Shouse v. Neiswaanger

18 Mo. App. 236, 1885 Mo. App. LEXIS 326
CourtMissouri Court of Appeals
DecidedJune 8, 1885
StatusPublished
Cited by9 cases

This text of 18 Mo. App. 236 (Shouse v. Neiswaanger) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shouse v. Neiswaanger, 18 Mo. App. 236, 1885 Mo. App. LEXIS 326 (Mo. Ct. App. 1885).

Opinion

Opinion by

Philips, P. J.

There are two questions presented by. this appeal which are of controlling importance. They are, first, admitting the truth of defendants’ evidence, were they entitled to recoup any damages for the failure of plaintiff to deliver the lumber at the time agreed upon; and second, were they entitled to recover more than nominal damages ?

1. It is conceded, in argument by plaintiff’s counsel, that there was evidence tending to show that plaintiff agreed to furnish the lumber on or about the 15th of October, 1879. It is also conceded by the instruction, that if plaintiff made default in delivering the joists at the time stipulated, it constituted a breach of his contract; but that the damages would be merely nominal.

If the plaintiff had contracted with defendants for the delivery of this lumber at a given time and place, without any knowledge on his part of the purpose or use for which it was contracted, the rule of law is well settled, that for the breach of such contract on the part of plaintiff, the vendor, the measure of damages would be the difference between the contract price and the market value of such lumber at the time and place of delivery according to the contract.

But the real question at bar is, did not the plaintiff have notice that this lumber was designed for a special purpose % Aside from the other evidence in this record, strongly tending to show that plaintiff must have known the particular fact, the mechanic’s lien filed by plaintiff, and read in evidence by him, shows that he knew at the time of entering into the contract that it was to be used by defendants in erecting this particular building on their lot. By the very provisions of the lien law, under the statute, it is made essential to the establishment of [244]*244the lien that plaintiff should have furnished the material under a contract with these defendants for this purpose. His affidavit to the account filed confesses that he so contracted and furnished the lumber. Superadded to which, the evidence on the part of the defendants was such as might reasonably warrant any jury in making the inference that plaintiff was advised of the specific object for which this lumber was contracted. Its-peculiar and limited quality and character, and the anxiety manifested by defendants in their interviews with plaintiff concerning it, were such as to have impressed any reasonable person with the fact that the building was in process of erection, and the emergency for the prompt delivery of the lumber was great.

Under such a state of the proof we think the court improperly limited the inquiry as to damages.

2-. Sutherland on Damages, vol. 1, p. 397, et seq., expresses the general doctrine on this subject thus: “When goods, or those of a particular description, are bargained for, for a special purpose, or for delivery at a particular time and place, in view of ulterior contracts or preparations, a failure of the vendor to perform may cause injury which would not be compensated by that rule (i. e., the difference between the contract price and market value); but unless that purpose, or the special circumstances from which, in case of default, such consequential damages would proceed, were communicated to' the seller when the bargain was made, such damages, though they may arise naturally and proximately from the breach of the contract, are yet exceptional, and cannot be said to have entered into the' contemplation of the parties. But if, at the time of contracting, sufficient notice be given of the intended use, or of other and dependent plans, the vendor, on failure to deliver, or delaying* delivery, will be subject to such damages. This rule is based upon reason and good sense, and is in a strict accordance with the plainest principles of justice. It affirms nothing more than where a party sustains a loss by reason of a breach of contract, he shall, so far as money can do it, be placed in as good a [245]*245situation, by recovery of damages, as if the contract had been performed.”

The leading case on this subject, to which all the courts refer for a reasonable rule, is that of Halley v. Boxendale (9 Exch. 341 S. C. 26 Eng. L. & Eq. 398), in which Baron Alderson said: ‘ ‘ Where two parties have made a contract, which one of them has broken, the damages which the other party ought to receive in respect of such breach of. contract, should be such as may be fairly and reasonably considered, either arising naturally, i. e., according to the usual course of things, from such breach of contract itself, or such as may be reasonably supposed to have been in the contemplation of both parties, at the time they made the contract, as the probable breach of it. Now, if the special circumstances under which the contract was actually made were communicated by the plaintiff to the defendant, and thus known to both parties, the damages resulting from the breach of such a contract, which they would reasonably contemplate would be the amount of the injury which would ordinarily follow from a breach of the contract under these circumstances. so known and communicated. But, on the other hand, if these special circumstances were wholly unknown to the party breaking the contract, he could only be supposed to have had in contemplation the amount of the injury which would arise generally, etc.”

The trouble arises in making a practical application of the rule to the varying state of facts and circumstances of each particular case. The weakness of the defendants’ case, as presented in the bill of exceptions, lies principally in the matter of carrying home to plaintiff special knowledge of the facts attending the situation of the building and the work in progress thereon.

3. As already stated, the knowledge which the plaintiff had at the time of making the contract, was that the lumber was designed for this particular building then in process of construction. It might be reasonably inferred, from the character of the lumber ordered, that it was to form a support for the floor, and was indis[246]*246pensable to the completion of the structure. And,, further, that there was some emergency for its timely delivery. The plaintiff is, therefore, only liable for such damages as might reasonably have been anticipated would likely result, according to the usual course of things, from his failure to comply, or such as may reasonably be supposed to have been within the reasonable contemplation of the parties.

We are of the opinion that the evidence in this case is-such as to make plaintiff liable for the loss of the use of the building during the time its completion was delayed by the failure of plaintiff to deliver the lumber according to contract. Such damages are natural and reasonable, and such as any reasonable person might well anticipate-to be likely to result from such delay.

In Brown v. Foster (51 Pa. St. 174-5), a party failed to complete a steamboat within the time promised. The measure of damages was held to be, not what it would cost the party to hire another boat for the time, but what would be the ordinary hire of such a boat during the time.

In Ruff v. Rinaldo (55 N. Y. 664), it is held that the measure of damages for the breach of a contractor’s-stipulation to build in given time, is the value of the use of the building while the owner is deprived of the use consequent upon the delay.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Minneapolis Threshing MacHine Co. v. Bradford
227 S.W. 628 (Missouri Court of Appeals, 1921)
Wilt v. Hammond
165 S.W. 362 (Missouri Court of Appeals, 1914)
Wheeling Mold & Foundry Co. v. Wheeling Steel & Iron Co.
51 S.E. 129 (West Virginia Supreme Court, 1905)
Wall v. St. Joseph Artesian Ice & Cold Storage Co.
87 S.W. 574 (Missouri Court of Appeals, 1905)
W. F. Wilson & Son v. Russler
91 Mo. App. 275 (Missouri Court of Appeals, 1902)
Cochran v. People's Railway Co.
33 S.W. 177 (Supreme Court of Missouri, 1895)
Wright v. Fullerton
60 Mo. App. 451 (Missouri Court of Appeals, 1895)
Dengler v. Auer
55 Mo. App. 548 (Missouri Court of Appeals, 1893)
McConey v. Wallace
22 Mo. App. 377 (Missouri Court of Appeals, 1886)

Cite This Page — Counsel Stack

Bluebook (online)
18 Mo. App. 236, 1885 Mo. App. LEXIS 326, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shouse-v-neiswaanger-moctapp-1885.