Wheeling Mold & Foundry Co. v. Wheeling Steel & Iron Co.

51 S.E. 129, 58 W. Va. 62, 1905 W. Va. LEXIS 80
CourtWest Virginia Supreme Court
DecidedMay 27, 1905
StatusPublished
Cited by9 cases

This text of 51 S.E. 129 (Wheeling Mold & Foundry Co. v. Wheeling Steel & Iron Co.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wheeling Mold & Foundry Co. v. Wheeling Steel & Iron Co., 51 S.E. 129, 58 W. Va. 62, 1905 W. Va. LEXIS 80 (W. Va. 1905).

Opinion

Cox, Judge:

By a contract in writing bearing date the 16th day of September, 1901, entered into by and between the Wheeling Steel and Iron Company, designated therein as the “owner,” and the Wheeling Mold and Foundry Company, designated therein as the “contractor,” the latter Company was to manufacture and deliver to the former Company, certain Pipe Mill Machinery. The contract recited that the contractor had full knowledge of the owner’s requirements in regard to the machinery, and full knowledge that the building of the machinery was to be begun forthwith and that it was necessary that it should be delivered at Benwood, West Virginia, on or before noon of January 14, 1902. Among other things, the contract provided, in effect, that the contractor should not further engage its capacity so as to militate against the manufacture and delivery of the machinery at Benwood, West Virginia, by noon of January 14, 1902; that neither party should be liable to the other in damages for delays due to wars, strikes, fires or accidents beyond their control; that, in case of delay from any of said causes, a certificate for time lost should be required; that all drawings furnished the contractor should remain the property of the owner and be returned to it on completion of the work; that the owner should furnish certain materials including motors to be used in, and in connection with the manufacture of the machinery to be manufactured and delivered by the contractor; that all foundations should be prepared by the owner; that in consideration of the faithful carrying out of said contract, together with all its various stipulations, and the delivery of the machinery at Benwood, West Virginia, by noon of January 14, 1902, the owner should pay the contractor $58,526.00; that if the machinery should be delivered before the date specified, fifty dollars per day should be added to the contract price for each day of twenty-four hours that the machinery should be delivered before the date specified; that in case of delay, fifty dollars for each day of twenty-four hours required to complete and deliver the machinery beyond the time specified, should be deducted from the contract price; that payment of eighty per cent, should be made on monthly estimates until such payments aggregated the sum of $46,820.00; that the remaining twenty per cent, should be [64]*64payable thirty days after the complete erection and acceptance of the machinery.

On the 15th day of April, 1903, this action of assumpsit was brought by the Wheeling Mold and Foundry Company against the Wheeling Steel and Iron Company. $46,825.03, having been paid or credited, the plaintiff claimed the residue of the contract price and, in addition, the amount of certain “extras,” not disputed by defendant. A trial by jury was had resulting in a verdict for plaintiff for $12,298.93, being the residue of the contract price without interest and the amount of the “extras” not disputed. Defendant moved to set aside the verdict, which motion was overruled and judgment was entered on the verdict, and defendant excepted and was afterwards allowed a writ of error to the judgment.

The assignments of error by defendant are numerous. They may, however, be grouped under four heads: First: The rejection of defendant’s notice of recoupment. Second: The admission and rejection of evidence. Third: The giving and refusing of instructions to the jury. Fourth: The sufficiency of the evidence to support the verdict,

First, the rejection of defendant’s notice of recoupment.

The notice of recoupment proceeded on the theoi-y that defendant might recoup damages for delay in excess of the fifty dollars per day provided by the contract. At the instance of defendant and without objection, the court instructed the jury, in effect, that the contract did not impose a penalty or forfeiture. The fifty dollars per day for delay to be deducted from the contract price, was in the nature of liquidated damages, and by the amount thereof fixed by the contract, the defendant was bound in an action at law, to recover from it the contract price. Welch v. McDonald, 85 Va. 500. See 19 Am. & Eng. Enc. Law. 422, 412 and 413; Pettis v. Bloomer, 21 How. Pr. 317; Texas &c. Ry. Co. v. Rust, 19 Fed. 239; Kunkle v. Wherry, 189 Pa. St, 198; Button Fastening Co.v. Breed, 163 Mass. 10; McPhee v. Wilson, 25 U. C. Q. B., 169; Smith v. Smith, 4 Wend. 468; Malone v. Philadelphia, 147 Pa. St. 416, Streeper v. William, 48 Pa. 450; Sedgwick on Damages (8th Ed.) sections 403 and 419; Crane v. Peer, 43 N. J. Eq. 553; 13 Cyc. 98. Defendant was not prejudiced by the rejection of its notice of recoupment.

[65]*65Second, the admission and rejection of evidence.

Defendant complains of certain general evidence admitted over its objection. This evidence was principally adduced from witness Blue, president of plaintiff Company, and witness Long, plaintiff’s engineer. This evidence was to the effect that plaintiff was diligent generally in the performance of its contract. The evidence consisted of many expressions by the witnesses for the plaintiff, such as the following: We “made as many castings as we could and did as much machine work on them as we could. We did as much, I believe, as anybody could.” “We went ahead with the work just as hard as we could.” “We performed the contract to the best of our ability in regard to the way material came to us.” “Why, it did everything in its power to carry out the contract. That is, in my opinion.” “We completed the machine work with all possible speed.” “We attempted to push the work as best possible.” “No sir, the Company did everything in their power to expedite matters,” and the like. These conclusions or opinions were allowed to go to the jury. We will consider this general evidence in the light of Instruction No. 3, given at the instance of the plaintiff, which is as follows: “If the jury find from the evidence that after the making of the written agreement which has been introduced in evidence, the plans mentioned in the said agreement were changed with the consent of both the plaintiff and the defendant, and if they further find that these changes made it impracticable for the work provided for in the said agreement, to be completed within the time specified in the said agreement, and if they further find from the evidence that the plaintiff the Wheeling Mold and Foundry Company, proceeded in good faith and with due diligence and with the use of all means in its power and at its command to proceed with and complete the work provided for in said agreement, and that any delays which may have taken place in the completion of the said work were not due to any neglect or default upon the part of the plaintiff, then the plaintiff is entitled to recover in this action the amount remaining due and unpaid of the contract price provided for in the said agreement without any deduction therefrom by reason or on account of such delay in the completion of the said work.” The clause of the instruction to which we direct special attention is sub[66]*66stantially, that if the plaintiff proceeded in good faith and with due diligence with the use of all means in its power and at its command, to complete the work provided for by the contract, the plaintiff was not liable for the delays occurring, but was entitled to the contract price without deduction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Earl T. Browder, Inc. v. County Court of Webster County
102 S.E.2d 425 (West Virginia Supreme Court, 1958)
Pittsonberger v. Andrews
166 S.E. 367 (West Virginia Supreme Court, 1932)
Allen v. Simmons
125 S.E. 86 (West Virginia Supreme Court, 1924)
Parke v. Pence Springs Co.
118 S.E. 508 (West Virginia Supreme Court, 1923)
Caldwell & Drake v. Schmulbach
175 F. 429 (N.D. West Virginia, 1909)
McCormick v. Jordon
63 S.E. 778 (West Virginia Supreme Court, 1909)
Charleston Lumber Co. v. Friedman
61 S.E. 815 (West Virginia Supreme Court, 1908)
John v. Elkins
59 S.E. 961 (West Virginia Supreme Court, 1907)
Wheeling Mold & Foundry Co. v. Wheeling Steel & Iron Co.
57 S.E. 826 (West Virginia Supreme Court, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
51 S.E. 129, 58 W. Va. 62, 1905 W. Va. LEXIS 80, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wheeling-mold-foundry-co-v-wheeling-steel-iron-co-wva-1905.