractor $58,526.00; that if the machinery should be delivered before the date specified, fifty dollars per day should be added to the contract price for each day of twenty-four hours that the machinery should be delivered before the date specified; that in case of delay, fifty dollars for each day of twenty-four hours required to complete and deliver the machinery beyond the time specified, should be deducted from the contract price; that payment of eighty per cent, should be made on monthly estimates until such payments aggregated the sum of $46,820.00; that the remaining twenty per cent, should be [64] payable thirty days after the complete erection and acceptance of the machinery.

On the 15th day of April, 1903, this action of assumpsit was brought by the Wheeling Mold and Foundry Company against the Wheeling Steel and Iron Company. $46,825.03, having been paid or credited, the plaintiff claimed the residue of the contract price and, in addition, the amount of certain “extras,” not disputed by defendant. A trial by jury was had resulting in a verdict for plaintiff for $12,298.93, being the residue of the contract price without interest and the amount of the “extras” not disputed. Defendant moved to set aside the verdict, which motion was overruled and judgment was entered on the verdict, and defendant excepted and was afterwards allowed a writ of error to the judgment.

The assignments of error by defendant are numerous. They may, however, be grouped under four heads: First: The rejection of defendant’s notice of recoupment. Second: The admission and rejection of evidence. Third: The giving and refusing of instructions to the jury. Fourth: The sufficiency of the evidence to support the verdict,

First, the rejection of defendant’s notice of recoupment.

The notice of recoupment proceeded on the theoi-y that defendant might recoup damages for delay in excess of the fifty dollars per day provided by the contract. At the instance of defendant and without objection, the court instructed the jury, in effect, that the contract did not impose a penalty or forfeiture. The fifty dollars per day for delay to be deducted from the contract price, was in the nature of liquidated damages, and by the amount thereof fixed by the contract, the defendant was bound in an action at law, to recover from it the contract price. Welch v. McDonald, 85 Va. 500. See 19 Am. & Eng. Enc. Law. 422, 412 and 413; Pettis v. Bloomer, 21 How. Pr. 317; Texas &c. Ry. Co. v. Rust, 19 Fed. 239; Kunkle v. Wherry, 189 Pa. St, 198; Button Fastening Co.v. Breed, 163 Mass. 10; McPhee v. Wilson, 25 U. C. Q. B., 169; Smith v. Smith, 4 Wend. 468; Malone v. Philadelphia, 147 Pa. St. 416, Streeper v. William, 48 Pa. 450; Sedgwick on Damages (8th Ed.) sections 403 and 419; Crane v. Peer, 43 N. J. Eq. 553; 13 Cyc. 98. Defendant was not prejudiced by the rejection of its notice of recoupment.

[65] Second, the admission and rejection of evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Wheeling Mold & Foundry Co. v. Wheeling Steel & Iron Co., 51 S.E. 129, 58 W. Va. 62, 1905 W. Va. LEXIS 80 (W. Va. 1905).

51 S.E. 129 (Wheeling Mold & Foundry Co. v. Wheeling Steel & Iron Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Earl T. Browder, Inc. v. County Court of Webster County
102 S.E.2d 425 (West Virginia Supreme Court, 1958)
Pittsonberger v. Andrews
166 S.E. 367 (West Virginia Supreme Court, 1932)
Allen v. Simmons
125 S.E. 86 (West Virginia Supreme Court, 1924)
Parke v. Pence Springs Co.
118 S.E. 508 (West Virginia Supreme Court, 1923)
Caldwell & Drake v. Schmulbach
175 F. 429 (N.D. West Virginia, 1909)
McCormick v. Jordon
63 S.E. 778 (West Virginia Supreme Court, 1909)
Charleston Lumber Co. v. Friedman
61 S.E. 815 (West Virginia Supreme Court, 1908)
John v. Elkins
59 S.E. 961 (West Virginia Supreme Court, 1907)
Wheeling Mold & Foundry Co. v. Wheeling Steel & Iron Co.
57 S.E. 826 (West Virginia Supreme Court, 1907)